Casing installation values for bored piles (rotary-drilled / slurry-supported): comparison of GB 51004-2015 cl. 5.6.3, JGJ 94-2008 cl. 6.3.5 and DB11/T 1832.1-2021 cl. 16.4.4
Casing center vs pile (hole) center deviation not (may not / should not) exceed 50mm — all three codes agree; casing inner diameter: 200mm larger than the drill bit OD for rotary drilling (GB 51004-2015), 100mm larger than bit diameter as the general slurry-boring caliber (JGJ 94-2008); verticality deviation preferably not over 1/100 (GB 51004-2015), inclination preferably not over 1% (DB11/T 1832.1-2021); embedment: cohesive soil preferably >=1.0m, sand preferably >=1.5m (JGJ 94-2008); casing top preferably about 200mm above ground (DB11/T 1832.1-2021); rotary rigs shall always install a casing (doubling as bucket guide).
Applicable Codes
- GB 51004-2015 · Code for Construction of Building Foundation 第5.6.3条
- JGJ 94-2008 · Technical Code for Building Pile Foundations 第6.3.5条
- DB11/T 1832.1-2021 · Specification for Construction Technology of Building Works (Part 1: Foundation Works) (Beijing) 第16.4.4条
Topic Positioning
This card consolidates casing installation values for bored piles (rotary-drilled and slurry-supported) in the building/municipal system: an item-by-item comparison of national GB 51004-2015, industry JGJ 94-2008 and Beijing DB11/T 1832.1-2021 — for direct use in casing setting, tolerance acceptance and technical disclosure.
Core Conclusions
Original calibers of the three codes (national standard as the floor; local projects also check the local procedure):
[GB 51004-2015 cl. 5.6.3] (mandatory national code, general boring) 1 Casings shall be steel plate with adequate stiffness and strength; an overflow hole on top; the outside of the lower end packed with clay; casing height shall satisfy the in-hole slurry level; embedment shall enter a stable soil layer; 2 The pile position shall be marked on the casing; casing center vs hole center deviation shall not exceed 50mm; 3 Casing inner diameter shall be 100mm larger than the bit OD; for impact and rotary drilling 200mm larger; verticality deviation preferably not over 1/100. Also: the rotary rig's casing both protects the hole mouth and guides the bucket, so rotary rigs shall always install casings with compliant verticality; overly long casings may be sectional, reliably connected at the mouth.
[JGJ 94-2008 cl. 6.3.5] (general slurry-supported boring) 1 Casing setting shall be accurate and stable; casing center vs pile center deviation shall not exceed 50mm; 2 Casings may be 4-8mm steel plate, inner diameter 100mm larger than the bit diameter, with preferably 1-2 slurry overflow openings on top; 3 Embedment depth: preferably not less than 1.0m in cohesive soil; not less than 1.5m in sand; the lower outside packed with clay; height shall satisfy the in-hole slurry level; 4 For piles affected by fluctuating water tables or underwater, casings shall be heightened and deepened, driven into an impermeable stratum if necessary.
[DB11/T 1832.1-2021 cl. 16.4.4] (Beijing, rotary-drilled bored piles) 1 Embedment depth per geology; preferably seated on a stable soil layer; 2 Casing top about 200mm above ground; survey the casing top level as the basis for hole depth; 3 Casing center vs pile center deviation preferably not over 50mm; inclination preferably not over 1%; 4 Pre-drilling or driver installation may be used; with pre-drilling, pack and compact clay around the casing.
Quick comparison table:
| Item | GB 51004-2015 (national) | JGJ 94-2008 (industry) | DB11/T 1832.1-2021 (Beijing) |
|---|---|---|---|
| Center deviation | shall not exceed 50mm | may not exceed 50mm | preferably not over 50mm |
| Verticality/inclination | preferably not over 1/100 | — | preferably not over 1% |
| Inner diameter | 100mm over bit OD; impact/rotary 200mm | 100mm over bit diameter | — (no value) |
| Embedment | into stable soil layer | cohesive >=1.0m; sand >=1.5m | preferably on stable soil layer |
| Above ground | satisfy in-hole slurry level | satisfy in-hole slurry level | about 200mm |
| Material/structure | steel plate, overflow hole on top | 4-8mm steel plate, 1-2 overflow openings | pre-drilled or driver-set |
Note the distinction: GB 51004-2015 gives the stricter "200mm over bit OD" specifically for rotary and impact boring; JGJ 94-2008's "100mm over bit diameter" is the general slurry-boring caliber (direct/reverse circulation). Different processes, no contradiction — take 200mm for rotary drilling.
Applicable Boundaries
- Applies to casing installation and tolerance control of bored piles (slurry-supported, rotary-drilled) in building and municipal works; Beijing projects also check "about 200mm above ground" and "inclination preferably not over 1%" per DB11/T 1832.1-2021.
- This card covers only the three building-system codes; railway (TB 10752-2018/TB 10415-2018) and highway (JTG/T 3650-2020) systems have their own calibers (e.g. casing top center 50mm, inclination 1%) — see the cited railway/highway card.
- Rotary drilling always requires a casing; the "shall not / may not / preferably not" wording differs in strength — acceptance follows the design documents and the governing code's mandatory items.
- Casing pricing (amortization cycles, quantity computation) is not covered here.
Further Reading
- GB 51004-2015 cl. 5.6.3 (boring chapter, casing setting and rotary-rig casing guidance).
- JGJ 94-2008 cl. 6.3.5 (bored pile construction — slurry-supported boring); further casing provisions for impact-bored piles in the related chapters.
- DB11/T 1832.1-2021 cl. 16.4.4 (rotary-drilled bored piles; process flow Fig. 16.4.1).
- Railway/highway comparison: TB 10752-2018 / TB 10415-2018 section 5.3; JTG/T 3650-2020 (see the cited card).
Keywords
- 护筒
- 护筒埋设
- 旋挖成孔灌注桩
- 钻孔灌注桩
- 泥浆护壁成孔
- GB 51004-2015
- JGJ 94-2008
- DB11/T 1832.1-2021