Railway signalling through-earth-wire trenching "additional part" items: XY-34~XY-43 tiering, distinction from ordinary cable-trench dig-and-fill, and quantity computation (TB/T 10827-2024 Volume 6, Chapter 1, Section 2)

The "additional part" of through-earth-wire trenching uses XY-34~XY-43 of TB/T 10827-2024 Volume 6, Chapter 1, Section 2, unit hm (hundred metres), work content only "excavate, clear" (no backfill). Tiering: first by position — "below cable-trench floor" (XY-34~XY-41) and "under cable trough" (XY-42~XY-43) — then by ground class x depth: ordinary soil/hard soil and soft rock have 0.8 m and 1.3 m tiers; sub-hard and hard rock only 0.6 m; under-trough only 0.6 m. Ground classes per TB 10012 "Code for Railway Engineering Geological Investigation". Quantities per the design length along the wire's laying route; depth tier per the design embedment depth. It is the second longitudinal segment of the same trench as Section 1's ordinary dig-and-fill (XY-1~XY-33), non-overlapping: the ordinary items include backfill, the additional part does not.

Applicable Codes

  • TB/T 10827-2024 · Budget Quota of Railway Engineering (Volume 6: Signaling Works) Ch. 1第二节(XY-34~XY-43)及册说明
  • TB 10012 · Code for Geological Investigation of Railway Engineering

Topic Positioning

The application rules for the "additional part" of trenching for through earth wires in railway signalling (XY-34~XY-43): tiering dimensions, distinction from ordinary cable-trench dig-and-fill, and quantity basis. Per the item tables and volume notes of Chapter 1, Section 2, TB/T 10827-2024 Volume 6.

Core Conclusions

  1. Dedicated items: the additional part sits in Chapter 1 "cable trenches", Section 2, items XY-34~XY-43, unit hm (hundred metres), work content "excavate, clear" — excavation and clearing only, no backfill.
  2. Tiering (two-step item selection): first by laying position — the "below cable-trench floor" series (XY-34~XY-41, wire buried below the trench floor) and the "under cable trough" series (XY-42~XY-43); then by ground class x depth tier. Depth rules: ordinary soil/hard soil/soft rock have 0.8 m and 1.3 m tiers (XY-34~XY-39); sub-hard rock and hard rock have only the 0.6 m tier (XY-40, XY-41); under trough only 0.6 m (XY-42, XY-43). The base price is dominated by labour cost, with plant cost zero and materials limited to minor sundries.
  3. Distinction from ordinary dig-and-fill: the two are longitudinal segments of the same trench, each covering its own stretch, non-overlapping. Section 1's XY-1~XY-33 (ordinary cable-trench dig-and-fill) serves the signal cable trench itself, tiered by cable count (1-5/6-10/11-20) x ground class x trench depth, with content covering line-marking, excavation of the cable trench and joint pits, backfill and clearing; Section 2's XY-34~XY-43 serves the deepened excavation for the through earth wire (buried below the trench floor / under the trough), excavation and clearing only — backfill lives only in the Section 1 items: neither double-count the dig-and-fill nor omit the backfill.
  4. Quantity computation: measured in hm (hundred metres), taken from the design length of the through-earth-wire laying route (i.e. the length of the deepened segment); the depth tier follows the design embedment depth — burial 0.8 m below the floor takes the 0.8 m tier, 1.3 m takes the 1.3 m tier, rock sections take the 0.6 m tier, under-trough takes the 0.6 m tier. This volume gives no separate volume-conversion rule for the "additional part" — count straight in hundred metres.
  5. Ground classes: determined per TB 10012 "Code for Railway Engineering Geological Investigation" (Volume 6, note 2).
  6. Full pricing chain: one through-earth-wire installation is usually split into three independent BOQ items, each priced separately — ordinary cable-trench dig-and-fill (XY-1~XY-33) + additional part of through-earth-wire trenching (XY-34~XY-43) + through-earth-wire laying (lightning protection and grounding chapter).

Applicable Boundaries

  • Applies only to pricing the deepened trenching for burying railway signalling through earth wires (below the cable-trench floor or under the cable trough); the trench body's dig-and-fill must use Section 1's XY-1~XY-33 and is not covered by this group of items.
  • This group of items excludes backfill; where the deepened segment requires backfill it must be considered separately under the quota norms and must not be omitted.
  • The ground class must be determined per TB 10012 before selecting the tier; in existing-railway reconstruction, the "detecting underground cables" quota applies only where newly laid cables require detection of live buried cables (volume note 3).
  • The "laying concrete cable troughs" items exclude trough fabrication — they must be used in combination with Section 5 "precast concrete cable troughs and covers" (volume note 4).
  • Base prices are base-period rates; at the time of preparation they must be adjusted for cost fluctuation against the local published price information (government guidance prices) and are not to be used directly as preparation-period rates.

Further Reading

  • TB/T 10827-2024 Volume 6: Chapter 1, Section 1 (XY-1~XY-33 cable-trench dig-and-fill), Section 2 (XY-34~XY-43 additional part of through-earth-wire trenching) item tables, and volume notes 1-4 (scope of preparation, basis for ground classification, limit on the "detecting underground cables" item, cable-trough pairing rule).
  • Basis for ground classification: TB 10012 "Code for Railway Engineering Geological Investigation".
  • Other application rules in the same volume (non-standard equipment listed separately per design quantities, demolition factors 0.7/0.5, bracketed materials listed separately) are in the volume's general notes and are to be used together with this card.