Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Pricing curtain-wall embedded parts and post-installed anchors: separate-listing judgment, pricing composition, and anchor compliance constraints

The BOQ work content stating "including embedded parts" ≠ already priced; whether to list separately depends on whether the quota consumption includes embedded parts; most curtain-wall items do not, so embedded parts must be listed separately (per t with embedded-iron installation items; channel-type embedded parts of unitized curtain walls per count, T-type transfer bolts per set). Post-installed anchors = anchor plates per t + anchors per set + installation labor + pull-out test fees counted separately. Anchors must be chemical/undercut anchors (expansion bolts prohibited), diameter >=10 mm, >=2 per embedded part; where welding is needed, choose mechanical undercut or inverted-cone chemical anchors.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
  • DB11/T 2382-2024 建设工程施工消耗量标准
  • DB11/T 1832.11-2022 建筑工程施工工艺规程 第11部分:幕墙工程
  • DBJ61/T 161-2019 建筑幕墙工程技术标准
  • DB11 512-2017 建筑装饰工程石材应用技术规程

Topic Positioning

The pricing method for curtain-wall embedded parts and post-installed anchors (anchors + plates): how to judge by BOQ and quota calibers, the pricing composition, measurement units, and the anchor-selection compliance constraints.

Core Conclusions

  1. The BOQ work content stating "framework including embedded parts" or "embedded part fabrication and installation" does not mean already priced; whether to list separately depends on whether the curtain-wall item consumption of the quota in use includes embedded parts — most curtain-wall items do not, so they must be listed separately.
  2. Separate-listing calibers (measured across four systems): Beijing DB11/T 2382-2024 prices embedded irons per t with installation items (labor + irons + arc welding); the railway TB/T 10831-2024 volume explanation states "embedded irons execute the corresponding items of the concrete and reinforced-concrete works section", measured by mass in t; Shaanxi/Hunan set special items for unitized curtain walls — channel-type embedded parts per count, T-type transfer bolts per set.
  3. Post-installed anchor pricing = anchor plate material cost (per t, with embedded-iron type items) + anchor material cost (per set, market prices of chemical/undercut anchors) + drilling, injection, and tightening labor + on-site pull-out test fees (counted separately).
  4. Compliance constraints (affecting pricing content): expansion-type bolts prohibited; anchor diameter >=10 mm, >=2 anchors per plate; embedded parts to be welded after positioning shall use mechanical undercut or special inverted-cone chemical anchors; embedded parts where chemical anchors exceed half must not be welded; anchor tensile-performance re-inspection and on-site load-bearing tests are counted separately.
  5. Common errors: listing separately when the quota already includes embedded parts = double charging (check the consumption first); curtain-wall lightning down-conductors computed separately; embedded parts per t, anchors per set, channel-type embedded parts per count — different units listed separately; take off quantities point by point per the developed subdivision drawings, never estimate by curtain-wall area.

Applicable Boundaries

Applies to pricing, pricing audit, and settlement disputes of stick/unitized/stone curtain walls; quota systems differ in caliber (Beijing/railway/local) — before use, verify whether the curtain-wall item consumption of that system includes embedded parts; this card covers pricing methods and compliance constraints only, with no specific price data.

Further Reading

GB/T 50854-2024 Appendix M Table M.6.1 (curtain wall works 011206); TB/T 10831-2024 Volume 10 volume explanation, "wall/column face works" section; DB11/T 2382-2024 Appendix A (embedded irons); DB11/T 1832.11-2022 Clause 3.1.4 (post-installed anchors); DBJ61/T 161-2019 Clause 8.5.7 (anchor diameter/quantity/testing); DB11 512-2017 Clause 8.2.6 (cross arrangement and welding restrictions of stone curtain walls).

Keywords

  • 幕墙
  • 预埋件
  • 后置埋件
  • 预埋铁件
  • 化学锚栓
  • 扩底锚栓
  • 埋件计价
  • 幕墙定额

Cited By