Monitoring during wellpoint dewatering operation and sand-content limits of pumped water (JGJ 111-2016 / GB 50296-2014 / GB 51004-2015)
During dewatering, monitor groundwater level, discharge, sand content, and the surrounding environment (DB11/T 1832.1-2021 Clause 31.7.8), and per GB 51004-2015 Clause 7.1.6 dynamically monitor level changes and deformation of surrounding ground and structures with informative construction. Sand-content limits have two regimes: (1) routine operational control (JGJ 111-2016 Clause 5.6.3): within half an hour of pumping, coarse sand < 1/50000, medium sand < 1/20000, fine sand < 1/10000; wellpoints in normal operation < 1/50000; radial wells < 1/20000 within half an hour and < 1/200000 in normal operation. (2) Well completion acceptance (GB 50296-2014 Clause 7.6.10, mandatory): measured before the pumping test ends - water-supply wells < 1/200000, dewatering wells < 1/100000 by volume ratio (acceptance stricter than operational control). Both are volume ratios (weight ratio is about twice the volume ratio).
Applicable Codes
- JGJ 111-2016 · Technical Code for Groundwater Control of Building and Municipal Engineering
- GB 50296-2014 · Technical Code for Water Supply Tube Wells
- GB 51004-2015 · Code for Construction of Building Foundation
- DB11/T 1832.1-2021 · Specification for Construction Technology of Building Works (Part 1: Foundation Works) (Beijing)
- DB37/T 5059-2016 · Technical Code for Groundwater Control of Engineering Construction (Shandong)
Topic Positioning
This card compiles what must be monitored during operation of wellpoint (and radial-well) dewatering works, the sand-content limits of pumped water (distinguishing "routine operational control" from "well completion acceptance"), monitoring frequency, and O&M requirements, based on JGJ 111-2016, GB 50296-2014, GB 51004-2015, DB11/T 1832.1-2021, and DB37/T 5059-2016.
Core Conclusions
I. Monitoring objects (four mandatory items): DB11/T 1832.1-2021 Clause 31.7.8: "During dewatering, the groundwater level, discharge, sand content, and surrounding environment shall be monitored." GB 51004-2015 Clause 7.1.6: "During dewatering, dynamic monitoring of groundwater level changes and deformation of surrounding ground and structures shall be carried out, with informative construction based on the data." Its commentary adds: dynamically monitor level, discharge, equipment status, and ground/structure settlement, analyzing the correlation between drawdown and ground settlement; for deep excavations dewatering confined water, automatic level monitoring inside and outside the pit is required.
II. Sand-content limits (two regimes - do not confuse): (1) Operational control of pumped water (JGJ 111-2016 Clause 5.6.3): within half an hour of pumping - coarse sand < 1/50000, medium sand < 1/20000, fine sand < 1/10000; wellpoints in normal operation < 1/50000; radial wells < 1/20000 within half an hour, < 1/200000 in normal operation. Commentary: dewatering-induced surface collapse mostly stems from improper or failed filter design around wells with soil loss through pumping - sand content is a key indicator of latent risk. (2) Well completion acceptance (GB 50296-2014 Clause 7.6.10, mandatory): "Before the end of the pumping test, the sand content of the pumped water shall be measured. For water-supply wells the volume ratio shall be below 1/200000; for dewatering wells below 1/100000." The acceptance value (1/100000) is stricter than the operational value (1/50000). Commentary: measure the stabilized value under steady discharge (the sand-content curve has peak, fluctuating, and stable values - the fluctuating value must not be used as the criterion); values are volume ratios, weight ratio is about twice the volume ratio - measure volumetrically on site (Imhoff cone), no weighing conversion needed; suspended solids (turbidity) is a different concept and must not be counted into sand content.
III. Frequency and O&M (JGJ 111-2016):
- Level (8.2.5): observe the static level before pumping and monitor well levels, readings to the centimeter with accuracy not below +/-2cm; twice daily until the design level is reached, then once daily after stabilization; increase frequency on power outages, pump failures, and during rain until levels stabilize.
- Discharge (8.3.1): frequency consistent with level observation; record quantity and flow characteristics.
- Sand content (DB37/T 5059-2016 8.3.7): set the frequency per project conditions, aquifer character, and surroundings (JGJ 111 does not fix a frequency).
- O&M (5.6.5): monitor level and inflow, report anomalies promptly; on pit outflow or sand boiling, immediately find the cause and act; wells, discharge pipes, and power facilities shall carry clear safety signage; check pumps and operation at least twice daily; act when the well level rises near the pit bottom to restore design drawdown; protect surface drainage networks from freezing in winter; switch power promptly on outage to keep dewatering going.
Applicable Boundaries
Applies to wellpoint and radial-well dewatering of building and municipal works (JGJ 111-2016 is the building-and-municipal groundwater-control code; DB11/T 1832.1-2021 the Beijing foundation-works procedure). Note the multiple sand-content regimes - GB 50296-2014 Clause 7.6.10's 1/100000 is the mandatory completion-acceptance value; JGJ 111-2016 Clause 5.6.3's 1/50000 is the routine operational value; both are volume ratios and must be used per occasion, not mixed; local standards may be looser or stricter - follow the project's current local standard in the plan. Sand content must be measured as the stabilized value under steady discharge; suspended solids are excluded.
Further Reading
- JGJ 111-2016: Clauses 5.6.3 (sand content), 5.6.5 (O&M), 8.2.5 (level monitoring), 8.3.1 (discharge monitoring).
- GB 50296-2014: Clause 7.6.10 (mandatory sand-content standard) and commentary (characteristic curve, volume vs weight ratio, Imhoff cone, suspended solids distinction).
- GB 51004-2015: Clause 7.1.6 (dynamic monitoring and informative construction).
- DB11/T 1832.1-2021: Clause 31.7.8 (monitoring objects during wellpoint dewatering).
- DB37/T 5059-2016: Clause 8.3.7 (principle for setting sand-content monitoring frequency).
Keywords
- 管井降水
- 含砂量
- 限值
- 降水监测
- 地下水位监测
- JGJ 111-2016
- GB 50296-2014
- GB 51004-2015
- 降水运行维护