Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-30

The quantified recognition thresholds of high formwork support systems and their load-conversion basis, the erection-height limits of support structures, and the formwork pricing tie-in once recognised as high formwork

A high formwork support system is recognised (HNLJQ-SGJB 001-2021 clause 3.0.1) where any one holds: erection height plus member depth 8 m or more; beam calculated span 18 m or more; slab thickness 320 mm or more; beam cross-section 0.53 m2 or more; cantilevers over 1000 mm long carried on rolled-steel cantilevers. The 320 mm and 0.53 m2 values back-solve from a total construction load of 15 kN/m2 and a concentrated line load of 20 kN/m (S = 1.3 x (0.75 + 25.1h) + 1.5 x 2.5 = 15 gives h = 314.8, taken as 320; S = 1.3 x (0.75b + 25.5bh) + 1.5 x 2.5b = 20 gives A = 0.528, taken as 0.53 m2). Support-structure erection heights (JGJ 300-2013 clause 5.1.1): frame-type preferably not over 40 m, truss-type not over 50 m - beyond, special design. Pricing tie-in (Jiangsu 2024 (2026 edition in the source data)): for high formwork, the support part executes the disc-lock steel-tube full propping items of the matching height; the members' formwork executes the coupler-tube items for clear propping heights within 8 m, labour x 0.6, deducting the tube props and clips within.

Applicable Codes

  • HNLJQ-SGJB 001-2021 高大模板支撑系统施工方案编制与实施技术标准 第3.0.1条
  • 建办质〔2018〕31号 住房城乡建设部办公厅关于实施《危险性较大的分部分项工程安全管理规定》有关问题的通知
  • JGJ 300-2013 建筑施工临时支撑结构技术规范 第5.1.1条
  • JGJ 162 建筑施工模板安全技术规范
  • GB 50068 建筑结构可靠性设计统一标准
  • 江苏省建筑与装饰工程消耗量(2026版)高支模子目

Topic Positioning

The quantified recognition thresholds of high formwork support systems, their load-conversion basis, the support-structure erection-height limits (JGJ 300-2013) and the formwork pricing tie-in once recognised - for judging sub-divisional works involving significant hazards (and the beyond-scale class) and setting the formwork support items accordingly.

Core Conclusions

1. Recognition thresholds (HNLJQ-SGJB 001-2021 clause 3.0.1, after Jianbanzhi [2018] No. 31) High formwork support systems include: 1 support systems for concrete members whose erection height plus member depth reaches or exceeds 8 m; 2 those for concrete beams whose calculated span reaches or exceeds 18 m; 3 those for concrete slabs 320 mm thick or more; 4 those for concrete beams of cross-section 0.53 m2 or more; 5 support systems for cantilevered structures projecting over 1000 mm on rolled-steel cantilevers. Application notes: for pitched roofs the height is the ridge erection height plus slab thickness; the calculated span approximates the distance between beam support centres, i.e. the grid lines; "slab" means solid slabs - voided floors compute loads for the actual case; "rolled steel" chiefly covers I-sections, channels, angles, rounds, squares and Bailey beams - support systems erected on cantilevered rolled steel are rolled-steel cantilever support systems.

2. Load-conversion basis of the thresholds Per the load values and combinations of JGJ 162 (Technical Code for Safety of Formwork in Construction), JGJ 300 and GB 50068 (unified reliability standard): setting the total construction load of a slab of thickness h at 15 kN/m2, S = 1.3 x (0.75 + 25.1h) + 1.5 x 2.5 = 15 gives h = 314.8 mm, taken 320 mm; setting the concentrated line load of a beam of section A at 20 kN/m, S = 1.3 x (0.75b + 25.5bh) + 1.5 x 2.5b = 20 gives A = bh = 0.528 m2, taken 0.53 m2.

3. Erection-height limits (JGJ 300-2013 clause 5.1.1) 1 Frame-type support structures preferably not over 40 m; beyond 40 m, special design. 2 Truss-type preferably not over 50 m; beyond 50 m, special design.

4. Formwork pricing tie-in (Jiangsu 2024 consumption standard, 2026 edition in the source data) Where the construction codes classify work as high formwork, the support part of the formwork executes the disc-lock steel-tube full-propping items of the matching height; the cast-in-place members' formwork executes the corresponding items for coupler-tube propping with clear height within 8 m, labour x 0.6, deducting the tube props and clips therein.

Applicability Boundaries

  • HNLJQ-SGJB 001-2021 is a local (Hunan) technical standard refining and tightening the national thresholds of Annex 2 to Jianbanzhi [2018] No. 31 ("propping height 8 m or more, or span 18 m or more") by adding slab 320 mm, beam section 0.53 m2 and rolled-steel cantilever 1000 mm; local rules may only tighten or extend, never relax - stack further local checks where they exist.
  • The recognition thresholds pair with the "beyond-scale hazardous works" tests and the special method statement / expert-review procedures; recognition does not by itself trigger any pricing adjustment.
  • The 320 mm and 0.53 m2 values back-solve from 15 kN/m2 and 20 kN/m and may shift with revisions of JGJ 162, JGJ 300 and GB 50068.
  • Section 4 is Jiangsu 2024 pricing; other regions band and factor differently - check locally; propping-height and high-formwork measurement rules sit on the formwork measurement cards.

Further Reading

  • HNLJQ-SGJB 001-2021 Technical Standard for Compiling and Implementing High Formwork Support System Construction Schemes, clause 3.0.1 and commentary
  • MHURD notice on implementing the Safety Management of Sub-Divisional Works Involving Significant Hazards (Jianbanzhi [2018] No. 31), annexes 1 and 2
  • JGJ 300-2013 Technical Code for Temporary Support Structures in Construction, clause 5.1.1; JGJ 162; GB 50068
  • Jiangsu building and decoration consumption standard (2026 edition in the source data), high-formwork disc-lock full-propping items and the formwork labour-factor provisions

Keywords