Segmental concreting of shaft lining for manually excavated piles: slump, formwork removal, overlaps and reinforcement parameters

For each lining segment of hand-dug piles: after excavating a segment, pour immediately from all sides evenly and compact by vibration, slump 70-100mm; remove lining forms 24h after placing (stripping strength not below 3MPa); each segment completed in one continuous pour the same day; overlap between segments not less than 50mm; lining thickness not less than 100mm, concrete preferably not below C20 or the pile concrete strength, with structural bars not smaller than 8mm (vertical bars lapped or tied top-to-bottom); the range of any diameter of the shaft ring at one level shall not exceed 50mm. Per DB11/T 1832.1-2021 cl. 15.4.6/15.4.9/15.4.13 and DB11/T 1833-2021 cl. 4.3.7.

Applicable Codes

  • DB11/T 1832.1-2021 · Specification for Construction Technology of Building Works (Part 1: Foundation Works) (Beijing) Ch. 15(15.4.6/15.4.9/15.4.13)
  • DB11/T 1833-2021 · Specification for Safe Operation of Building Construction (Beijing) 第4.3.7条

Topic Positioning

Segmental concreting workmanship and control parameters for the shaft lining of manually excavated (hand-dug) concrete piles, per Chapter 15 "hand-dug concrete cast-in-place piles" of DB11/T 1832.1-2021 and cl. 4.3.7 of DB11/T 1833-2021 Safety Operation Rules — covering per-segment pouring sequence, slump, formwork timing, overlaps, reinforcement and tolerances.

Core Conclusions

Lining follows "excavate segment by segment, pour segment by segment": position the pile — excavate in stages (usually 1m each) — pour the lining per stage (tie bars, set forms, place, cure, strike) — repeat to design depth — enlarge the base — lower the cage — place the pile concrete (DB11/T 1833-2021 cl. 4.3.7).

Per-segment points (DB11/T 1832.1-2021 cl. 15.4.9):

  1. After excavating the first segment, set forms and pour the lining immediately, pouring evenly from all sides and compacting manually; slump 70-100mm.
  2. Strike forms 24h after placing, preferably after the next segment's soil is excavated; if honeycombing or seepage appears, plug or drain.
  3. After the first segment, transfer the pile axis control points onto the lining as the datum for lining centers, and level-mark the relative datum on the first collar.

Lining detailing (cl. 15.4.6): thickness not less than 100mm; strength preferably not below C20 or the pile concrete; compact by vibration; structural bars not smaller than 8mm with vertical bars lapped or tied between segments.

Collar lining rules (cl. 15.4.13): 1 thickness, tie bars, reinforcement and strength per design, with specimens made as required; 2 overlap between upper and lower segments not less than 50mm; 3 each segment poured continuously the same day; 4 compact fully, using accelerators per seepage; 5 strike forms only 24h after placing; 6 strengthen promptly on honeycombs or seepage; 7 the range of any diameter of the collar at one level shall not exceed 50mm.

Safety-rule supplement (DB11/T 1833-2021 cl. 4.3.7): lining concrete not below C15; striking strength not below 3MPa, normally only after 24h, before continuing excavation.

Rationale (commentary of cl. 15.4.9): during pile concreting, excessive slump causes segregation, producing faults and interlayers in the pile shaft — hence the 70-100mm limit and the "pour evenly from all sides" requirement, the key control of lining concreting.

Applicable Boundaries

  • For segmental lining concreting of hand-dug cast-in-place piles; a Beijing local standard (minimum/basic) — execute per design drawings.
  • Local standards may differ on thickness and strength; other regions follow their current standards — do not transplant directly.
  • The 1m-per-stage sequence suits ordinary strata; special strata (seepage, soft ground) need accelerators, adjusted stage heights and special measures.

Further Reading

  • DB11/T 1832.1-2021 Chapter 15: cl. 15.4.6 (thickness/strength/structural bars), 15.4.9 (first segment, slump), 15.4.13 (collar rules).
  • DB11/T 1833-2021 cl. 4.3.7 (segmental lining pouring and striking strength).
  • Extensions: same-condition cured specimens (stripping control) vs standard-cured specimens (strength evaluation).

Keywords

  • 人工挖孔桩
  • 护壁混凝土
  • 护壁浇筑
  • 坍落度
  • 拆模时间
  • 井圈护壁
  • DB11/T 1832.1-2021
  • DB11/T 1833-2021