Procedure for applying prestress (pre-axial force) to steel struts: jack calibration -> node inspection -> symmetric synchronized staged loading -> hold then lock -> weld fix ends -> monitor and re-apply
Prestressing of steel struts follows the procedure "calibrate equipment -> check strut nodes -> jacks symmetric, equidistant, synchronized, staged loading (hold 10min per stage) -> load to design, hold 10min, lock -> weld strut ends to steel wales/embedded plates -> monitor, re-apply on pressure loss", per the core basis JGJ 120-2012 Clause 4.10.6.
Applicable Codes
- JGJ 120-2012 建筑基坑支护技术规程 第4.10.6条
- DB11/T 1832.1-2021 建筑工程施工工艺规程 第1部分:地基基础工程 第29.4.10条
- DB62/T 3019-2018 建筑地基基础工程施工工艺规程 第6.3.6条
Topic Positioning
The standard procedure and hard technical requirements for applying prestress/preloading to steel struts (pre-loaded axial struts) in building excavation support - JGJ 120-2012 Clause 4.10.6 as the procedural backbone, with process details from the Beijing and Gansu local specifications.
Core Conclusions
Apply prestress in the following order (not to be reversed):
- Equipment preparation and calibration: jacks used to load struts shall have reliable, accurate metering (JGJ 120-2012 Clause 4.10.6 item 1); select pump and jack per the design axial force; pump and jack must be calibrated (DB62/T 3019-2018 Clause 6.3.6 item 1).
- Node inspection after strut installation: after installing struts, promptly inspect all node connections and confirm compliance before prestressing (DB62/T 3019-2018 Clause 6.3.6 item 2); after instruments are installed and commissioned, load stepwise to the design prestress, checking connection stability and firmness - stop on any anomaly, eliminate the hazard, then continue (DB11/T 1832.1-2021 Clause 29.4.10 item 1).
- Jack layout and staged loading: the resultant of jack forces shall coincide with the strut axis; jacks shall be placed symmetric and equidistant on both sides of the axis and apply pressure synchronously (JGJ 120-2012 Clause 4.10.6 item 2); pressure shall be applied in stages, holding each stage steady for 10min before the next (item 3); when preloading, load symmetrically and synchronously on both sides in stages of 10% of design, observe deformation during loading, and stop immediately if actual deformation exceeds design, then resolve with the designer (DB62/T 3019-2018 Clause 6.3.6 item 3).
- Hold then lock: after reaching the design value, hold pressure steady 10min before locking at the design prestress (JGJ 120-2012 Clause 4.10.6 item 3); re-inspect all connections before locking (DB11/T 1832.1-2021 Clause 29.4.10 item 2).
- Post-lock fixing: after locking, weld strut ends to steel wales or embedded plates; struts are usually tied together with tie members (small-section I-beams or channels combined) fixed to struts with steel clamps to ensure overall stability (DB62/T 3019-2018 Clause 6.3.6 items 4-5).
- Monitoring and re-application: during loading watch wall/pile deformation and upper struts to keep forces even (DB11/T 1832.1-2021 Clause 29.4.10); when monitored strut pressure is lost, re-apply prestress (JGJ 120-2012 Clause 4.10.6 item 5); large day-night temperature swings causing prestress loss shall be corrected per design (DB11/T 1832.1-2021 Clause 29.4.10 item 3); keep construction records throughout (item 4).
Anomalies: if weld cracking or local buckling occurs during loading, release the pressure, strengthen the weak points, and only then continue (JGJ 120-2012 Clause 4.10.6 item 4).
One-line summary: calibrate -> check nodes -> symmetric synchronized staged loading (10min hold per stage) -> hold 10min at design then lock -> weld ends -> monitor losses and re-apply.
Applicable Boundaries
- Applies to applying pre-axial force to steel struts (pipe/section struts) in building excavation support systems; prestress values and stage sizes follow the design documents.
- JGJ 120-2012 "Technical specification for retaining and protection of building foundation excavations" is the nationwide industry standard and the core procedural basis (staged loading, 10min hold per stage, hold 10min then lock, etc.).
- DB11/T 1832.1-2021 Clause 29.4.10 is the current Beijing local standard, consistent with JGJ 120 and adding records and temperature-correction; DB62/T 3019-2018 Clause 6.3.6 (Gansu) is a process reference only (deformation observation, 10% stages, end welding) and is not the applicable basis outside Gansu.
- Covers only prestress application - not strut design, positioning, or removal.
Further Reading
- JGJ 120-2012 Clause 4.10.6 (Chapter 4 retaining structures) - all hard procedural requirements.
- DB11/T 1832.1-2021 Clause 29.4.10 (Chapter 29 steel struts) - current Beijing procedure.
- DB62/T 3019-2018 Clause 6.3.6 (Chapter 6 excavation support) - process detail reference.
- Deep-excavation steel-strut work is a dangerous larger-part-division work; for special construction plans see Jianbanzhi [2021] No. 48 "Guidelines for preparing special construction plans" and JGJ 311-2013 "Technical code for safety of building deep excavation engineering".
Keywords
- 钢支撑
- 预压力
- 预加轴力
- 预顶力
- 千斤顶
- 分级加载
- excavation retention (support) system
- JGJ 120-2012