Pipe jacking pricing: working/receiving shafts, jacking quantity rules, and the short-distance adjustment factor (SJG 181.4-2024)

Pipe jacking costs fall into four blocks: working/receiving shaft construction (open caissons apply tunnel-volume sub-items; working-pit bedding/foundation labor x 1.10), installation/removal of jacking equipment and facilities, jacking operation, and separately charged costs. Jacking quantities are measured in meters by design jacking length; when the total length of extrusion-type jacking with pipe diameter <= 1650 mm is <= 100 m, or the total length of earth-pressure/slurry/air-pressure/compound jacking is <= 50 m, the labor and machine-shifts of jacking sub-items are multiplied by 1.30; spoil hauling, slurry treatment and transport, and groundwater dewatering/drainage are all charged separately.

Applicable Codes

  • SJG 181.4-2024 市政工程消耗量标准 Vol. 4 给水排水管网工程
  • DB11/T 1835-2021 给水排水管道工程施工技术规程

Topic Positioning

The pricing framework of pipe jacking works: measurement calibers and adjustment rules for working/receiving shaft construction, jacking operation, auxiliary measures, and separately charged costs, structured on Shenzhen SJG 181.4-2024 "Municipal works consumption standard, Volume 4: water supply and sewer networks" — applicable to BOQ pricing, budgeting, and settlement review of municipal pipe jacking (including box-arch culvert jacking).

Core Conclusions

  • Open caissons of working/receiving pits apply the corresponding sub-items of Volume 3 "Tunnel works"; the bedding and foundations of working pits apply pipeline-laying chapter sub-items with labor x 1.10, other items unchanged.
  • Jacking quantities are measured in meters by design jacking length (not actual length consumed); installation/removal of jacking machinery and appurtenances is per set; intermediate jacking stations are per set by design quantity (installing one counts as one stage, each additional one adds a stage, staged jacking sections converted by the adjustment-factor formula); thixotropic-slurry friction reduction and cement-slurry replacement are measured in meters by design jacking length; grout holes per count; joints per actual joint count or cross-sectional area in count/m2.
  • Short-distance adjustment: in a unit work, when the total length of extrusion-type jacking with pipe diameter <= 1650 mm is <= 100 m, or the total length of earth-pressure-balanced, slurry-balanced, air-pressure-balanced, or rock-crushing compound jacking (regardless of diameter) is <= 50 m, the labor and machine-shifts of jacking sub-items are multiplied by 1.30.
  • Installation/removal of jacking reaction blocks and in-pit platforms: timber reaction blocks per design installation/removal quantity in units; reinforced concrete reaction blocks by actual concrete volume in m3, without deducting reinforcement, embedded parts, or single holes <= 0.3 m2.
  • Easily missed separately charged items: jacking sub-items include only spoil removal from the pit (outward hauling charged separately); slurry-balanced jacking excludes slurry treatment and transport; the quota is compiled assuming no groundwater — dewatering/drainage costs charged separately if encountered; when pipe materials differ from design, adjust per design.

Applicable Boundaries

Framed on Shenzhen SJG 181.4-2024; municipal quota calibers differ across regions (short-distance thresholds, wellpoint set division, etc.) — before pricing, follow the current local consumption standard and measurement rules; this card contains measurement rules and the pricing framework only, without labor/material/machinery base prices or specific rates.

Further Reading

SJG 181.4-2024 Clause 1.1.6 (pipe-jacking application rules: open caisson, factors, separately charged items) and Clause 1.2.5 (pipe-jacking measurement rules); safety facilities of working shafts (rain canopies, sump pits, guardrails, ladders) see DB11/T 1835-2021 Clause 12.2.5; shaft dimension design basis: small-diameter microtunnel machines about 3.5 m, large/medium-diameter >= 5.5 m.