Measurement of rework and the rules on rework compensation: the written rework confirmation requirement and the consequences of delay, the two measurement branches by responsible party (employer responsibility vs contractor fault), the order for setting rework rates (the three tiers of variation valuation), and the eight categories of employer-responsibility events carrying an additional profit claim

Under GB/T 50500-2024: the contractor must submit a written rework confirmation request within the time agreed in the contract; on expiry the rework is deemed not to have occurred, the rework quantities are not measured and no costs are compensated (Article 7.6.1). Where the rework arises from a variation or the employer's responsibility, the rework items, quantities and amounts of written-off or scrapped materials stated in the rework confirmation sheet form the measured quantities and are priced under Chapter 8; rework attributable to the contractor is not measured (Article 7.6.4). Rework rates follow the three tiers of variation valuation: where the price list has an applicable item, adopt its rates and prices; where none is applicable but a similar item exists, proceed by reference to the similar item; where neither exists, set new rates on a cost-plus-profit basis. Where the employer's responsibility causes rework, profit is claimable in addition to economic loss and increased costs (Article 8.11.10).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第7.6.1、7.6.4、8.11.3、8.11.9、8.11.10条
  • 建市〔2020〕96号 建设项目工程总承包合同(示范文本)GF-2020-0216 通用合同条件第13.1.1、13.3.1、13.3.3.1、13.3.3.2、19.1~19.4款
  • 《中华人民共和国民法典》第八百零四条、第八百零五条

Topic Positioning

The measurement basis, the make-up of rework compensation, the order for setting rework rates and the claim procedure deadlines, within the BOQ pricing system, for rework caused by variations or employer-responsibility events (removal and redoing of completed works; write-off or scrapping of purchased and processed materials); rework caused by the contractor's own fault takes the opposite route of 'no measurement'.

Core Conclusions

1. Measurement precondition: a written rework confirmation request within the time limit - on expiry, everything falls to zero. GB/T 50500-2024, Article 7.6.1: 'Where a variation or an employer-responsibility event causes rework of part or all of the works the contractor has completed, or causes materials the contractor has purchased or processed to be written off or scrapped, the contractor shall, within the time agreed in the contract, submit to the employer a written rework confirmation request and provide the supporting evidence. Where the contractor fails to submit the rework confirmation request within the agreed time, it is deemed that the variation instruction or the employer-responsibility event caused no rework of the works and no write-off or scrapping of the purchased or processed materials; the rework quantities shall not be measured and the related costs shall not be compensated.' Second limb of the same article: 'Where rework of the works completed by the contractor, or write-off or scrapping of purchased (processed) materials, is caused by a variation or the employer's responsibility, the rework quantities shall be computed, and the employer shall compensate the contractor for the related losses and/or direct costs of carrying out the rework.'

2. Measurement rules branch by responsible party. Article 7.6.4: 'For projects in which rework occurs, the responsibilities of the employer and the contractor shall be clarified as agreed in the contract, and the related costs of the rework shall be borne by the responsible party. Where the cause is a variation or the employer's responsibility, the rework items and their quantities, and the written-off or scrapped purchased and processed materials and their quantities, stated in the rework confirmation sheet are the measured quantities of the rework works and the basis for computing the price of the rework works under the contract price adjustment provisions of Chapter 8 of this standard; where the cause is the contractor's responsibility, the related rework quantities shall not be measured.' Make-up of the compensation (second limb of the same article): 'Where the rework is caused by a variation or by the employer, the rework compensation shall be computed, per the relevant provisions, from the rework items and their quantities and the written-off or scrapped materials and their quantities fixed in the rework confirmation sheet signed by the employer and the contractor. Where the rework is caused by the contractor's failure to perform its duties under the contract, the related costs are borne by the contractor itself, and the rework confirmation sheet cannot be used to compute the rework compensation.'

3. The order for setting rework rates (the three tiers of variation valuation). GF-2020-0216, clause 13.3.3.1 [valuation of variations]: unless the particular conditions provide otherwise, (1) where the contract contains no price list, the contract price is adjusted on the basis of the cost of the varied works plus profit; (2) where the contract contains a price list, the contract price is adjusted as follows: 1) where the price list contains items applicable to the varied works, the rates and prices of those items are adopted; 2) where the price list contains no applicable item but contains items similar to the varied works, the rates or prices of the similar items may be referenced within a reasonable range; 3) where the price list contains neither applicable nor similar items, the item is adjusted to new rates or prices on a cost-plus-profit basis. Clause 13.3.3.2 requires the contractor to submit its variation quotation to the engineer within 14 days after receiving the variation instruction; price adjustments arising from variations are included in the most recent progress payment.

4. Employer-responsibility events carrying an additional profit claim (eight categories), and the four heads of suspension loss. GB/T 50500-2024, Article 8.11.10: where the following events occur for reasons attributable to the employer and cause the contractor economic loss, increased costs and/or prolongation of time, the contractor may, in addition to claiming under Article 8.11.9, also claim profit: 1 the employer transfers an item of work under the contract to another contractor to complete; 2 the employer is late in providing construction drawings or the construction site; 3 materials supplied by the employer are non-conforming, delivered late, or their delivery place is changed, causing the works to be non-conforming; 4 employer-caused errors in the contractor's setting-out, or rework of the works; 5 additional restrictions imposed by the employer on the site, failure to perform approvals on time, or interference with the normal construction sequence; 6 employer-caused delay, suspension of the works, or failure to resume work on time after suspension; 7 the employer takes over the works prematurely before completion; 8 employer-caused repair of defects or damage to the works within the defects liability period. 'Losses of labour, materials and plant from suspension, waiting, reduced efficiency or prolongation include the following costs: (1) idle labour costs of personnel already mobilised who cannot carry out work; (2) losses on materials already delivered that cannot be put to use; (3) plant standby costs of plant already delivered that cannot be put to work; (4) other losses.' For economic loss and/or delay caused by government authorities, the time is extended accordingly and the economic loss is borne by each party itself.

5. Claim procedure deadlines (model contract basis). GF-2020-0216, clause 19.1: the claiming party must send the other party a Notice of Claim within 28 days after it knows or should know of the claim event - 'where the claiming party fails to send the notice of claim within those 28 days, it loses the right to demand added or reduced payment, extension of the defects liability period and/or extension of time'; within 28 days after sending the Notice of Claim it must submit the formal claim report; for events with continuing effect, a further notice is submitted each month; within 28 days after the influence ends, the final claim report is submitted. Clause 19.2: where the engineer fails to reply within 42 days after receiving the claim report or further supporting material, the claim is deemed approved; where the contractor accepts the outcome of the claim, the employer must complete payment within 28 days after the reply. Clause 19.4: on receiving the completion payment certificate, the contractor is deemed to have no further right to claim for any event arising before the Taking-Over Certificate was issued; under the final closure application it may claim only for events after the certificate was issued, and the period ends on acceptance of the final closure certificate.

6. The rework cost formula and the evidentiary anchor Rework cost = direct costs of removal and rebuilding (labour + materials + plant) + the written-off/scrapped value of purchased or processed materials + secondary erection and dismantling and other preliminaries + overheads + (where Article 8.11.10 applies) profit + losses from prolongation such as idle labour, plant standby and guarantee extensions. Measurement and pricing are anchored throughout to the 'rework confirmation sheet signed by both parties': the three data classes - items, quantities and written-off material amounts - must be confirmed item by item; the sheet is the sole gateway into settlement and expert assessment. In-house statistics of rework cost by labour workdays, material write-offs and machine-shifts belong to cost accounting and are a separate ledger from the price measurement here; the two cannot substitute for each other.

Boundaries of Application

  • GB/T 50500-2024 is a recommended national standard; the contract prevails. Where the contract expressly cites the old GB 50500-2013, that version governs (under the 2013 version a late claim notice meant 'loss of the right to claim' - a hard time bar - unlike the 2024 version's softer 'may be handled as agreed in the contract').
  • The fallback for the 'time agreed in the contract' in Article 7.6.1, where none is agreed, is 'the period agreed in the contract (28 days if none agreed)' under GB/T 50500-2024, Article 8.11.3.
  • Rework quantities mean the rework items and quantities stated in the rework confirmation sheet, with written-off or scrapped materials listed separately by quantity; they do not allow the original works to be measured twice; rework attributable to the contractor is never measured, and quantities must not be double counted under the name of rework.
  • Not applicable to defects the contractor repairs of its own accord during the defects liability / warranty period (that scenario falls under Civil Code Article 801: the contractor repairs, reworks or rebuilds free of charge at its own cost).
  • Suspension and idle losses unconnected with rework facts go through the claim route of Articles 8.11.9 and 8.11.10 together with Civil Code Article 804, without needing a rework confirmation sheet.

Further Reading

  • GB/T 50500-2024, China national pricing standard for BOQ: Article 7.6.1 (rework confirmation request and loss of the right on expiry), Article 7.6.4 (rework quantities and rework compensation), Article 8.11.3 (Notice of Claim and deadlines), Article 8.11.9 (claimable costs), Article 8.11.10 (situations carrying profit and the four heads of suspension loss), Chapter 8 (adjustment of the contract price).
  • GF-2020-0216 general conditions: clause 13.1.1 [employer's right to vary], clauses 13.3.1 to 13.3.3 [variation procedure and valuation], clauses 19.1 to 19.4 [claims].
  • Civil Code Article 804 (losses and costs on halting or slowing the works), Article 805 (added costs from inaccurate data causing rework).
  • Related topics: the evolution of the 28-day claim deadline (2013 hard time bar vs 2024 soft treatment), the full chain of claim procedure deadlines, where claim costs are listed in the final account, and the labour / material / plant statistical bases of rework cost.

Keywords

  • 返工确认单
  • 返工工程量计量
  • 返工补偿费
  • 变更估价原则
  • 8.11.10 索赔利润
  • 28天索赔意向通知书
  • 报损报废材料
  • GB/T 50500-2024 第7.6条