Four-layer AI review method for checking the consistency of the bill of quantities (BOQ) against the drawings (screening for BOQ errors and omissions)

Any inconsistency between the BOQ and the drawings constitutes "errors and omissions in the BOQ" (GB/T 50500-2024 clause 2.0.27: redundant items, omitted or erroneous items, non-conforming item descriptions, quantity deviations). AI review is organised into four layers by degree of automation: the numerical layer re-calculates quantities under the applicable measurement standard and compares them (fully automatic); the textual layer semantically compares item descriptions with the build-ups shown on the drawings (semi-automatic); the item-listing layer compares listings to find omissions and redundant items (manual determination); the version layer checks drawing numbers, versions and design changes (rule-based automatic). Responsibility for defects: under a re-measurable (unit-rate) contract, defects in the divisional and sub-divisional work items are the employer's responsibility and are adjusted under clause 8.2; under a lump-sum contract they are the contractor's responsibility and no adjustment is made; preliminary (measures) items are in all cases the contractor's responsibility.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
  • GB 50860-2013 构筑物工程工程量计算规范
  • GB 50861-2013 城市轨道交通工程工程量计算规范
  • T/ZBD 100.5-2023 建设工程结算审核作业指引

Topic Positioning

This card sets out a layered AI method for reviewing the consistency of the bill of quantities with the tender drawings: taking the "BOQ errors and omissions" defined in GB/T 50500-2024 (redundant items, omissions, non-conforming item descriptions, quantity deviations) as the detection target, the review is implemented in four layers by degree of automation, for use by the employer and contractor sides in screening BOQ quality at the tendering stage.

Core Conclusions

The AI review takes the tender drawings (including notes, details and standard-atlas references) as the benchmark and checks them against the five BOQ elements (code, name, item description, unit of measurement, work content). The four detection layers:

  1. Numerical layer (fully automatic): extract element geometry from CAD/BIM, re-calculate quantities under the measurement rules of the applicable measurement standard for the discipline (BOQ quantity = net quantity), compare with the BOQ, and flag quantity-deviation suspects where the deviation exceeds the agreed threshold (e.g. ±3%); high-volume, high-value items such as earthworks, concrete and rebar are checked in full as a priority.
  2. Textual layer (semi-automatic): semantically compare the drawing specification schedules and material schedules with the BOQ item descriptions (location, strength grade, specification, build-up) to identify non-conforming descriptions; references of the "see XX standard atlas" type must also be parsed for completeness.
  3. Item-listing layer (manual determination): compare the list of elements shown on the drawings with the BOQ listings; every difference is a candidate omission or redundant item, cross-checked with the tick-list of divisional items in the appendix to the measurement standard.
  4. Version layer (rule-based automatic): check the version numbers in the drawing register and the completeness of drawing numbers, and verify whether drawing-review comments and design changes have been reflected in the tender drawings. Where defects are found, they are dealt with by responsibility: defects in divisional and sub-divisional items under a re-measurable (unit-rate) contract are the employer's responsibility and are adjusted at settlement; under a lump-sum contract they are the contractor's responsibility and no adjustment is made; preliminary (measures) items are in all cases the contractor's responsibility.

Applicable Boundaries

Applicable to BOQ review at the tender stage. AI can only detect differences that are digitisable; conformity of item descriptions and whether an omission falls within the tender scope must be determined manually; each discipline must re-calculate under its own measurement standard; deviation thresholds and sampling ratios should follow the project agreement; under lump-sum contracts the contractor bears the quantity differences even after its own review.

Further Reading

GB/T 50500-2024 clause 2.0.27 (definition of BOQ errors), clause 4.1.7 (elements of preparation), 3.3.3/6.1.7/Section 8.2 (risk and adjustment); GB/T 50854-2024 clause 4.1.2 (item description); GB 50860-2013 clauses 3.0.1 and 4.2.5 (basis of measurement and mandatory measurement rules); GB 50861-2013 clause 3.0.4 (rounding of measurements); T/ZBD 100.5-2023 clause 3.1.8 (design-change confirmation and pricing).