FIDIC 2017 Red Book Sub-Clause 8.8 Delay Damages: trigger, daily rate, cap, sole-remedy character, and the linked risks of 8.2/20.2/15.2/17.4
Under FIDIC 2017 Red Book 8.8: where the contractor fails to complete by the Time for Completion under 8.2 (even as reset by EOT), the employer recovers Delay Damages at the daily rate stated in the Contract Data for every day late, capped at the maximum stated (blank = no cap); 8.9 makes DD the "only damages" for late completion - not relieving the duty to complete, excluding fraud, gross negligence, deliberate default, and recklessness; hitting the cap while incomplete detonates the 15.2(b) termination right, and 17.4(a) sets the liability limit for this breach at the DD cap itself. The employer's DD claim is equally subject to 20.2 (28-day hard bar) - the 2017 procedure is symmetric.
Applicable Codes
- FIDIC Conditions of Contract for Construction, 2nd Ed. 2017 (Red Book): Sub-Clause 8.8 Delay Damages; 相关 8.2/8.5/8.9、15.2、17.4、20.2
- GB/T 50500-2024 建设工程工程量清单计价标准 第 8.11.3、8.11.4、8.11.19 条、第 2.0.33 条
- GB/T 50875-2013 建设工程造价术语标准 第 3.4.6 条
Topic Positioning
A complete reading of Sub-Clause 8.8 Delay Damages (DD) of the FIDIC Conditions of Contract for Construction, 2nd ed. 2017: element structure, rate and cap, sole-remedy character, and the linked risks with the 20.2 claims procedure, 15.2 termination, and 17.4 liability limits - for contractors' and employers' contract management on FIDIC projects, with reminders of where the domestic regime of delay damages/liquidated damages must not be imported.
Core Conclusions
(1) Clause structure (a closed loop of five elements): Trigger - failure to comply with Sub-Clause 8.2 [Time for Completion] (including as reset by approved EOT); Procedural precondition - "subject to Sub-Clause 20.2", the employer's DD claim itself follows the claims procedure (2017 symmetric; domestically, GB/T 50500-2024 8.11.4 expressly excludes delay damages from the employer-claim procedure - a systemic difference); Rate - "Delay Damages shall be the amount stated in the Contract Data, which shall be paid for every day which shall elapse between the relevant Time for Completion and the relevant Date of Completion of the Works or Section"; Cap - "The total amount due under this Sub-Clause shall not exceed the maximum amount of Delay Damages (if any) stated in the Contract Data" (unstated = no cap). (2) Sole remedy (8.8 closing / 8.9): "These Delay Damages shall be the only damages due from the Contractor for the Contractor's failure to comply with Sub-Clause 8.2 [Time for Completion]" - DD is the exclusive damages for late completion (except 15.2 termination cases); DD "shall not relieve the Contractor from the obligation to complete the Works" (nor other obligations); fraud, gross negligence, deliberate default, or reckless misconduct (fraud, gross negligence, deliberate default or reckless misconduct) are not limited by this clause. (3) Three trapdoors of the cap: First, 15.2 termination - the employer may terminate where the contractor fails to comply with Clause 8 or where the 8.2 breach "entitles the Employer to Delay Damages exceeding the maximum stated in the Contract Data"; the cap only limits daily accrual - once hit with the works incomplete, the termination right arises, and post-termination re-procurement cost claims under 15.4 sit outside DD protection. Second, 17.4 limits interlock - liability to the employer is itemized: "(a) for failure to comply with Sub-Clause 8.2, the limit shall be the maximum amount of Delay Damages stated in the Contract Data" (the time-breach limit is the DD cap itself), with loss-of-profit and damage-to-works limits as sums A/B - so the DD cap must be negotiated within the 17.4 system. Third, leaving the cap blank in the Contract Data ("if any" unstated) means unlimited daily accrual and a hollow 17.4(a) - a contractor red line, unacceptable. (4) Milestone DD (optional wording): FIDIC 2017 offers per-milestone DD - daily amounts between each milestone's time and the Milestone Certificate date, each milestone's DD the sole remedy for that breach, all milestones' DD still capped by the stated maximum (fraud etc. excepted). (5) Hard procedural bar (20.2): the claiming Party must notify the Engineer within 28 days of awareness - "If the claiming Party fails to give a Notice of Claim within this period of 28 days, the claiming Party shall not be entitled to any additional payment" - substantive forfeiture; then the fully detailed Claim in time, else the Notice lapses, the Engineer notifying within 14 days after expiry. Against the domestic elastic "may be deemed waived (unless ...)", FIDIC's bar is rigid - contractors must shed the domestic habit of late papering rescued by negotiation. (6) Domestic habits to shed: domestically delay damages are not exclusive - GB/T 50500-2024 8.11.19 lets the employer "choose one or more of: extended warranty / extra cost / delay damages / liquidated damages", and term 2.0.33 defines the fee as contract-based compensation; under FIDIC, DD is exclusive and does not relieve completion - manage FIDIC time without the "stack DD with liquidated damages; paid, so no need to rush" mindset.
Applicable Boundaries
- Text: Red Book 2017 2nd ed. (English quoted); 1999's counterpart is 8.7, and 2017 is more symmetric on employer claims - check clause numbers for older contracts.
- DD parameters live in the Contract Data, not the conditions; rate form (fixed or percentage), cap, and any blank are negotiation matters - no suggested values here.
- DD is subject to 20.2 but runs parallel to EOT (8.5: variations, listed delay causes, exceptional climate): pursue EOT to reset completion, else the DD start point turns against the contractor.
- The domestic comparison is for understanding only: GB/T 50500-2024 binds on incorporation; the FIDIC text itself is the parties' agreement, needing no domestic backstop.
Further Reading
- Red Book 2017: 8.2, 8.5, 8.8, para. 8.9, 15.2 (DD above cap as termination ground), 17.4 (limits; 8.2 breach = DD cap; sums A/B), 20.2 (20.2.1 bar; 20.2.2 lapse and 14-day notice); milestone DD wording per the conditions and Contract Data guidance.
- Domestic: GB/T 50500-2024 8.11.3 (contractor procedure), 8.11.4 (employer claims excluding delay damages), 8.11.19 (multiple remedies), 2.0.33 (term); GB/T 50875-2013 3.4.6 (delay claim). Whole-system comparison and the 28-day chain in cited cards.
Keywords
- International Federation of Consulting Engineers (FIDIC)
- FIDIC Red Book (Conditions of Contract for Construction)
- Delay Damages
- 误期损害赔偿
- 8.8
- Contract Data
- extension of time
- 索赔程序
- 违约金