Developed area formulas for ducts (ventilation ductwork): rectangular F = 2(a+b) x L, circular F = pi x D x L, tapers by average diameter / average perimeter; lock seam overlap not added; elbows, tees and reducers merged by centreline length; component lengths deducted, not merged

Duct developed area is uniformly calculated as 'developed perimeter x design centreline computation length': rectangular ducts F = 2(a+b) x L, circular ducts F = pi x D x L (pi taken as 3.1416); circular tapers by average diameter, rectangular by average perimeter; metal ducts take the internal diameter (internal perimeter), GRP and composite ducts the external diameter. Lock seam overlap (folded edges) neither enters the developed area nor adds quantity (already included in the quota). Elbows, tees, reducers and round-to-rectangular transitions merge their lengths into the centreline length and their areas into the m2 totals of the connected duct at the section perimeter; lengths occupied by dampers, outlets and other components are deducted and the components are listed separately under 030703; opening areas of access doors, test holes, supply and return outlets are not deducted. The BOQ item 030702 is measured in m2.

Applicable Codes

  • GB/T 50856-2024 通用安装工程工程量计算标准 App. G Table G.2.1(code 030702)、Table G.3.1(code 030703)
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 册说明 第三节 通风及空调工程
  • DB11/T 2382-2024 建设工程施工消耗量标准 第6.7节(6.7.28、6.7.29、6.7.30、6.7.39、6.7.41)
  • SJG 111.3-2022 城市地下综合管廊工程消耗量标准(Vol. 3 附属设施安装工程)4.2.2 通风工程

Scope of the Topic

In HVAC cost engineering: the formulas for duct developed area, the variable definitions and size bases, whether lock seam folds count, how elbows / tees / reducers merge into the duct quantities, and what must be listed separately to avoid double measurement. For BOQ preparation, budget quantity take-off and settlement checking.

Core Conclusions

1. The single computation formula: F = developed perimeter x centreline computation length Quota wording: 'Ducts are measured by the developed area shown on the design drawings, without deducting the areas of access openings, test holes, supply air openings and suction openings. The developed area is calculated as the perimeter shown on the design drawings multiplied by the duct centreline length.' (TB/T 10831-2024 'Railway works budget quota manual, volume 10, building works', volume notes, section 3, III, 1(1))

  • Rectangular ducts: F = 2(a + b) x L. a, b - the two side lengths of the section shown on the design drawings (m), metal ducts taking the internal side lengths; L - the design centreline computation length (m).
  • Circular ducts: F = pi x D x L. D - the diameter shown on the design drawings (m); L - the centreline computation length (m); pi taken as 3.1416. The circular perimeter is pi x D, so pi x D x L is simply the concrete form of 'perimeter x length' - not a second algorithm.
  • Taper (reducer) ducts: circular by average diameter, rectangular by average perimeter - 'Duct tapers: circular ducts are calculated by the average diameter; rectangular ducts by the average perimeter' (GB/T 50856-2024 table G.2.1, explanatory note 1).
  • Where a whole ventilation system uses taper ducts for uniform supply, the quota labour is multiplied by 2.50 (TB/T 10831-2024 volume notes, section 3, II.2; DB11/T 2382-2024 clause 6.7.28 likewise, labour consumption x 2.50, materials and plant unadjusted); air-curtain supply ducts are fabricated under the average larger side of rectangular ducts with labour x 3.00; arc-shaped ducts carry labour and material consumption x 1.12 (DB11/T 2382-2024 clause 6.7.28).
  • Worked examples (basis demonstration only): rectangular 1000x400, centreline length 10 m -> 2 x (1.0 + 0.4) x 10 = 28.00 m2; circular D500, centreline length 10 m -> pi x 0.5 x 10 = 15.71 m2.

2. Size basis: internal or external diameter depends on the standard and material executed

  • Metal ducts take the internal diameter: GB/T 50856-2024 table G.2.1 measures by developed area on the design internal diameter; DB11/T 2382-2024 clause 6.7.29 'measured by developed area on the design internal diameter'; TB/T 10831-2024 volume notes, section 3, II.6 'the duct diameter is the internal diameter and the perimeter the internal perimeter'.
  • GRP and composite ducts take the external diameter: DB11/T 2382-2024 clauses 6.7.39 and 6.7.41 'measured by developed area on the design external diameter'.
  • SJG 111.3-2022 clause 4.2.2: thin steel sheet ducts are measured in square metres by developed area on the design external diameter specification.
  • Diameter and perimeter must be taken on the same basis (internal perimeter with internal diameter); the two must not be mixed across standards.

3. Lock seams and folds: neither enter the developed area nor add quantity

  • BOQ basis: 'The duct developed area does not include the overlapping areas of ducts and duct ends' (GB/T 50856-2024 table G.2.1, explanatory note 1).
  • Quota basis: 'Diameter and perimeter are taken from the dimensions shown on the design drawings; the overlap of lock seams is already included in the quota and is not added' (TB/T 10831-2024 volume notes, section 3, III, 1(2)).
  • Local basis: 'The overlapping areas of ducts and duct ends are already included in the items and may not be counted again' (SJG 111.3-2022 clause 4.2.2).
  • Conclusion: in fabrication and material cutting, add the lock seam allowance to the developed perimeter; the priced quantity takes only 'design perimeter x centreline length', the seam's material and labour being amortised into the items.

4. Merging rules for fittings and the no-double-measurement boundary

  • Start and end points: 'The duct length follows the centreline length shown on the design drawings (main and branch ducts divide at the intersection of their centrelines), including the lengths of elbows, tees, reducers, round-to-rectangular transitions and other fittings, but excluding the lengths occupied by components' (GB/T 50856-2024 table G.2.1, explanatory note 1); 'the start and end points of the centreline are taken at the intersections of duct centrelines' (DB11/T 2382-2024 clause 6.7.30). Division at centreline intersections, not at flanges or joints.
  • Merging method: fittings are converted into the m2 total of the ducts they connect, at 'centreline length x section perimeter', and are not computed as exact geometric developed areas of the elbows nor given separate items. The quota itself already contains the fittings - 'The fabrication and installation quotas for thin steel sheet and GRP ductwork cover elbows, tees, reducers, round-to-rectangular transitions, flanges, stiffening frames and suspension brackets, but exclude floor-standing brackets across duct runs; floor-standing brackets follow the equipment support items' (TB/T 10831-2024 volume notes, section 3, II.4); floor-standing brackets for ducts crossing spans follow the equipment support items (DB11/T 2382-2024 clauses 6.7.31 and 6.7.24).
  • To be deducted (not merged into the duct): the lengths occupied by dampers and other components. GB/T 50856-2024 gives no deduction values; where the design is silent, local standards may be used: butterfly damper L=150mm, non-return damper L=300mm, circular fire damper L=220mm, rectangular fire damper L=210mm, airtight opposed-blade control damper L=210mm, airtight inclined slide-plate damper L=220mm (SJG 111.3-2022 clause 4.2.2). The components themselves are listed separately under the component items of GB/T 50856-2024 table G.3.1 (code 030703) and measured by count - neither omit the components through the length deduction nor merge them into the ductwork for double counting.
  • Not deductible (area basis): the opening areas of access openings, test holes, supply outlets, suction outlets and the like are never deducted (BOQ and all quota norms agree). Deduct component lengths in length; do not deduct openings in area - the two rules run in parallel.
  • Supports and hangers: the ductwork items already cover their fabrication and installation; if listed separately, use the codes of Appendix N 'other and ancillary works' of GB/T 50856-2024 (table G.2.1, explanatory note 6).
  • Other companion rules (table G.2.1 explanatory notes): wall sleeves are measured by developed area and enter the corresponding ductwork quantities by material and thickness (note 2); where the structural steel of purification ductwork is to be galvanised, the work content shall state the galvanising of the structural steel (note 3); factory-made ducts use the corresponding ductwork item codes (note 4); stainless steel smoke-exhaust ducts use the stainless steel sheet ductwork codes (note 5).

5. BOQ item division (m2) Ducts fall under GB/T 50856-2024 Appendix G, table G.2.1 'fabrication and installation of ventilation ducts', code 030702, unit m2, measured by developed area on the design internal diameter, work content covering the fabrication and installation of ducts, fittings, flanges and parts; items are divided by item description - material (thin steel sheet / stainless steel sheet / GRP / composite / flexible and the like), shape (circular / rectangular), size, plate thickness, connection form. Elbows, tees, reducers and other fittings are not given separate BOQ items; their quantities sit inside the m2 of 030702; dampers, outlets, diffusers, hoods, silencers and the like fall under the 030703 component items measured by design count (plenum boxes by developed area, without deducting the areas of the duct openings they receive). Quota side, the corresponding item chapters are TB/T 10831-2024 volume 10 building works, section 3, ventilation and air conditioning works, 'II. ducts' and 'III. measurement rules'; and DB11/T 2382-2024 section 6.7, III thin steel sheet ductwork and fittings (clauses 6.7.25 to 6.7.37), IV GRP ductwork, V composite ductwork.

Applicability Boundaries

  • Scope: BOQ preparation, budget quantity take-off and settlement checking of ventilation and air conditioning ductwork (thin steel sheet, stainless steel sheet, GRP, composite, flexible and the like); ventilation works of utility tunnel ancillaries may refer to the SJG 111.3-2022 basis.
  • pi x D x L and 2(a+b)L are concrete forms of 'developed perimeter x centreline length', not a second rule running alongside the standard; where the executed standard provides otherwise on internal / external diameter or component deduction lengths, that standard prevails.
  • 'No area deduction' applies only to openings such as access openings, test holes, supply / return outlets and suction outlets; the lengths occupied by dampers, outlets and similar components are still deducted - 'no area deduction' must not be stretched into 'no length deduction'.
  • 'No addition' for lock seams concerns the priced quantities only; cutting allowances are a technological consumption and may not serve as a quantity increase nor as the basis for claims through site instruction records.
  • The taper rule 'by average diameter / average perimeter' settles only the item-selection basis; the labour factors (uniform supply 2.50, air-curtain ducts 3.00) are adjustable, materials and plant generally are not - check against the notes of the executed quota.
  • Local consumption standards pair with the local quotas; before cross-regional application, check the local current edition and pricing basis.

Further Reading

  • GB/T 50856-2024 'general installation works quantity take-off standard', Appendix G ventilation and air conditioning works: table G.2.1 fabrication and installation of ventilation ducts (code 030702), explanatory notes 1 to 6 and the table body (unit m2, work content); table G.3.1 fabrication and installation of duct components (code 030703), notes; separate listing of supports and hangers in Appendix N, other and ancillary works.
  • TB/T 10831-2024 'railway works budget quota manual, volume 10, building works', volume notes, section 3, ventilation and air conditioning works: I. air conditioning components and equipment supports (notes 1 to 3); II. ducts (notes 1 to 7, covering labour factors, the fittings and supports included, internal / external diameter basis); III. measurement rules 1 (1) (2), 2.
  • DB11/T 2382-2024 'consumption standard for construction works', section 6.7 ventilation and air conditioning installation: clauses 6.7.24 and 6.7.25 to 6.7.37 (thin steel sheet ducts and fittings, incl. 6.7.28 factors, 6.7.29 area basis, 6.7.30 length basis, 6.7.32 wall sleeves and end plates), 6.7.39 and 6.7.41 (GRP and composite by external diameter).