Supply–demand balance calculation for the number of builder's hoists

The number of builder's hoists is determined from code selection parameters plus a peak supply–demand balance calculation: single-unit capacity = trips per hour × effective payload / passenger limit (cycle time = 2 × lifting height ÷ speed + loading/unloading time); peak demand = daily transport volume ÷ working hours × peak factor 1.3–1.5 (materials) or peak-period headcount ÷ hours (personnel); N = max(N_material, N_personnel) ÷ utilization 0.75–0.85, rounded up; personnel transport is usually the controlling case, and staged calculation should take the maximum.

Applicable Codes

  • JGJ 3-2010 高层建筑混凝土结构技术规程
  • JGJ 215-2010 建筑施工升降机安装使用拆卸安全技术规程
  • DBJ/T 15-92-2021 高层建筑混凝土结构技术规程(广东)

Topic Positioning

How the number of builder's hoists is determined: code selection parameters + the peak supply–demand balance calculation, for vertical transport equipment configuration in the project execution plan (construction methodology and site organization).

Core Conclusions

Selection rests on two parameter sets: demand side — building shape and size, gross floor area (GFA), total transport volume, duration, and supply conditions (JGJ 3-2010, Clause 13.4.6); capacity side — cargo dimensions, payload, frequency of transport, and service height (JGJ 215-2010, Clause 3.0.6). The unit count is calculated by the supply–demand balance method:

  1. Single-unit cycle time T = 2 × lifting height ÷ rated speed + door and loading/unloading time;
  2. Trips per hour = 60 ÷ T; material capacity = trips × effective payload (about 75%–80% of rated load); personnel capacity = trips × passengers per trip (about 80%–85% of rated passenger count);
  3. Peak demand: materials = daily total transport volume ÷ daily effective working hours × peak factor (1.3–1.5); personnel = headcount needing to go up during the peak period ÷ hours in the period;
  4. Calculate N_material and N_personnel separately; N = max(N_material, N_personnel) ÷ utilization k (0.75–0.85), rounded up. Where one hoist carries both, the shift-change rush hour is usually the controlling case; separate passenger/goods hoists or staggered exclusive use can be adopted. Transport demand differs greatly between the structure and finishing stages — calculate by stage and take the maximum; for elongated plans, split into high/low zones. Provision threshold: a builder's hoist is required above 15 storeys or 40 m (Guangdong DBJ/T 15-92-2021 uses 5 storeys or 15 m — follow the project location).

Applicable Boundaries

Applies to initial hoist-count configuration at the project execution plan (construction methodology and site organization) stage of building works. The efficiency factor, peak factor, and effective payload are empirical values, to be taken per project conditions and verified; local storey/height thresholds follow the project location; hoist positioning, foundation and wall-tie anchorage design, and anti-fall system selection follow their own codes.

Further Reading

JGJ 3-2010, Technical Specification for Concrete Structures of Tall Buildings, Clauses 13.4.6 and 13.4.3; JGJ 215-2010, Code for Safety of Installation, Use and Dismantling of Construction Hoists, Clause 3.0.6; DBJ/T 15-92-2021 (Guangdong), Clause 15.4.4.

Keywords

  • builder's hoist
  • 施工升降机
  • 电梯数量
  • 供需平衡
  • 垂直运输
  • 选型参数
  • JGJ 215