Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

GB 51004-2015 deep soil-mixing (cement) column penetration/withdrawal speed requirements: single- and double-shaft (Clause 4.10.2) vs. triple-shaft (Clause 4.10.3)

GB 51004-2015 speed provisions for deep soil-mixing (cement) columns: single/double shaft (Clause 4.10.2) — bit slurry-injection mixing lifting speed preferably not greater than 0.5 m/min, mixing penetration speed preferably not greater than 1.0 m/min, lift (or penetration) per revolution preferably 10-15 mm, and after penetrating to the predetermined level, inject and mix for 30 s before lifting; near buildings/underground pipelines, the lowest lifting speed of 0.33 m/min should be used as far as possible. Triple shaft (Clause 4.10.3) — penetration speed preferably 0.5-1.0 m/min, lifting speed preferably 1-2 m/min at uniform rate; near protected objects, penetration preferably 0.5-0.8 m/min, lifting preferably within 1.0 m/min, slurry pressure preferably not greater than 0.8 MPa. Grout-pump outlet pressure should be kept at 0.4-0.6 MPa in both cases. Most parameters are recommendatory ("should") and must be set by trial piles for the given soil.

Applicable Codes

  • GB 51004-2015 · Code for Construction of Building Foundation 第4.10.2条、第4.10.3条及条文说明

Topic Positioning

This card compiles the construction provisions of GB 51004-2015 "Code for Construction of Building Foundation Works" on the penetration (sinking) and withdrawal (lifting) speeds of deep soil-mixing (cement) columns (commonly "cement mixing columns"), distinguishing single-/double-shaft (Clause 4.10.2) from triple-shaft (Clause 4.10.3) types, with supplementary parameters from the clause commentary.

Core Conclusions

Single- and double-shaft soil mixing method (Clause 4.10.2): 1 Construction depth preferably not greater than 18 m; the rig frame must be installed level, guide-mast verticality deviation less than 1/150, pile-position deviation not greater than 50 mm, pile diameter and length not less than design values; 2 Slurry water-cement ratio preferably 0.55-0.65; prepared slurry must not segregate; pumping must be continuous, with automatic pressure-and-flow recorders; 3 Double-shaft piles use the two-injection three-mixing process, with more mixing passes preferably added for coarse sand and gravel; the bit's slurry-injection mixing lifting speed should not exceed 0.5 m/min, the bit's mixing penetration speed should not exceed 1.0 m/min, and the lift (or penetration) per revolution of the bit should be 10-15 mm; the mixing volume of a single rig within 24 h should not exceed 100 m³; 4 Grout-pump outlet pressure kept at 0.40-0.60 MPa, with constant slurry delivery rate; 5 After the mixing bit penetrates to the predetermined level, slurry must be injected and mixing continue for 30 s before the rods are lifted. Commentary supplement: the two-injection three-mixing sequence is rig positioning -> premixing penetration -> slurry-injection mixing lift -> repeated mixing penetration -> repeated slurry-injection mixing lift -> slurry stop -> repeated mixing penetration -> repeated mixing lift to the collar -> mixing stop -> rig shift; near buildings or underground pipelines, the lowest lifting speed (0.33 m/min) should be used as far as possible, with alternating and intermittent sequences where necessary.

Triple-shaft soil mixing method (Clause 4.10.3): 1 For mixing piles deeper than 30 m, the rod-extension process should be used, and masts over 30 m need stability measures; guide-mast verticality deviation not greater than 1/250; 2 Slurry water-cement ratio preferably 1.5-2.0; 3 Mixing penetration speed preferably 0.5-1.0 m/min and lifting speed preferably 1-2 m/min, with uniform sinking or lifting maintained; 4 Alternating (skip), single-side squeezing, and pilot-hole overlapping sequences may be used; where pile formation in hard soils is difficult, the pilot-hole overlapping method with pre-loosened strata may be used; 5 The soil-disturbance zone above the improved area should preferably be improved at low cement dosage; 6 Works with high environmental-protection demands should use triple-shaft piles, adjusting parameters through trial piles and monitoring; near protected objects, mixing penetration speed preferably 0.5-0.8 m/min, lifting speed preferably within 1.0 m/min, slurry-injection pressure preferably not greater than 0.8 MPa; 7 Grout-pump outlet pressure preferably kept at 0.4-0.6 MPa, with the mixing lifting speed synchronized with the slurry delivery rate. Commentary supplement: the skip and single-side squeezing sequences generally suit soils with N values below 30; pilot-hole overlapping suits hard soils with N above 30 (relation between mixing-pile and pilot-hole diameters in commentary Table 5; bentonite may be added to ease loosening); triple-shaft piles cause comparatively less soil displacement than double-shaft piles and high-pressure jet grouting, with less impact on the surroundings.

Key comparison: single/double shaft — penetration not over 1.0 m/min, lifting not over 0.5 m/min, 10-15 mm per revolution; triple shaft — penetration 0.5-1.0 m/min, lifting 1-2 m/min. The triple-shaft lifting speed is in fact faster than single/double shaft — do not apply interchangeably.

Applicable Boundaries

  • This card covers only penetration/withdrawal speeds and accompanying process parameters, not cement dosage, pile-strength design, or rig selection;
  • Most clauses use "should/should not" wording — recommendatory parameters; the commentary notes that the recommended parameters derive from trial-pile measurements, and actual penetration and lifting speeds must be set by trial piles for the soil — lower speeds increase mixing passes and strength but extend duration and reduce output;
  • Single/double-shaft and triple-shaft piles differ in depth limits (18 m / 30 m), verticality deviation (1/150 / 1/250), water-cement ratio (0.55-0.65 / 1.5-2.0), and slurry pressure near protected objects (0.4-0.6 MPa / not over 0.8 MPa) — apply separately by pile type;
  • Near buildings, underground pipelines, or works with high environmental-protection demands, use the lower special speed tiers from the commentary together with monitoring.

Further Reading

  • GB 51004-2015 "Code for Construction of Building Foundation Works", Clause 4.10.2 (single- and double-shaft soil mixing), Clause 4.10.3 (triple-shaft soil mixing), and the corresponding commentaries;
  • The diagrams of the three triple-shaft sequences (skip, single-side squeezing, pilot-hole overlapping) and "Table 5: relation of mixing-pile and pilot-hole diameters" in the Clause 4.10.3 commentary;
  • The full two-injection three-mixing sequence and the applicable situations of the 0.33 m/min minimum lifting speed in the Clause 4.10.2 commentary.

Keywords

Cited By