Establishing and continuously updating the contract risk register (landing the risk register in contract performance management)
The contract risk register is the "risk record" defined in GB 50652-2011 (risk name, level, treatment measures, control effect) landed in the contract management context: it is built following the four procedures of GB/T 50326-2017 risk management (identification → assessment → response → monitoring), with fields in four groups — risk identity / assessment / response / monitoring; it is maintained by event-driven updates (variations, site instructions / variation records, claims, new risks) plus periodic review (quarterly, with higher frequency for major risks), and risk levels are adjusted dynamically.
Applicable Codes
- GB 50652-2011 城市轨道交通地下工程建设风险管理规范
- GB/T 50326-2017 建设工程项目管理规范
- GB/T 50358-2017 建设项目工程总承包管理规范
- RISN-TG 012-2011 建设工程项目经理执业导则
- GB/T 50927-2013 大中型水电工程建设风险管理规范
Topic Positioning
This card covers how to establish and continuously update a contract risk register in the performance stage: positioning, field design, update mechanism, and the underlying standards — directly usable for contract risk management of main (general) contracting, EPC, and similar projects.
Core Conclusions
① Positioning: the contract risk register is the "risk record" of GB 50652-2011 Clause 2.0.14 (tracking and managing identified risks: risk name, risk level, treatment measures, and control effect) landed in the contract management context; it complements the dynamic contract management ledger (T/SDJZXH 001-2021: entity name, signing date, contract lump sum, execution period, and actual performance dynamics) — the former records "events", the latter records "contracts". ② Establishment follows the four procedures of GB/T 50326-2017 Clause 17.1.2: identification (RISN-TG 012-2011 Clause 16.2.2: in-contract risks are collected from tender documents, contract documents, techno-economic data, and site conditions; out-of-contract risks from policy, weather, and economic information; GB/T 50358-2017 Clause 9.2.1 requires coverage of design, procurement, construction, and commissioning stages) → assessment (level set by likelihood × loss) → response (measures, responsible post, time limit) → monitoring. ③ Fields in four groups: risk identity (number, name, category, stage, factors, location/signs — refer to GB 50652-2011 Appendix B), assessment (likelihood, loss, level), response (measures, responsibility, time limit, resources), monitoring (frequency, current status, control effect, updater/date). ④ Continuous updating: event-driven — immediately supplement and revise upon variations, site instructions / variation records, claims, price fluctuations, or new policies (DB37/T 5096-2017 Clause 12.2.1 "supplement and adjust in a timely manner"); periodic review — GB/T 50927-2013 Clause 8.3.2 quarterly monitoring, with higher frequency for major risks and frequency scaling with level; per GB/T 50358-2017 Clause 9.4.2, monitor dynamically, update prevention levels, issue risk warnings, and assess and tally losses.
Applicable Boundaries
Applies to the post-signing performance stage; the register is a management tool, not a statutory document, and fields may be tailored per project; risk-level classifications (I–IV or major/significant/general/low) follow enterprise or contract agreements; the monitoring process shall leave records, and the frequency for major risks must be increased.
Further Reading
GB 50652-2011 Clauses 2.0.14, 3.3.4 and Appendix B; GB/T 50326-2017 Clauses 17.1.2, 17.6.2; GB/T 50358-2017 Clauses 9.2.1, 9.4.2; RISN-TG 012-2011 Clause 16.2.2; GB/T 50927-2013 Clause 8.3.2; DB37/T 5096-2017 Clause 12.2.1; T/SDJZXH 001-2021 Clause 7.3.1. For identification methods see also the card "Four-layer identification of high-risk clauses in tender documents and bid pricing"; for update triggers see the card "28-day two-node claim time limits".
Keywords
- 合同风险台账
- 风险记录
- risk register
- 合同风险管理
- 风险登记
- 风险管理程序
- 风险监控
- 动态合同管理台账