Cost calculation of dewatering and drainage for pipeline/foundation-pit construction (wellpoint selection, set-day measurement, machine-shift conversion)
Dewatering and drainage are two separate pricing paths: wellpoint dewatering is charged by quota norms on a "set-day" basis (light wellpoints 50 wells/set, ejector wellpoints 30/set, large-diameter wellpoints 10/set; a fraction of a set counts as one set; one day = 24 h; installation and removal per well), cost = installation + removal + usage + separately charged items; open drainage is charged per the project execution plan (construction methodology and site organization) and site instructions / variation records. Selection: a dewatering depth of <= 6 m uses light wellpoints, 6~30 m ejector wellpoints, special cases large-diameter wellpoints; the design drawdown should be not less than 0.5 m below the pit bottom.
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准 第7.1.56条
- SJG 111.2-2022 城市地下综合管廊工程消耗量标准(Vol. 2)第8.1.5条、第8.2.4条
- SJG 84-2020 市政维修工程消耗量标准 第二册 第7.2.22条
- 京建发〔2021〕201号 北京市2021预算消耗量标准 房屋建筑与装饰工程(下册)第十六章 措施项目
- 湖南2025版市政工程消耗量标准 第四节 井点降水
- 陕西新编消耗量定额(征求意见稿)降排水工程量计算规则
- GB 50860-2013 构筑物工程工程量计算规范 Table C.5 施工排水、降水(code 070305)
- GB 50861-2013 城市轨道交通工程工程量计算规范 Table N.9 施工排水、降水(code 081309)
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 Ch. 1 土石方工程 四、施工支护、降排水(二)降排水(FY-87~FY-122)
- TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程 QY-31~32
- GB 50141-2008 给水排水构筑物工程施工及验收规范 第4.3.7条、第4.3.8条
- GB/T 50500-2024 建设工程工程量清单计价标准 第6.2.13条、App. ETable E.3.3、第7.4.4条、第8.9.4条
- T/YJXB 0001-2023 建设工程停工承包人费用计算标准 第2.0.11条、第5.0.10条
Topic Positioning
Cost calculation of dewatering and drainage for pipeline/foundation-pit construction: dewatering (wellpoints actively lowering the groundwater table, charged by quota norms on a "set-day" basis) and drainage (open drainage, sump pits + pumps, charged per the project execution plan (construction methodology and site organization) and site instructions / variation records) are two different pricing paths — distinguish them first, then apply quota items.
Core Conclusions
- Wellpoint selection (consistent across regions): a dewatering depth within 6 m uses light wellpoints (typical well spacing 1.2 m), 6 m to 30 m uses ejector wellpoints (about 2.5 m), special high-inflow conditions use large-diameter wellpoints (about 10 m), deep wells counted per "unit"; the design drawdown depth should be not less than 0.5 m below the pit bottom.
- Measurement rules: light wellpoints 50 wells = 1 set, ejector wellpoints 30 wells = 1 set, large-diameter wellpoints 10 wells = 1 set; usage is charged by "set-day", cumulative well counts falling short of one set count as one set, one day = 24 h; well installation and removal are counted per well, deep-well installation and removal per unit and usage per unit-day.
- Cost composition = installation cost + removal cost + usage cost, applying local current municipal consumption quota (resource norm) line items.
- Machine-shift conversion: where actual cumulative pump operation per day-night is under 4 h count 0.5 machine-shift, under 8 h count 1, under 16 h count 2, over 16 h count 3, to adjust machinery consumption.
- Easily missed separately charged items: hole-making slurry treatment and ditch excavation for drainage, water-level monitoring and data compilation fees, standby power fees, sand-backfill quantity differences for well pipes adjusted by site instruction / variation record; where natural water sources are available, water fees are not charged.
- Open drainage applicable to: pits (trenches) in firm soil with small permeability coefficient, low water table, small inflow, and dewatering depth within 5 m; the sump pit bottom should be below and not less than 1.2 m under the pit bottom, and the drainage ditch depth should be not less than 0.3 m.
Applicable Boundaries
- Wellpoint type and well spacing are general values, ultimately set by the project execution plan (construction methodology and site organization) per geology and dewatering requirements; specific line-item division and base prices follow the current local quota volumes — this card gives general rules only, no prices.
- Whether deep wells are usable and the staging ranges of ejector wellpoints are worded slightly differently in some local standards (e.g., Hunan 2025 allows large-diameter and deep wellpoints under special conditions) — the local quota notes govern.
Further Reading
- Wellpoint selection, well spacing, and machine-shift conversion: SJG 111.2-2022 "Consumption standard for urban utility tunnel works", Volume 2, Clause 8.1.5 dewatering and drainage line-item notes; Hunan 2025 municipal works consumption standard "wellpoint dewatering" notes and method of measurement (set division such as light wellpoints 50 wells/set).
- Wellpoint system construction and acceptance: GB 50141-2008 "Code for construction and acceptance of water and wastewater structures" Clause 4.3.8 (wellpoint selection conditions, borehole diameter = pipe OD + 2 x filter thickness, trial pumping, tolerance (permissible deviation)) and Clause 4.3.7 (open drainage method).
- Quota line-item references: TB/T 10831-2024 railway budget quota manual Volume 10 building works FY-87~122 dewatering line items; TB/T 10823-2024 Volume 2 bridge and culvert works QY-31~32 light wellpoints.