Counting and measuring rework costs (labor/materials/machinery) caused by quality problems
Rework cost accounting starts with responsibility: rework caused by works variations or the employer is measurable and forms the basis of contract-price adjustment; rework caused by the contractor itself through quality failures is not measured and is borne by the contractor. A written rework-confirmation request must be raised within the contract period and a rework confirmation sheet signed, then costs are counted under three heads — labor worker-days, written-off/scrap materials, and machinery shifts — with an internal ledger kept for evidence.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB 50300-2013 建筑工程施工质量验收统一标准
- GB/T 50430-2017 工程建设施工企业质量管理规范
Topic Positioning
How the labor, material, and machinery costs of quality-problem rework are counted: fix responsibility first, follow the procedure, then book by cost head — for contract measurement and internal quality-cost accounting.
Core Conclusions
Rework costs run on two tracks — external measurement and internal cost. ① Responsibility first: under GB/T 50500-2024 Clause 7.6.4, rework caused by works variations or the employer has its quantities and written-off/scrap materials measurable as a basis for contract-price adjustment; rework caused by the contractor's own quality failures is not measurable and is borne by the contractor. ② Procedural evidence: the contractor must raise the written rework-confirmation request with supporting documents within the contract period — late requests are deemed no rework and not measured (Clause 7.6.1); both parties sign the rework confirmation sheet citing the drawing/variation-instruction numbers relied on; items not measurable per drawings have their scope and quantities negotiated; written-off/scrap materials are listed by name, specification, quantity, unit/total price, and disposal method (Clause 7.6.3). ③ Three-head breakdown: labor = rework worker-day ledger × unit rates; materials = written-off/scrap items (valued at main-material cost within contract unit rates, salvage offset) plus newly added materials; machinery = shift records × shift rates. Formula: rework cost = demolition and clearing + re-construction + written-off/scrap materials − salvage value. Regardless of external measurability, the enterprise should keep a rework ledger with photographic evidence (GB/T 50430-2017, Clause 11.5.1).
Applicable Boundaries
Applies to measurement of employer-responsibility/variation-induced rework under the BOQ valuation system (GB/T 50500) and to contractors' quality-cost management. Not applicable: contractor-caused rework (not measured), single-point price queries, defect-repair workmanship, or accident grading; contract agreements prevail; rework without written confirmation must not be measured.
Further Reading
See GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clauses 7.6.1, 7.6.3, 7.6.4 (measurement of contract works); the term "rework" defined in GB 50300-2013, Unified Standard for Construction Quality Acceptance of Building Works, Clause 2.0.17; classified management of quality problems in GB/T 50430-2017, Clause 11.5.1.