Railway bridge and culvert quota foundation excavation and pit pumping: excavation excludes pumping; pumping measured per wet-soil/pit volume with inflow-rate steps (TB/T 10823-2024, Volume 2)

In TB/T 10823-2024 "Railway works budget quota, Volume 2: bridge and culvert works", the excavation items (QY-1~23) have the work content "excavate and haul 10 m beyond the pit, including manual digging and hauling of the soil within 0.3 m of the pit bottom, and trimming of pit walls and bottom" — pumping is not included and must use the separate pit-pumping items. Pit pumping QY-35~37 is measured per "10 m3 of wet soil" (wet soil = the volume excavated below the standing groundwater table), stepped by design inflow rate (weak flow <=15, medium flow <=40, strong flow <=60 m3/h); QY-38 pumping of static water is per the designed pumped volume (applicable only to removing ponded water from ponds and pools). Where wellpoint dewatering is used, the excavation is always treated as water-free — no double counting with wet excavation or pit pumping; inflow rates above 60 m3/h have no step and must be separately assessed.

Applicable Codes

  • TB/T 10823-2024 · Budget Quota of Railway Engineering (Volume 2: Bridge and Culvert Works) Ch. 1 下部工程 第一节 挖基及抽水

Topic Positioning

Interpretation of the pricing rules of "Section 1, excavation and pumping" in Chapter 1 (substructure works) of the railway 2024 bridge-and-culvert budget quota (TB/T 10823-2024 Volume 2): whether the excavation items themselves include pumping, by what the pit-pumping items are measured, and when pumping may be booked. For compiling budgets/BOQs for open-cut foundations and pile caps of railway bridges.

Core Conclusions

  1. Excavation itself excludes pumping. The excavation items (mechanical QY-1~7, manual QY-8~17, blasting QY-18~23) all have the work content "excavate and haul 10 m beyond the pit, including manual digging and hauling of the soil within 0.3 m of the pit bottom, and trimming of pit walls and bottom"; the consumptions include only labor, other material costs, and excavator shifts — no pumps or drainage costs; pumping must be booked separately under the pit-pumping items.
  2. "Wet/dry" does not mean with/without pumping. The volume notes state: "dry excavation means excavation above the groundwater table; wet excavation means excavation below the groundwater table." The "wet" items (e.g., QY-2, QY-4/5) reflect only the reduced efficiency of digging wet soil and carry higher base prices — they do not include pumping; the "without/with sheeting" of QY-4/5 refers to pit-wall sheeting and boarding, unrelated to pumping.
  3. Measurement of the pit-pumping items. The four items (QY-35~38) have the work content "dig pumping sumps, pump, dig drainage ditches" — sump digging and ditches are included, not booked separately:
    • QY-35 weak flow <=15 m3/h, QY-36 medium flow <=40 m3/h, QY-37 strong flow <=60 m3/h: unit 10 m3 wet soil, wet-soil volume being the excavation volume below the standing groundwater table (consistent with the subgrade volume's caliber that "blind-drain and pipe-trench excavation pumping is measured by the wet-soil excavation volume below the standing groundwater table"), stepped and selected per the design inflow rate of the work point;
    • QY-38 pumping static water: unit 10 m3, quantity per the designed pumped volume (volume note: static-water pumping applies only to removing ponded water from ponds and pools).
  4. Booking conditions: (1) where groundwater gushes and continuous pumping is needed, select QY-35/36/37 by the design inflow rate; where the rate exceeds 60 m3/h the quota has no step — a supplementary assessment is required, not a forced fit. (2) A dry pit books no pumping item; where inflow is slight and only pit water accumulates, use QY-38 static-water pumping. (3) Where wellpoint dewatering is adopted, the dewatering cost is booked separately (wellpoint installation/removal and dewatering per "set-day"), and the excavation after dewatering is always treated as "dry" — no booking of wellpoint dewatering together with wet excavation and pit pumping; where porous-concrete tube wells are used for dewatering, the pump cost is booked separately (1 pump per well, sized per the design inflow rate).
  5. Other exclusions: the excavation items exclude pit-wall support (sheeting and boarding, reinforced-concrete ring walls, steel sheet piles, etc. per their own items; anchors/shotcrete/soil nails per the relevant items of Volume 1 subgrade); spoil haul for pit excavation is 10 m, longer haul per the Volume 1 subgrade items.

Applicable Boundaries

  • Applies only to Section 1 "excavation and pumping" of Chapter 1 substructure works, TB/T 10823-2024 Volume 2 (bridge and culvert works); the dewatering calibers of Volume 1 subgrade and of municipal/building quotas differ — follow each quota's own rules.
  • Wet/dry and the pumping steps are judged by the standing groundwater table and the design inflow rate; when compiling, wet-soil quantities are the excavation volume below the standing groundwater table.
  • Wellpoint dewatering and open pumping are mutually exclusive: after wellpoint dewatering the excavation counts as dry and must not be double-counted.
  • Inflow rates >60 m3/h have no quota step and need supplementary assessment; this card carries no base prices — price by the companion fee quotas and the compilation-period price level.

Further Reading

  • TB/T 10823-2024 "Railway works budget quota, Volume 2: bridge and culvert works", Chapter 1 substructure works, "Section 1: excavation and pumping": volume notes (wet/dry definitions, pit-wall support, spoil haul, wellpoint dewatering, porous-concrete tube-well dewatering), mechanical excavation QY-1~7, pit pumping QY-35~38 (including the wellpoint items QY-31/32).
  • Longer spoil haul and pit-wall support (anchors/shotcrete/soil nails) per the relevant items of "Railway works budget quota, Volume 1: subgrade works".
  • Cross-references: selection of wellpoint systems and the "set-day" measurement rules are in the card "dewatering and drainage cost calculation for pipe/pit construction (wellpoint selection, set-day measurement, shift conversion)"; the red lines on non-adjustable quota consumptions are in the card "list of situations where quota consumptions must not be adjusted".

Keywords

  • TB/T 10823
  • 桥涵定额
  • 挖基
  • 基坑抽水
  • 湿土
  • 涌水量
  • 抽静水
  • 井点降水