TB/T 10826-2024 railway budget quota Volume 5 communication works: scope, application rules, and the separate booking of cable/pole/tower main materials
TB/T 10826-2024 Volume 5 applies to new and rebuilt (expanded) railway communication works, is the basis for design estimates (budgets), with implementation-stage prices market-determined. Key rules: (1) optical (copper) cables, leaky coaxial cables, poles, and towers are main materials — neither price nor weight is in the items' "unit price"/"weight"; book separately per the appendix "cross-table of items whose main materials are excluded from the base prices"; (2) installation items exclude equipment cost; (3) demolition books only labor and plant shifts (per demolition Table 1); (4) waste rates and turnover-material amortization per TB/T 10821-2024, and labor/material/plant prices per TB 10811-2024, TB/T 10813-2024, TB/T 10814-2024; (5) terrain in four classes (plain, relative relief <20 m; hills <80 m; mountains >80 m; urban), laying items split by terrain x fiber count and applied directly, with no extra factors.
Applicable Codes
- TB/T 10826-2024 铁路工程预算定额 Vol. 5 通信工程
- TB/T 10821-2024 铁路工程基本定额
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
- TB/T 10813-2024 铁路工程材料基期价格
- TB/T 10814-2024 铁路工程施工机具台班费用定额
- TB 10012 铁路工程地质勘察规范
- TZJ 2005 铁路工程预算定额 第五册 通信工程(旧版,已废止)
Topic Positioning
The scope and application rules of TB/T 10826-2024 Volume 5 (2024 system, revised from the old TZJ 2005 communication quotas): what is booked separately (cable/pole/tower main materials, equipment, bracketed materials, HT-0 concrete), what is selected directly by stepped items (terrain, fiber count, ground), and what takes factors (demolition) — for compiling and auditing railway communication estimates (budgets).
Core Conclusions
Scope. General notes: applies to new and rebuilt railway works, is the basis for design estimates (budgets); implementation-stage prices market-determined; 13 volumes, communication being Volume 5. Volume notes: applies to new and rebuilt (expanded) railway communication works. 22 chapters: trenches and ducts; cable laying; jointing and testing; protection; branch devices and terminations; pole lines; towers; lightning protection; racks/trays and reinforcing facilities; cabinets (racks) and cabling; transmission and access networks; data networks; telephone exchange; wired dispatch; digital mobile; video conferencing; video surveillance; emergency communication; clock and time synchronization; power; monitoring and maintenance; other private radio.
Separate booking / factors / swapping. (1) Main materials separate (volume note 5): optical (copper) cables, leaky coaxial cables, poles, and towers are main materials — prices not in "unit price", weights not in "weight"; book separately per the appendix cross-table. Covers buried/duct/aerial optical cable laying, long-distance trunk cables in trays/ducts, regional cables, leaky coaxial cables (including on catenary masts), pole erection, struts, stays, angle-steel towers, unit-combination angle towers, etc. — base prices exclude all these. (2) Equipment separate (general note 7): installation items exclude equipment cost. (3) Demolition (volume note 4): only labor and plant shifts, per demolition Table 1. (4) Bracketed materials (general note 5): bracketed quantities are consumptions per quota unit; such items carry no "material cost" or "weight" — book per design; for bracketed concrete/mortar, "HT-0" concrete carries no cost, weight, or constituents (per the basic quotas); other codes carry them and adjust per the basic quotas when the design differs. (5) Ready-mixed concrete: at the local market price including freight; no separate mixing and transport. (6) Where main materials differ from the item, swap with consumptions unchanged. (7) Concrete conversion: using basic-quota mixing/transport/mix items, multiply the design solid volume by the consumption-to-solid conversion factor.
Direct selection without extra factors. Terrain (volume note 2): plain — flat or gently undulating, relief under 20 m; hills — strongly but regularly undulating, relief under 80 m; mountains — very broken or interlaced, relief over 80 m; urban — station/townhouse, street, and yard zones. Laying items are already split by terrain and fiber count (e.g., buried optical cable <=12/24/48/96 fibers x plain / hills-mountains, TY-74~TY-81) — select directly, no self-applied factors. Ground classes per TB 10012; trench and pole items split by ordinary soil/hard soil/soft rock/hard rock etc.
Labor, materials, and price calibers (general notes). Labor consumptions include basic, auxiliary, and site short-haul labor; short haul — factory-process items within the temporary yard, others within 50 m (unless noted); shifts of 8 hours. Material consumptions include net use and waste (rates per TB/T 10821-2024); turnover materials (formwork, supports, scaffold poles/planks, sheeting) amortized per the basic quotas. Labor prices per TB 10811-2024; materials per TB/T 10813-2024; plant per TB/T 10814-2024. "Within/below" include the number; "beyond/above" exclude it; unmarked dimensions mm.
Applicable Boundaries
- For pricing new and rebuilt (expanded) railway communication works; demolition books only labor and plant shifts per Table 1 (values not attached — use the original table).
- "Main materials separate" covers only cables, leaky coax, poles, towers; whether an item is main-material-excluded is judged by the appendix cross-table, not impression.
- The quota is a consumption and base-price standard; implementation-stage prices are market-determined; compile per the estimate (budget) measures and difference-adjustment mechanism — this card carries no item base prices.
- Building-works concrete and mortar mixes do not follow this volume — per TB/T 10831-2024 Volume 10.
Further Reading
- TB/T 10826-2024: general notes, volume notes, and the appendix cross-table (optical/cable laying from TY-70; leaky coax TY-105/112; pole lines TY-275~300; towers TY-307/333); Chapter 2 cable laying (buried optical cable TY-74~81).
- Companions: TB/T 10821-2024 (waste rates, amortization, concrete); TB 10811-2024; TB/T 10813-2024; TB/T 10814-2024; TB 10012.
- Basis: revised per TB 10006 "Code for design of railway communication", TB 10418 acceptance, TB 10755 high-speed acceptance; from TZJ 2005 (superseded), issued with the 2024 system (effective date and interface per the TB 10801-2024 card).
Keywords
- railway works budget quota manual (China Railway)
- 通信工程
- TB/T 10826
- 通信定额
- 主材另计
- 光缆敷设
- 杆塔
- 地形划分