Organization and acceptance requirements of water ponding (flood) tests and water-spray tests in waterproofing works

The test type follows the location: pondable flat roofs and kitchen/bathroom floors use the ponding (water-retention) test (≥24 h, ≥20 mm at the shallowest point), repeated after the finish layer in kitchens/bathrooms; sloped roofs, exterior walls, walls requiring waterproofing, and curtain walls use water-spray tests (roof ≥2 h, exterior/interior walls ≥30 min, curtain walls per JGJ/T 139-2020 Appendix D parameters); retest after leak repair, then complete and archive the test record.

Applicable Codes

  • GB 55030-2022 建筑与市政工程防水通用规范
  • GB 50207-2012 屋面工程质量验收规范
  • JGJ/T 299-2013 建筑防水工程现场检测技术规范
  • JGJ/T 139-2020 玻璃幕墙工程质量检验标准
  • DB11/T 1811-2020 厨房、厕浴间防水技术规程
  • DB11/T 1076-2023 居住建筑装饰装修工程质量验收标准
  • DB33/T 1140-2017 住宅工程分户质量检验技术规程

Topic Positioning

Type selection, parameter floors, organizational procedure, and leak handling for ponding (water-retention) and water-spray tests in waterproofing acceptance — covering roofs, kitchens and bathrooms, exterior walls, and curtain walls.

Core Conclusions

  • Test type by location: pondable roofs and kitchen/bathroom floors use the ponding test, which is mandatory for gutters, valleys, and rainwater outlets; non-pondable sloped roofs use spray tests or post-rain observation; walls requiring waterproofing and exterior walls use spray tests; glass curtain walls use dedicated spray equipment.
  • Parameter floors: ponding ≥24 h, water depth ≥20 mm at the shallowest point, total water weight not exceeding structural capacity; roof spraying ≥2 h (or post-rain observation at moderate-rain level); exterior and interior waterproofed walls sprayed ≥30 min, high-rise walls preferably sprayed storey by storey ensuring continuous full-flow; curtain-wall nozzles ≥530 mm from the wall, each test area 1800 mm × 1800 mm, water feed ≥4 L/(m²·min) for 5 min.
  • Procedure: plug floor drains and pipe openings, contain and fill with water, mark the water line, dedicated observers watch for water-level drop and leakage on the back face, focusing on pipe penetrations through floors, riser roots, membrane terminations at parapets, and around drains; stop immediately on leakage, repair, and retest; kitchens/bathrooms run a first ponding test after the waterproof layer and a second after the finish layer; after passing, complete and archive the ponding/spray test record.

Applicable Boundaries

Applies to waterproofing acceptance of roofs, kitchens/bathrooms, exterior walls, curtain walls, etc., in building works; the ponding test presumes pondable conditions (containable and load-bearing). The listed parameters are minimums; stricter local or discipline rules prevail; underground waterproofing acceptance has separate requirements outside this card's scope.

Further Reading

Mandatory national code GB 55030-2022, General Code for Waterproofing of Building and Municipal Works, Clauses 6.0.10–6.0.11; GB 50207-2012, Code for Quality Acceptance of Roof Works, Clause 9.0.8; JGJ/T 299-2013, Technical Specification for In-situ Testing of Building Waterproofing, Clause 12.1.3; JGJ/T 139-2020, Standard for Quality Inspection of Glass Curtain Walls, Appendix D; local references: DB11/T 1811-2020, DB11/T 1076-2023, DB33/T 1140-2017.