Consequences of contractor-caused delay in completion: the defined term delay damages and its calculation base, the six classes of claimable events and eight heads of loss open to the employer, and the four optional remedies (extended defects warranty / extra costs / delay damages / liquidated damages)

Delay damages are the sums that, where the contractor fails to construct at the planned progress of the contract works so that the actual duration exceeds the contract duration or, for works completed in sections, the contract duration of the sectional works (including extensions of time granted by the employer), the contractor must pay the employer as compensation under the contract; for works completed and handed over in sections they are calculated separately from the delay time of each section and the method agreed in the contract (GB/T 50500-2024 Clause 2.0.33). Contractor-caused delay earns no extension of time; the employer may claim time and (or) cost under the six classes of events in Clause 8.11.18 and, under Clause 8.11.19, choose one or more of: extending the defects warranty period, requiring payment of extra costs, requiring payment of delay damages, and requiring liquidated damages as agreed in the contract.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.33条(误期赔偿费)、第8.11.18条(承包人原因的反索赔)、第8.11.19条(发包人可选的补偿方式)
  • GF-2017-0201《建设工程施工合同(示范文本)》通用条款7.5.2(承包人原因导致工期延误/逾期竣工违约金)、7.8.2(承包人原因暂停施工)
  • GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.13.2、9.13.3条(已废止,仅供历史合同对照)

Topic positioning

This card defines the legal meaning of the term 'delay damages' and sets out, for delay caused by the contractor, what claims the employer may raise and which remedies it may choose alone or in combination. Based on GB/T 50500-2024, the China national pricing standard for BOQ, Clause 2.0.33 (term), Clause 8.11.18 (claim events and losses caused by the contractor) and Clause 8.11.19 (remedies), compared with Clause 7.5.2 of GF-2017-0201, the Model Construction Contract, on liquidated damages for late completion.

Core conclusions

I. Definition of delay damages (Clause 2.0.33)

The sums that, where the contractor fails to construct at the planned progress of the contract works so that the actual duration exceeds the contract duration or, for works completed in sections, the contract duration of the sectional works (including extensions of time granted by the employer), the contractor must pay the employer as compensation under the contract. For works contractually completed and handed over in sections, delay damages are the compensation calculated from the delay time of the relevant works as agreed in the contract; for works so completed and handed over, delay damages shall be calculated separately from the delay time occurring in each sectional completion and handover and the calculation method of delay damages agreed in the contract. Key point: the calculation base is 'the days in excess of the contract duration (approved extensions included)' - approved extensions do not count as delay; sectional works are calculated section by section.

II. Six claimable event classes for contractor causes (Clause 8.11.18)

Where the following events occur for reasons attributable to the contractor and cause delay and (or) economic loss to the employer, the employer may raise one or more claims according to the time of delay and (or) the economic loss:

  1. extra costs or expenditures incurred by the employer because the contractor failed to perform its obligations as contractor or to execute the employer's instructions for the works as agreed in the contract, and the like;
  2. losses caused to the employer by the contractor's failure to perform, as required by the contract, the main contractor's attendance and coordination provisions for the employer-supplied materials, the nominated specialist subcontract works and the specialist works directly awarded;
  3. fines paid by the employer to government departments or compensation paid to third parties as a result of events attributable to the contractor;
  4. losses caused to the employer by delay in the contract works for reasons attributable to the contractor;
  5. losses caused to the employer by the completed works of the contractor failing to meet the requirements agreed in the contract;
  6. other losses beyond the above that the employer can prove.

The eight heads of loss listed in the same clause (borne by the contractor): (1) the excess, where the contractor fails to carry out the relevant works as agreed in the contract so that the employer must engage another contractor to complete them, of the resulting contracting cost over the contract price of the relevant works within the total contract price; (2) the excess, where the contractor refuses without reasonable justification to carry out the variation instructed by the employer so that the employer engages another contractor to complete the variation, of the resulting variation cost over the cost agreed in the contract; (3) costs incurred where the employer pays on the contractor's behalf the fees and fines payable to government departments that the contractor failed to pay as agreed in the contract; (4) costs incurred where the employer pays on the contractor's behalf the compensation to third parties that the contractor failed to pay as agreed in the contract; (5) the cost of repairing the affected surrounding works caused by the contractor removing or re-executing works that fail the quality standards agreed in the contract, and the losses caused to the employer thereby; (6) the losses caused to the employer by the main contractor's failure to perform, as agreed in the contract, its duty to manage and coordinate the suppliers of the employer-supplied (free-issue) materials; (7) the losses caused to the employer by the main contractor's failure to perform, as agreed in the contract, its duties of management, coordination and attendance towards the nominated subcontractors and its duties of coordination and attendance towards the directly awarded specialist works; (8) the losses caused to the employer by the contractor's failure to perform any other duty as agreed in the contract. These heads of loss are all measured as 'the excess over the contract price' or 'the costs the employer paid on the contractor's behalf', not as a second charge on the contract price.

III. Remedies open to the employer (Clause 8.11.19)

For losses caused to the employer for reasons attributable to the contractor, the employer may choose one or more of the following remedies:

  1. Extending the defects warranty period;
  2. Requiring the contractor to pay the extra costs incurred from the affected events;
  3. Requiring the contractor to pay delay damages;
  4. Requiring the contractor to pay liquidated damages as agreed in the contract. 'One or more' means the four remedies may be stacked, but the same loss may not be compensated twice (where delay damages and liquidated damages for late completion point to the same facts of delay, their nature and caps are determined by the contract, avoiding double penalties).

IV. The model contract position (GF-2017-0201)

Clause 7.5.2 (delay caused by the contractor): where the delay is caused by the contractor, the special conditions of the contract may agree the calculation method and the cap of the liquidated damages for late completion; after the contractor pays the liquidated damages for late completion, the contractor is not released from its duty to continue and complete the works and to remedy defects. Clause 7.8.2 (suspension caused by the contractor): where the suspension is caused by the contractor, the contractor bears the added costs and (or) the delay thereby, and if the contractor still fails to resume the works within 84 days after receiving the supervisor's resumption instruction, it is treated as the event, agreed in item (7) of sub-clause 16.2.1 [events of contractor default], that the contractor is unable to continue performing the contract. Clause 7.5.1 is the mirror provision for delay caused by the employer (the employer bears the delayed time and (or) the added costs and pays reasonable profit); the two form the two ends of the attribution of delay - fix the responsibility first.

Applicable boundaries

  1. The nature and amount of delay damages are matters for the contract (the calculation method and cap agreed in the contract); GB/T 50500-2024 gives only the definition of the term and the employer's optional remedies, prescribes no rate or daily price, and absent agreement no rate may simply be applied.
  2. In counting the days of delay, first deduct the extensions granted by the employer (including the days that should be extended as determined by the critical path method) and the time already extended by excusable events such as force majeure or government control; for extensions not granted but due under the contract and the law, establish them in the claims procedure before counting them as deductions.
  3. Clause 8.11.18 addresses 'contractor-cause' events and mirrors the claims for employer causes (Clauses 8.11.9 to 8.11.11); use them as a pair. Employer claims are equally bound by the time limits of the claims procedure (the time limit system of Clauses 8.11.3 and 8.11.5 applies symmetrically to the claim reports and replies of both parties).
  4. GB 50500-2013 has been replaced by GB/T 50500-2024; the clause numbers of the old edition cited in historic contracts (Section 9.13 claims; Section 9.14 site instruction records) should be mapped old-to-new before use.
  5. Whether delay damages and liquidated damages for late completion can coexist depends on the wording of the contract; it is a question of interpretation and they should not be stacked as a rule.

Further reading

  • GB/T 50500-2024 Clause 2.0.33 (term 'delay damages'), Clause 8.11.18 (claim events caused by the contractor and the eight heads of loss), Clause 8.11.19 (the four remedies: extended defects warranty period, extra costs, delay damages, liquidated damages); compare Clauses 8.11.3 and 8.11.5 (claims procedure and reply time limits) and Clause 8.11.8 (critical path determination of the days of extension).
  • GF-2017-0201 Model Construction Contract, general conditions 7.5.1 (delay caused by the employer), 7.5.2 (delay caused by the contractor and the liquidated damages for late completion), 7.8.2 (suspension caused by the contractor; the consequences of failing to resume within 84 days), 16.2.1 (events of contractor default).
  • Companion reading: Civil Code Article 577 (liability for breach) and Article 585 (liquidated damages and their adjustment).

Keywords

  • 误期赔偿费
  • delay damages
  • 逾期竣工违约金
  • 承包人原因延误
  • 反索赔
  • 延长质量缺陷保修期
  • 补偿方式