Recording blow counts in rod penetration testing (qiantan) of natural foundations: record every 300mm of penetration, unified forms, signed and archived by testers (DB11/T 1832.1-2021 Chapter 3)

Beijing DB11/T 1832.1-2021 Clause 3.4.4: in rod penetration, the drop hammer falls 500mm freely and vertically; blow counts shall be recorded for every 300mm the rod penetrates; record into unified forms numbered by hole order, legibly; mechanical rigs shall count automatically; records are signed by testers and archived. Clause 3.7.2: record sheets should distinguish holes of different blow counts by color or symbol; the layout plan shall mark holes that are too hard/soft and dimensions of underground features such as dry wells, tombs, and cavities.

Applicable Codes

  • DB11/T 1832.1-2021 · Specification for Construction Technology of Building Works (Part 1: Foundation Works) (Beijing) Ch. 3(3.4.4、3.5.1、3.7.2条,Table 3.3.2)

Topic Positioning

Methods of recording blow counts, organizing record sheets, and archiving for rod penetration testing (penetration inspection) of natural foundations in Beijing, per Chapter 3 of DB11/T 1832.1-2021 "Construction work procedure specifications for building works, Part 1: foundation engineering".

Core Conclusions

(I) Positioning and recording frequency (3.4.4): align the rod tip with the hole position, sleeve the drop hammer on the rod, hold the rod plumb, and lift the hammer to fall freely with a drop of 500mm, driving the rod vertically into the soil; mechanical penetration follows its own requirements. Recording rules:

  1. Record the blow count each time the rod penetrates 300mm (one number per 30cm; each hole yields a string of counts by depth);
  2. Where design sets no penetration depth, follow Table 3.3.2 of this procedure;
  3. Organize records by hole order into unified forms, legibly; mechanical rigs shall count automatically; records shall be signed by testers and archived. (II) Depth (3.5.1): penetration depth shall meet survey/design requirements; blow counts recorded accurately. (III) Organizing records and layout plan (3.7.2):
  4. Use different colors or symbols to separate holes of different blow counts;
  5. On the hole layout plan, mark positions of holes that are too hard or too soft; where dry wells, tombs, cavities, etc. are met, note their dimensions.

Applicable Boundaries

  • Applies to rod penetration of natural foundations in Beijing (DB11/T 1832.1-2021 is Beijing's local standard); projects elsewhere should check their local current procedures.
  • Covers only blow-count recording and documentation; the criteria for stopping penetration (e.g., abnormal standards such as over 100 blows per 30cm) are not listed in this procedure - follow survey/design or local rules; do not import other regions' clauses.
  • Blow-count records are part of base-inspection documentation and shall be archived together with the hole layout plan.

Further Reading

  • DB11/T 1832.1-2021 Chapter 3 (natural foundations): 3.4.4 (positioning and blow-count recording), 3.5.1 (depth), 3.7.2 (records and layout plan); Table 3.3.2 for depth when design is silent.

Keywords

  • 钎探
  • 天然地基钎探
  • 锤击数
  • 钎探记录
  • 穿心锤
  • 地基验槽
  • DB11/T 1832.1-2021
  • 施工工艺规程