Completion-acceptance filing for construction projects: the 15-day deadline, the document checklist, and the distinction from fire-protection filing (5 working days)

Within 15 days of passing completion acceptance, the employer (construction unit) shall file with the filing authority (the county-level-or-above local housing/construction department where the works are located) (Regulations on Quality Management Article 49, consistent with Ministry Order on Filing, Article 4). Six categories of documents are filed per Article 5, housing projects adding the residential quality warranty and instruction booklets; late filing: correction within a time limit plus a 200,000-500,000 yuan fine (Article 9). Note: fire filing is separate and shorter - within five working days of acceptance for "other construction works", filed with the fire design-review authority (MOHURD Order No. 58, Article 36).

Applicable Codes

  • 《建设工程质量管理条例》(2017修订)第四十九条
  • 《房屋建筑和市政基础设施工程竣工验收备案管理办法》(住建部令第2号,2009修正)第四、五、九条
  • 《建设工程消防设计审查验收管理暂行规定》(住建部令第58号,2023修正)第三十六条、第二十八条、第十四条
  • http://zjj.liaoyuan.gov.cn/zcfg/bmzc/202512/t20251224_728519.html
  • https://www.baiyin.gov.cn/szjj/fdzdgknr/lzyj/zcfg/art/2022/art_86fd97ecfad948b4a0607dc1619df4b3.html
  • https://www.baiyin.gov.cn/szjj/fdzdgknr/lzyj/zcfg/art/2022/art_29899a4dfc864da6a80d73638807d543.html
  • https://jst.zj.gov.cn/col/col1229129246/art/2020/art_530fc5471c4acb607ee5d98b6412b81e.html
  • https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1848190709849337856.html
  • https://www.meizhou.gov.cn/zwgk/gsgg/content/post_2855987.html

Topic Positioning

The employer's filing duty after passing completion acceptance: the 15-day deadline and document checklist (MOHURD Order No. 2, Article 5), and the procedural distinction from fire-acceptance filing (MOHURD Order No. 58, 5 working days).

Core Conclusions

  1. Deadline: within 15 days (calendar days) of passing acceptance, per two consistent provisions:
    • Regulations on Quality Management (2017 revision) Article 49: within 15 days of acceptance, the employer shall file the acceptance report and the approvals or permits from planning, fire, environmental and other departments with the construction administration.
    • Measures for Filing of Completion Acceptance of Housing and Municipal Works (MOHURD Order No. 2, 2009 revision) Article 4: within 15 days of acceptance, file with the county-level-or-above local housing/construction department (the filing authority).
  2. Documents (Article 5, original): (1) the acceptance filing form; (2) the acceptance report - including filing date, permit number, drawing-review opinion, quality certificates signed by the survey, design, construction, and supervision units and the original acceptance documents, quality tests and functional tests for municipal infrastructure, and other materials the authority requires; (3) approvals or permits from planning, environmental, and other departments as required by law; (4) fire-acceptance certificates for large assembly venues and other special works as required by law; (5) the quality warranty letter signed by the contractor; (6) other documents required by laws and regulations. Housing projects shall also submit the residential quality warranty and instruction booklets.
  3. Fire filing is separate and tighter (a common trap): MOHURD Order No. 58 (2023 revision) Article 36 - within five working days of acceptance of "other construction works", the employer shall file with the fire design-review authority, submitting: the fire filing form, the acceptance report, and the as-built drawings covering fire systems. In practice fire filing (5 working days) usually precedes housing filing (15 days) - both duties coexist; special works go through fire acceptance, not filing.
  4. Late filing: under Article 9 of the Measures, the authority orders correction within a time limit and fines 200,000-500,000 yuan.

Applicable Boundaries

  • The filing obligor is the employer (construction unit).
  • The 15-day housing filing is in "days" (calendar); the 5-working-day fire filing is in "working days"; both run from acceptance, but they are different procedures with different authorities - handle each separately.
  • The Measures cover housing and municipal works; Regulations Article 49 covers all construction works.
  • Covers only the post-acceptance filing duty; acceptance conditions (Regulations Article 16, five items), use before acceptance, and warranty periods are adjacent topics.
  • Special works do not use fire filing (they use fire acceptance) - scope per Order No. 58 Article 14.