Legal consequences where contractors fail or delay warranty performance: correction order + 100k-200k fine running in parallel with damages (Regulations Articles 66/41, Construction Law Article 75, Ministry Order No. 80 Article 19)

A contractor failing or delaying warranty performance shall be ordered to correct and fined 100,000-200,000 yuan, and shall compensate losses from quality defects within the warranty period - the fine (administrative) and damages (civil) run in parallel; paying the fine does not exempt compensation. Basis: Regulations on Quality Management Article 66, Measures for Quality Warranty of Housing Projects Article 19, Construction Law Article 75; Regulations Article 41 requires the contractor to perform warranty and compensate for losses for quality problems within the warranty scope and period.

Applicable Codes

  • 《建设工程质量管理条例》(国务院令第714号,2019修订)第六十六条、第四十一条、第四十条
  • 《房屋建筑工程质量保修办法》(建设部令第80号)第十九条、第十三条
  • 《中华人民共和国建筑法》(2019修正,主席令第29号)第七十五条

Topic Positioning

Consequences of refusing or delaying warranty repairs of in-warranty defects by contractors: administrative penalties (correction order + fine) in parallel with civil damages - per Regulations on Quality Management Articles 66 and 41, Ministry Order No. 80 Article 19, and Construction Law Article 75.

Core Conclusions

I. Administrative penalty: correction order plus a 100,000-200,000 yuan fine, both imposed.

  • Regulations (Decree No. 714, 2019 revision) Article 66: "Where a contractor fails or delays warranty performance in violation of this Regulation, it shall be ordered to correct and fined 100,000-200,000 yuan, and shall compensate losses caused by quality defects within the warranty period."
  • Measures for Quality Warranty of Housing Projects (Order No. 80) Article 19 restates the same range: "ordered to correct and fined 100,000-200,000 yuan".
  • Construction Law (2019 revision, Decree No. 29) Article 75: "A construction enterprise failing or delaying warranty performance shall be ordered to correct, may be fined, and shall compensate losses from defects such as roof and wall leakage or cracking within the warranty period." The specific fine follows the Regulation. II. Damages: yes - fine and damages coexist; the fine is administrative, the damages civil; paying the fine does not remove the duty to compensate.
  • Article 66 latter half: compensate losses from quality defects within the warranty period.
  • Article 41: "For quality problems within the warranty scope and period, the contractor shall perform warranty and compensate for losses caused." Repair and compensation are statutory once the defect is in scope and period; refusal or delay merely adds the fine. III. Practice: (1) recoverable losses include those directly caused by the defect (flooded finishes, furniture, third-party property) plus losses enlarged during delay - keep photos, appraisal opinions, repair quotes to prove causation; (2) administrative complaint and civil suit run in parallel - complain to the local housing authority to trigger correction + fine, and sue for performance and damages; the penalty decision itself evidences the delay.

Applicable Boundaries

Applies where the contractor is indeed the warranty obligor and the defect is within scope and period. Defects from design, misuse, or force majeure shift responsibility. Statutory minimum periods differ by part (waterproofing 5 years; heating/cooling 2 seasons; etc., Article 40) - beyond them this does not apply. This targets "failure/delay" of warranty itself; acceptance treatment of substandard quality and cost allocation are separate topics.

Further Reading

  • Regulations (Decree No. 714, 2019) Article 66 (penalty), 41 (warranty and damages), 40 (minimum periods: leakage 5 years; heating/cooling 2 seasons; electrical/plumbing/fittings 2 years; foundation and structure - the design service life).
  • Measures for Quality Warranty (Order No. 80) Articles 19 (fine) and 13 (warranty costs borne by the responsible party).
  • Construction Law (2019 revision) Article 75.
  • Extensions: warranty when the employer uses the works early; cost allocation of repair/strengthening; the warranty letter at acceptance (related cards).

Keywords

  • 保修义务
  • 不履行保修
  • 拖延保修
  • 责令改正
  • 10万元以上20万元以下罚款
  • 建设工程质量管理条例第六十六条
  • 房屋建筑工程质量保修办法
  • 建筑法第七十五条
  • 保修期赔偿责任