Railway 2024 quotas: the station-track additional rail waste items (GY-232~234) — application rules and waste mechanics; main line no addition, station tracks add (TB/T 10825-2024 Volume 4, Chapter 1 note 18)

In the jointed-track material quotas, the rail's site handling and operating waste is compiled at 0.1% and applies to the main line only (already embedded — no separate booking on main lines); for station tracks add 0.1% (about 0.2% total), and for new terminal marshalling yards 0.2% (about 0.3% total), using the station-track additional rail waste quotas GY-232/233/234 (unit km, material cost only). Waste = per-km double-track rail weight x the added rate, rounded to whole rails.

Applicable Codes

  • TB/T 10825-2024 铁路工程预算定额 Vol. 4 轨道工程 Ch. 1 铺轨 册说明第十八条、第九条、第二条、第十九条
  • TB/T 10825-2024 Ch. 1 第三节 有缝线路 三、轨料 (六) 站线增加钢轨损耗 GY-232~234

Topic Positioning

The application rules of the "station-track additional rail waste" quota (GY-232~234) in Chapter 1 track laying of TB/T 10825-2024 Volume 4: why main-line laying adds nothing, why station tracks add waste, and how the waste is determined. For budgeting and auditing jointed-track station-track laying under the railway 2024 quotas.

Core Conclusions

Textual basis (Chapter 1 note 18, as written): "The rail in the jointed-track material quotas is compiled with a site handling and operating waste rate of 0.1%, applicable to the main line only. When used for station tracks and new terminal marshalling yards, the station-track additional rail waste quotas must add 0.1% and 0.2% respectively."

  • Why the main line adds nothing: its 0.1% waste is already embedded in the jointed-track material quotas — direct application includes rail waste; nothing is missed; station tracks (tight curves, many turnouts, frequent short rails and sawing, many joints) waste more than main line, and the "additional rail waste" quota makes up the difference.
  • Totals: station tracks 0.1% added -> about 0.2% total; new terminal marshalling yards 0.2% added -> about 0.3% total.
  • Companion clauses: note 9 — "the rail in the CWR material quotas is compiled with a site handling and operating waste rate of 0.4%" (higher, and already included); note 19 — "the jointed-track material quotas include the joint bars and bolts needed for the extra joints caused by laying short rails"; note 2 — "machine laying, manual laying, and long-rail laying quotas exclude rails, sleepers, fastenings, and joint bars — they must be used with the matching material quotas".

Items (Chapter 1 Section 3 jointed track, 3. materials, (6) station-track additional rail waste): unit km; work content "rail waste" only — material cost only, no labor or plant; three steps:

  • GY-232 additional rail waste +0.1%, 50 kg rail, 12.5 m length;
  • GY-233 +0.1%, 50 kg rail, 25 m;
  • GY-234 +0.1%, 60 kg rail, 25 m.

Waste mechanics: waste = double-track rail weight per km x the added rate, rounded to whole rails. Check: 1 km of double 50 kg/m rail = 100,000 kg; 0.1% = 100 kg = 0.16 rails/km of 12.5 m (625 kg each) or 0.08 rails/km of 25 m (1,250 kg); 1 km of double 60 kg/m rail = 120,000 kg; 0.1% = 120 kg = 0.08 rails/km of 25 m (1,500 kg). The 0.2% marshalling-yard case: only the 0.1% step exists; for 0.2%, book double the quota consumption (waste per km doubled, still material only).

Compiling practice: for station tracks, book the jointed-track material quota per design quantity (e.g., the GY-20x series) plus GY-232/233/234, the latter measured by the same track-km as the material quota; select the step by rail type and length (50 kg/12.5 m, 50 kg/25 m, 60 kg/25 m).

Applicable Boundaries

  • The rule targets jointed-track material quotas. Station tracks laid as CWR follow note 9's 0.4% (already included) — this "additional rail waste" quota does not apply.
  • "0.1% main line only" is the material quota's compilation caliber; station tracks and new marshalling yards add — rather than recompute — to totals of about 0.2% and 0.3%.
  • The additional-waste quota carries material cost only (zero labor and plant) — no labor or plant may be added.
  • The laying quotas (machine/manual/long-rail) themselves exclude rails, sleepers, fastenings, joint bars — pair with the matching material quotas; closure-gap sawing and rail drilling are also excluded and follow Chapter 6 per design quantities.
  • Rail-material transport is compiled for double-locomotive haul with grades comprehended — locomotive consumptions must not be adjusted for grade (note 10).

Further Reading

  • TB/T 10825-2024 Volume 4, Chapter 1 notes: esp. 18 (station-track additional rail waste); companion 2 (laying excludes materials), 6 (grade/tunnel factors), 9 (CWR 0.4% waste), 10 (rail-material transport), 19 (short-rail joint bars and bolts included).
  • Chapter 1 Section 3 jointed track, 3. materials, (6) station-track additional rail waste: GY-232, GY-233, GY-234.
  • Compare the other material items of the same section (jointed-track materials GY-20x series) to see the "material quota + waste addition" combination.

Keywords

  • 站线增加钢轨损耗
  • 有缝线路轨料
  • 钢轨损耗率
  • TB/T 10825-2024
  • GY-232
  • GY-233
  • GY-234
  • 轨道工程预算定额
  • 铺轨定额