Early completion (acceleration compensation): allocation of liability and drafting requirements - the 20% cap on compression against the norm-based duration, the employer bearing the acceleration compensation, the per-calendar-day compensation rate and its listing in the final account (GB 50500-2013 Section 9.11 / GB/T 50500-2024 clause 8.11.17 / GF-2017-0201 clause 7.9)

Three rules on early completion (acceleration compensation): (1) the compressed duration shall not exceed 20% of the norm-based duration, and beyond that the additional acceleration cost must be stated in the tender documents (GB 50500-2013 clause 9.11.1, grounded on Article 10 of the Regulation on Quality Management of Construction Projects, which forbids arbitrary compression of the reasonable duration); (2) where the employer requires early completion it must obtain the contractor's consent, agree acceleration measures and revise the programme, and the added acceleration compensation is borne by the employer (clause 9.11.2; GF-2017-0201 clause 7.9.1 requires the early completion proposal to state the method, the time shortened and the added contract price, with objections answered within 7 days); (3) the compensation payable per calendar day is agreed in the contract, listed in the final account documents as an addition to the contract price and paid together with the settlement monies (clause 9.11.3); the commentary figure that early completion compensation may be 5% of the contract price is a reference only. Reverse case: where the contractor accelerates to recover its own delay, the acceleration cost is its own (commentary on Section 9.12); where the contractor completes early on its own initiative rather than at the employer's request, the employer's consent is required and the cost falls on the contractor (GB/T 50500-2024 clause 8.11.17).

Applicable Codes

  • GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.11.1~9.11.3条及第9.11节条文说明(已被替代)
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.17条
  • GF-2017-0201《建设工程施工合同(示范文本)》第7.9.1、7.9.2条
  • 《建设工程质量管理条例》第十条

What this card covers

This card sets out the allocation of liability and the drafting requirements for 'early completion (acceleration compensation)': the 20% cap on duration compression, who bears the acceleration compensation, how the per-calendar-day rate is agreed and listed in the final account, and the contrast with acceleration undertaken to recover a delay caused by the contractor itself. Based on GB 50500-2013 Section 9.11, GF-2017-0201 clause 7.9 and GB/T 50500-2024 clause 8.11.17.

Core conclusions

1. The 20% cap: compressed duration shall not exceed 20% of the norm-based duration

GB 50500-2013 clause 9.11.1: 'The tendering employer shall calculate the duration reasonably from the duration quota norms for the relevant works; the number of days by which the duration is compressed shall not exceed 20% of the norm-based duration; where it exceeds that, the additional acceleration cost shall be stated in the tender documents.'

The commentary on Section 9.11 gives the statutory basis and the quantification: Article 10 of the Regulation on Quality Management of Construction Projects provides that the employer of a construction project shall not force the contractor to bid below cost and shall not arbitrarily compress the reasonable duration. Accordingly, this section requires the tendering employer to calculate the duration reasonably from the duration quota norms, and quantifies the rule: the compressed duration shall not exceed 20% of the norm-based duration; beyond that, the additional acceleration cost shall be stated in the tender documents.

Practical points:

  • The base of the 20% test is the norm-based duration (the reasonable duration calculated from the duration quota norms), not the tenderer's self-declared duration and not the contract duration.
  • Exceeding 20% is not forbidden outright; it triggers the duty to 'state the additional acceleration cost in the tender documents' - the acceleration cost must be exposed at tender stage; later additions lack basis.
  • The model text points the same way (GF-2017-0201 clause 7.9.1): '... in no circumstances shall the employer compress the reasonable duration.'

2. Who bears the acceleration compensation

GB 50500-2013 clause 9.11.2: 'Where the employer requires the contract works to be completed early, it shall obtain the contractor's consent, agree with the contractor on measures to accelerate progress, and shall revise the programme of the contract works. The employer shall bear the early completion (acceleration compensation) costs incurred by the contractor thereby.'

Three elements, all required: (1) the employer makes the request; (2) the contractor's consent is obtained and acceleration measures agreed; (3) the programme of the contract works is revised. Once all are met, the added cost falls to the employer.

GB/T 50500-2024 clause 8.11.17 (the current recommended standard): 'For claims arising from early completion (acceleration) events, the parties may bear the corresponding costs and adjust the contract price and the duration as follows: 1 where the employer requires the contract works to be completed early, the contractor shall formulate reasonable measures to accelerate progress and revise the programme, implement them with the employer's consent, and the added early completion cost (acceleration compensation) shall be borne by the employer; 2 where the contractor completes early on its own initiative and not at the employer's request, the employer's consent shall be obtained and the added cost shall be borne by the contractor.' Commentary on the same clause: 'Where the employer requires early completion (acceleration) of the contract works, the employer shall bear the added costs the contractor incurs in using non-economical labour, materials and construction plant.'

Reverse case (the key contrast): where actual progress falls behind the planned progress for reasons attributable to the contractor itself, the contractor shall accelerate to achieve the contract duration - even if the contractor takes acceleration measures, the acceleration cost is still borne by the contractor (commentary on GB 50500-2013 Section 9.12). 'Whoever benefits pays' is not the test; what decides is who initiated the acceleration instruction and where the liability sits.

3. The compensation rate and its listing in the final account

GB 50500-2013 clause 9.11.3: 'The employer and the contractor shall agree in the contract the compensation amount payable per calendar day for early completion; this cost shall be listed in the final account documents as an addition to the contract price and paid together with the settlement monies.'

  • Compensation runs on calendar days, the same per-calendar-day basis as delay damages, so the two can be drafted symmetrically in both directions within one contract.
  • The settlement direction is opposite to delay damages: acceleration compensation is an addition to the contract price, paid together with the settlement monies; delay damages are deducted from the settlement monies.
  • Reference figure: the commentary to Section 9.11 notes that 'unless otherwise agreed in the contract, the early completion compensation may be 5% of the contract price' - a commentary-level reference like the delay damages figure, not mandatory; the contract must state the agreed value.

4. Procedural requirements in the model text (GF-2017-0201 clause 7.9)

Clause 7.9.1: 'Where the employer requires the contractor to complete early, the employer shall issue an early completion instruction to the contractor through the supervising engineer; the contractor shall submit an early completion proposal to the employer and the supervising engineer, and the proposal shall include the method to be implemented, the time to be shortened and the addition to the contract price. If the employer accepts the proposal, the supervising engineer shall agree with the employer and the contractor on measures to accelerate progress and revise the construction programme, and the added costs shall be borne by the employer. If the contractor considers the early completion instruction impossible to execute, it shall raise a written objection to the supervising engineer and the employer, and the employer and the supervising engineer shall reply within 7 days of receipt. In no circumstances shall the employer compress the reasonable duration.'

Clause 7.9.2: 'Where the employer requires the contractor to complete early, or where a proposal by the contractor for early completion would bring the employer benefit, the contracting parties may agree in the particular conditions a bonus for early completion.'

The procedural loop: instruction (issued through the supervising engineer) -> proposal (method / time shortened / added price) -> employer acceptance -> agreement on acceleration measures and revision of the programme -> costs borne by the employer; where the contractor does not accept, written objection and reply within 7 days.

Applicable boundaries

  1. The 20% cap constrains the duration set at tender stage (against the norm-based duration), not the acceleration cost rate during construction; during construction, the acceleration cost is taken on the actual added cost of non-economical labour, materials and plant, or on the per-calendar-day rate agreed in the contract.
  2. '5%' is only a commentary reference and must not be cited as a statutory cap or standard; the actual rate follows the particular conditions of the contract, and absent agreement is proved by the actual added cost.
  3. Where the contractor completes early on its own initiative (not at the employer's request), the added cost is the contractor's own and the employer's consent must be obtained first (GB/T 50500-2024 clause 8.11.17, item 2); unilateral acceleration without consent supports no claim to compensation.
  4. This applies to the durations of construction contracts; emergency and rescue operations and acceleration for reasons not attributable to the employer follow their own liability rules.
  5. The 2024 edition is a recommended standard; where the contract still invokes the 2013 edition, cite clause numbers 9.11.1 to 9.11.3, not 8.11.17.
  6. Acceleration compensation and delay damages should be drafted as symmetric clauses in the contract (same base, same calendar-day basis), otherwise the reverse incentives fall out of balance.

Further reading

  • GB 50500-2013 (code for BOQ pricing of construction works) Section 9.11 (9.11.1 compression not exceeding 20% of the norm-based duration; 9.11.2 cost bearing where the employer requires early completion; 9.11.3 per-calendar-day compensation rate and listing in the final account) and its commentary (including the citation of Article 10 of the Regulation on Quality Management of Construction Projects).
  • GB/T 50500-2024 (standard for BOQ pricing of construction works) clause 8.11.17 (the two principles on early completion / acceleration cost bearing, and the added cost of non-economical labour, materials and plant).
  • GF-2017-0201 Model Construction Contract clause 7.9.1 (early completion instruction procedure, proposal content, 7-day objection and reply, no compression of the reasonable duration), clause 7.9.2 (agreeing an early completion bonus).
  • Cross-reading: GB 50500-2013 Section 9.12 (delay damages) and the commentary sentence that even where the contractor takes acceleration measures, the acceleration cost is still borne by the contractor.

Keywords

  • 提前竣工
  • 赶工补偿
  • 赶工费用
  • 压缩工期20%
  • 定额工期
  • 每日历天补偿额度
  • 提前竣工建议书
  • GB 50500-2013 9.11