The three-year limitation period for claims to construction payment: its starting point (the day the creditor knew or should have known of the harm to the right and of the obligor) and the consequences of the limitation defence having to be raised at first instance (Civil Code Article 188; Fa Shi [2008] No. 11, Article 3)
The limitation period for applying to a people's court for protection of civil rights is three years, counted from the day the right holder knew or should have known of the harm to the right and of the obligor; where more than twenty years have passed since the right was harmed, the people's court will not protect the right (Civil Code Article 188). An employer or debtor raising the limitation defence must do so at first instance; raising it at second instance will not be supported (except where new evidence proves the claim already time-barred), and applications for retrial or retrial defences based on expiry of the limitation period, where the defence was not raised in time, are likewise not supported (Fa Shi [2008] No. 11, Article 3).
Applicable Codes
- 《中华人民共和国民法典》第一百八十八条
- 法释〔2008〕11号《最高人民法院关于审理民事案件适用诉讼时效制度若干问题的规定》(2020修正)第三条
Scope and purpose
Claims to construction payment are subject to the three-year limitation period. This card sets out the duration of the period, its starting point, and when the obligor must raise the limitation defence, for judging whether a claim is filed too late, whether the defence stands, and when the creditor should fix its evidence of asserting the right.
Key conclusions
Article 188 of the Civil Code, in full: 'The limitation period for applying to a people's court for protection of civil rights is three years. Where the law provides otherwise, those provisions apply. The limitation period runs from the day the right holder knew or should have known of the harm to the right and of the obligor. Where the law provides otherwise, those provisions apply. However, where more than twenty years have passed since the right was harmed, the people's court will not protect the right; in special circumstances the people's court may, on the right holder's application, decide to extend the period.'
Article 3 of the Provisions of the Supreme People's Court on Several Issues Concerning the Application of the Limitation System in the Trial of Civil Cases (Fa Shi [2008] No. 11, as amended in 2020), in full: 'Where a party fails to raise the limitation defence at first instance and raises it at second instance, the people's court will not support it, except where that party can prove on the basis of new evidence that the other party's claim has passed the limitation period. Where a party fails to raise the limitation defence as provided in the preceding paragraph and applies for retrial or raises a retrial defence on the ground that the limitation period has expired, the people's court will not support it.'
Practical points:
- The three-year period starts on the day the creditor 'knew or should have known of the harm to the right and of the obligor'; for construction payment this usually falls at expiry of the agreed payment term, at confirmation of the settlement, or on continued non-payment after a demand; the twenty-year period is the maximum, runs from the day the right was harmed, and does not restart because a party was unaware.
- The limitation defence is the obligor's first-instance-only weapon: if not raised at first instance, it will in principle not be supported at second instance (unless new evidence proves the claim time-barred); retrial applications or retrial defences based on expiry of the period are never supported.
- The creditor's corresponding move: before suing, fix the evidence of asserting the right into a chain (demand letters, account confirmations, correspondence, minutes of meetings), so that if the defence is raised at first instance it can be answered with facts of continuous assertion; the debtor, for its part, must raise the limitation defence in writing at the first-instance pleading stage - leaving it to the second instance leaves virtually no remedy.
- Procedural time-bar periods (such as the Notice of Claim, or agreed periods for raising settlement objections) and the limitation period are two separate mechanisms; they cannot substitute for each other, and both lines must be held.
Applicability boundaries
This card states the general limitation rules; the ordinary three-year period applies to claims to construction payment where no special limitation rule exists, and special statutory periods prevail where the law provides them. The limitation period differs from a peremptory period: the 18-month period for exercising the priority right of payment for construction works prices is a peremptory period, not subject to suspension, interruption or extension (see the priority-right card). Expiry of the limitation period does not extinguish the substantive right; its legal effect depends on whether the obligor raises the defence.
Further reading
- Civil Code Article 188 (ordinary three-year period, starting point, twenty-year maximum protection period); Article 3 of the Provisions of the Supreme People's Court on Several Issues Concerning the Application of the Limitation System in the Trial of Civil Cases (Fa Shi [2008] No. 11, as amended in 2020) (consequences at second instance or retrial where no defence was raised at first instance); for the distinction from procedural time bars on construction claims and settlement objections, see the card on the evolution of the 28-day claim period.
Keywords
- 诉讼时效
- 三年诉讼时效
- 时效抗辩
- 一审提出
- 民法典第188条
- 工程款请求权
- 除斥期间