Residual-value determination and settlement rules for demolished old-road materials (demolition quotas by default exclude residual-value credits)

Old materials from road demolition carry residual value (milled asphalt can be recycled, crushed concrete can backfill, metals are recoverable), but demolition quota sub-items cover only "demolition, cleanup, on-site transport, and piling up old materials" and by default exclude residual-value credits. Settlement follows three scenarios by material destination: handed to the employer for recovery (transport charged separately and recovery value offset), reused by the contractor (material cost deducted by actual utilization), sold by the contractor (handled per contract); waste hauling and disposal is charged separately and does not conflict with residual-value credits.

Applicable Codes

  • SJG 84-2020 市政维修工程消耗量标准 第二册 给水排水维修工程
  • SJG 181.1-2024 市政工程消耗量标准 Vol. 1 道路工程
  • CJJ 1-2008 城镇道路工程施工与质量验收规范
  • DB23/T 2994-2021 黑龙江省公路与城市道路工程绿色施工规程
  • GB/T 50905-2014 建筑工程绿色施工规范

Topic Positioning

Residual-value determination and settlement rules for materials from demolished old roads/structures: demolition quotas by default exclude residual-value credits; whether the residual value is offset, who owns it, and at what price depend on demolition method, material destination, and contract terms.

Core Conclusions

  1. Old materials carry residual value: asphalt milling is suited to cold/hot recycling; crushed cement concrete and stabilized base are suited to nearby filling, recycled aggregate, or yard hardening; metals and pipes are recoverable. But the work content of demolition quota sub-items is only "demolition, clearing the base, on-site transport, and piling up old materials", and demolition-and-renewal sub-items by default do not consider material reuse — the demolition fee is charged at the full quota price and the residual value is handled separately, not automatically offset.
  2. Settlement by material destination in three scenarios: (1) old materials handed to the employer / hauled to a designated recovery point: pay the demolition fee as usual, charge transport per the approved project execution plan (construction methodology and site organization), and offset the corresponding recovery value of the old materials (determined by the recovering party or market conditions); (2) reused by the contractor (backfill, recycling, hardening): deduct the sub-item material cost as incurred per the actual utilization rate; (3) recovered and sold by the contractor itself: pay the demolition fee as usual and handle the residual value per market conditions and the contract.
  3. Non-reusable waste and residue hauled out is charged separately by applying the corresponding residue/waste transport sub-item per the actual transport method — hauling away for disposal is chargeable, recycling is creditable: one thing at a time.

Applicable Boundaries

The rules are compiled from local quota notes such as Shenzhen SJG 84-2020 (municipal maintenance); the core logic (quota excludes residual value; handle by destination) is universal across regions; specific deduction ratios, material utilization rates, and recovery prices follow local quota notes, the contract, and tender documents. Protective demolition (curbstones and tile/stone finishes removed intact) yields high reuse value; destructive demolition yields low or even negative residual value (disposal cost above recovery price). Where the contract is silent on residual-value ownership, settlement disputes are likely — lock it in writing before construction and keep weighing/recovery slips as evidence.

Further Reading

SJG 84-2020 Clause 0.1.11 (demolition-renewal does not consider material reuse), Clause 7.1.3 (on-site stockpiling and separately charged transport), Clause 7.1.12 (protective vs. destructive demolition); SJG 181.1-2024 old-road demolition chapter work content; CJJ 1-2008 Clause 8.1.5 (centralized recovery and recycling of old asphalt); DB23/T 2994-2021 Clause 11.3.3 (pavement demolition utilization requirements); GB/T 50905-2014 Clause 11.4.3 (recovery and utilization of demolition materials).

Keywords

  • 拆除残值
  • 旧料回收价值
  • 残值抵扣
  • 旧路拆除
  • 拆除定额
  • 旧料再生利用
  • 结算抵扣
  • 拆旧换新