Correction of arithmetic errors and minor deviations in bid prices: statutory handling order for words-vs-figures amounts and unit-price vs extended-amount conflicts (GB/T 50500-2024 clause 3.5.2)
Seven rules for correcting arithmetic errors in bid prices: (1) inconsistent amounts in words and figures — words prevail; (2) BOQ total at variance with the bid price — the bid price prevails; (3) provisional sums, provisional sums for nominated specialist subcontract works and prime cost (PC) sums for materials — per the tender BOQ; (4) extended amount at variance with quantity x unit price — the unit price prevails and the extended amount is corrected (if extended amount / quantity back-calculates to a unit price matching identical BOQ items, or the decimal point is clearly misplaced, the extended amount prevails and the unit price is corrected); (5) BOQ unit price at variance with the analysis sheet — the BOQ prevails; (6) VAT corrected as the corrected BOQ total (less provisional sum for nominated specialist subcontract works) x tax rate; (7) the total error is apportioned in the ratio of the trade-items BOQ total (excluding prime cost (PC) sums for materials). No correction may change the bid price.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第3.5.1~3.5.4条
- 工程建设项目施工招标投标办法(七部委30号令)第53条
Topic Positioning
This card covers how arithmetic errors and minor deviations in bid prices are corrected: the statutory handling order for conflicts between amounts in words and figures, BOQ extended amounts and the bid price, unit prices and extended amounts, and the effect of corrected results.
Core Conclusions
Per GB/T 50500-2024 clause 3.5.2, error correction is anchored on "the bid price is immutable"; the rules in order: (1) where the amount in words differs from figures in the bid letter, words prevail and figures are corrected; (2) where the accumulated total of the priced BOQ differs from the bid price, the bid price prevails and the BOQ accumulation is corrected; (3) where provisional sums, provisional sums for nominated specialist subcontract works or prime cost (PC) sums for materials differ from the tender BOQ, the tender BOQ prevails; (4) where a BOQ item's extended amount differs from quantity x all-in unit rate, the all-in unit rate prevails and the extended amount is corrected — but if the unit price back-calculated from extended amount / quantity matches identical items in the BOQ, or the decimal point is clearly misplaced / clearly unreasonable, the extended amount prevails and the all-in unit rate is corrected; (5) where a BOQ item's all-in unit rate differs from the all-in unit rate analysis sheet, the BOQ prevails and the sheet is corrected; (6) VAT is corrected as the corrected total of the three BOQ sections (less provisional sum for nominated specialist subcontract works) x tax rate; (7) if the corrected total still differs from the bid letter, the total error is apportioned to each trade item's all-in unit rate and extended amount in the ratio it bears to the trade-items bid total (excluding prime cost (PC) sums for materials); after apportionment, prime cost (PC) sums for materials remain at the tender BOQ values. Corrections bind only after the bidder's confirmation; corrected all-in unit rates may be used for progress payments and variation pricing. The same general principles apply at bid evaluation (Order No. 53 of the seven-ministry decree No. 30: words prevail over figures; unit price prevails; where the decimal point is clearly misplaced, the total prevails and the unit price is corrected).
Applicable Boundaries
Applies to bid evaluation and clarification of construction tenders; the bid price is the correction anchor — no correction may materially change it. Below-cost bidding is handled by clarification/explanation and bid-rejection procedures (MOHURD Order No. 43 article 42; Ministry of Transport 2018 Decree No. 13 article 32), outside the scope of arithmetic correction.
Further Reading
See GB/T 50500-2024 clause 3.5.2 and clauses 3.5.1, 3.5.3, 3.5.4 (BOQ pricing risks, clarification and use of corrected unit rates); "Measures for tendering and bidding of construction projects" (seven-ministry decree No. 30) article 53.
Keywords
- 投标报价修正
- 算术误差
- 细微偏差
- 大小写金额
- 单价与合价
- tender review and normalization (arithmetic and compliance check)
- 评标修正
- 投标总价