GB 51004-2015 method for estimating single-rig 24 h progress of deep soil-mixing (cement) columns: converting the 100 m³/24 h cap by cross-section, plus process-time derivation for two-injection three-mixing and triple-shaft
Converting the GB 51004-2015 Clause 4.10.2 cap "mixing volume per rig within 24 h shall not exceed 100 m³": single-shaft d500 ~= 509 m/24 h; d600 ~= 354 m/24 h; double-shaft d700@500 ~= 142 m/24 h; triple-shaft d650@450 ~= 115 m/24 h; d850@600 ~= 67 m/24 h. Process time derived at code speed limits: single/double-shaft two-injection three-mixing about 9 min/m -> theoretical ~= 160 m/24 h (practical ~= 128 m); triple-shaft two-injection two-mixing about 4 min/m -> theoretical ~= 360 m/24 h (practical ~= 288 m). Practical experience: single/double shaft 100-150 m; double-shaft d700 about 100-140 m; triple-shaft d650 about 120-200 m; triple-shaft d850 about 150-250 m (slurry production capacity is often the bottleneck). A single 8 h shift is roughly the 24 h value divided by 3.
Applicable Codes
- GB 51004-2015 · Code for Construction of Building Foundation 第4.10.2条、第4.10.3条及条文说明
Topic Positioning
Method for estimating single-rig 24 h progress of deep soil-mixing (cement) columns (single/double/triple shaft): converting the "mixing volume per rig within 24 h shall not exceed 100 m³" red line of GB 51004-2015 "Code for Construction of Building Foundation Works", Clause 4.10.2 item 3, into meters by panel cross-sectional area, and deriving per-meter process time from code speed parameters. For scheduling in the project execution plan (construction methodology and site organization) and for estimating mixing-column duration and rig allocation.
Core Conclusions
I. 100 m³/24 h cap conversion (100 m³ / panel cross-section):
- Single-shaft d500 (area 0.196 sqm) ~= 509 m/24 h
- Single-shaft d600 (0.283 sqm) ~= 354 m/24 h
- Double-shaft d700@500 (panel 0.702 sqm) ~= 142 m/24 h
- Triple-shaft d650@450 (panel 0.866 sqm) ~= 115 m/24 h
- Triple-shaft d850@600 (panel 1.495 sqm) ~= 67 m/24 h Note: "mixing volume per rig within 24 h shall not exceed 100 m³" comes from Clause 4.10.2 (single- and double-shaft provisions); single- and triple-shaft have no explicit written cap — reference only. The double-shaft panel area must deduct the overlap of the two circles (d700@500 overlap per formulas like 2 x [r²·acos(d/2r) - (d/2)·sqrt(r² - d²/4)]) — not a simple 2 x single circle.
II. Process-time derivation (fastest code-permitted speeds, 1440 min of pure mixing per 24 h, practical values at 80% shift utilization):
- Single/double-shaft two-injection three-mixing: 3 penetrations x 1.0 m/min (code limit) + 3 lifts x 0.5 m/min (code limit) = 9 min/m -> theoretical ~= 160 m/24 h, practical ~= 128 m/24 h;
- Triple-shaft two-injection two-mixing: mean penetration 0.75 m/min, mean lift 1.5 m/min (Clause 4.10.3: penetration preferably 0.5-1.0 m/min, lift preferably 1-2 m/min) ~= 4 min/m -> theoretical ~= 360 m/24 h, practical ~= 288 m/24 h. The theoretical progress of double-shaft d700 (~= 142 m) essentially matches the 100 m³ conversion value (142 m), showing the cap was set at normal construction capability.
III. Field experience values (24 h continuous work): single/double shaft 100-150 m; double-shaft d700 100-140 m (~= 100 m³); triple-shaft d650@450 120-200 m; triple-shaft d850@600 150-250 m — triple-shaft theoretical values far exceed practice; the bottleneck lies in slurry production/supply. A single 8 h shift is about the 24 h value / 3, i.e., single/double shaft about 30-50 m per shift.
Applicable Boundaries
- Speeds are code limits/ideal values; actual progress is decided jointly by column diameter, column length, soil, rig condition, and slurry-plant capacity; upper speeds serve only to estimate ceiling output;
- For coarse sand and gravel the code requires more mixing passes, so speeds must drop; near buildings/underground pipelines the minimum lifting speed (0.33 m/min) applies and progress falls sharply;
- For triple-shaft columns, "pumping must be continuous" and "lifting speed synchronized with slurry delivery" are hard requirements, and slurry production/supply is often the true bottleneck;
- The commentary states that the recommended parameters derive from trial-column measurements; formal construction parameters should be set from trial columns and their monitoring (Clause 4.10.3);
- This card excludes cement dosage, column strength, rig selection, and cost.
Further Reading
- GB 51004-2015 "Code for Construction of Building Foundation Works", Clause 4.10.2 (single/double-shaft: depth <= 18 m, W/C 0.55-0.65, two-injection three-mixing, lift <= 0.5 m/min, penetration <= 1.0 m/min, 10-15 mm per revolution, 100 m³/24 h cap, grout pressure 0.40-0.60 MPa) and its commentary (process flow; 0.33 m/min minimum lifting speed);
- Clause 4.10.3 (triple-shaft: rod extension beyond 30 m, verticality 1/250, W/C 1.5-2.0, penetration 0.5-1.0 m/min, lift 1-2 m/min, three sequences — skip/single-side squeezing/pilot-hole overlapping; near protected objects penetration 0.5-0.8 m/min and lift <= 1.0 m/min, slurry pressure <= 0.8 MPa) and its commentary (applicable soils by N value above/below 30; Table 5 deep soil-mixing (cement) column vs. pilot-hole diameters);
- Clause-by-clause speed comparison of single/double vs. triple shaft: see the existing cards cited by this card.