Verifying the source of "pull the mouth casing before initial set of the concrete": it is NOT a clause of JTG/T 3650-2020 (likely from the railway passenger-dedicated TZ 213-2005 system), with the current codes' real casing/pipe extraction-timing clauses compiled
"After concreting, the mouth casing below ground and pile top shall be extracted before the initial set of the concrete" is not a clause of JTG/T 3650-2020 (Highway bridge and culvert construction code) - it likely comes from the railway passenger-dedicated guide TZ 213-2005 system and is widely mis-attributed online. The clauses actually governing extraction timing: DBJ/T 36-055-2019 Clause 4.4.5 (casing-machine method: withdraw with the pour, casing bottom >2m below the concrete surface, concrete within the tremie embedded depth not yet set); DBJ/T 15-236-2021 Clause 7.5.1 (withdraw with the pour; lift when concrete passes 4m above the casing bottom; keep the bottom 2m below the surface); DB/T 29-75-2018 Clause 10.3.7 (start withdrawing at about 2m above the casing bottom; casing may sit 5-8m in the concrete, lifted continuously and removed in sections). "Initial set" in current codes governs pour continuity (each pile poured within the first-batch initial-set time).
Applicable Codes
- JTG/T 3650-2020 · Technical Specifications for Construction of Highway Bridges and Culverts
- DBJ/T 36-055-2019 · Technical Standard for Rotary Drilled Cast-in-Place Pile Construction (Jiangxi)
- DBJ/T 15-236-2021 · Technical Specification for Rotary Drilled Cast-in-Place Pile Construction (Guangdong)
- DB/T 29-75-2018 · Standard for Construction and Acceptance of Urban Bridges of Tianjin
- JGJ 94-2008 · Technical Code for Building Pile Foundations
- CJJ 2-2008 · Code for Construction and Quality Acceptance of Urban Bridge Works
- GB 51004-2015 · Code for Construction of Building Foundation
- 铁路客运专线桥涵施工技术指南 TZ 213-2005(出处待核实)
Topic Positioning
Verifying the true source of claims like "the temporary mouth casing shall be pulled before initial set", correcting its common mis-attribution to JTG/T 3650-2020, and compiling quotable originals of the clauses that actually govern casing (steel casing/casing-pipe) extraction timing - for construction-plan drafting.
Core Conclusions
- Source check: the sentence is not in JTG/T 3650-2020. That code (issued 2020-06-18, effective 2020-10-01, replacing JTG/T F50-2011) is a recommended sector standard whose text is not publicly posted (only the announcement); but by its system, "initial set" there governs underwater pour continuity, and its casing clauses all concern installation (center offset, verticality, embedment, height above water) - no initial-set clause targets casing extraction. The sentence likely comes from the railway passenger-dedicated guides TZ 213-2005 concreting provisions (identified in 2008 practitioner-forum discussions; exact clause number unverified); numerous online plans and AI excerpts mislabel it as the highway code.
- What "initial set" actually governs: the continuity of underwater pours - each pile must be poured continuously within the initial-set time of the first batch, consistent with JGJ 94-2008 Clause 6.3.30 item 4: "the pouring time of each pile shall be controlled by the initial-set time of the first-batch concrete."
- Quotable extraction-timing clauses in current standards:
- DBJ/T 36-055-2019 "Technical standard for rotary-bored cast-in-place piles", Clause 4.4.5 (closest current wording): with the casing-machine method, the steel casing "must be pulled out in sections with the pour, keeping the casing-pipe bottom more than 2m below the concrete surface"; "when lifting the casing in sections, the concrete inside the tremie and within its embedded-depth range shall not have initially set"; vibratory hammers may assist; monitor and record the drop of the concrete surface inside the casing and act on the data.
- DBJ/T 15-236-2021 "Technical regulation for rotary-bored cast-in-place piles", Clause 7.5.1: extraction keeps pace with pouring; "withdraw with the pour"; "when the concrete surface passes 4m above the casing bottom, lift the casing, keeping its bottom at least 2m below the placed surface"; on withdrawal, the concrete within the tremie and 2m below its mouth shall retain good workability; vibratory assistance and surface monitoring advised.
- DB/T 29-75-2018 "Tianjin standard for urban bridge construction and acceptance", Clause 10.3.7: "when the concrete fills to about 2m above the casing bottom, begin shaking and slowly lifting"; the casing may sit 5-8m in the concrete, lifted continuously and dismantled in sections, drawing off excess water to relieve pressure.
- JGJ 94-2008 Clause 6.5.3 (driven-tube pile pipe withdrawal - not a casing; do not confuse): ordinary soils about 1 m/min; soft soils and interfaces 0.3-0.8 m/min; monitor the surface with a plumb or float.
- Practice note: the passenger-line clause's intent is that a land casing (typically 2-4m embedment) whose bottom reaches below design top cannot be pulled after set (it jams or disturbs the head concrete); if early withdrawal risks collapse or soil inclusions, wait until the concrete stands high enough above the casing bottom (e.g., 2m) then withdraw with the pour - the two requirements do not conflict.
Applicable Boundaries
- This card covers extraction-timing control and source verification; casing installation requirements (50mm offset, 1% inclination, embedment, diameter) are a separate topic - see the cross-linked card.
- JTG/T 3650-2020's full text was not verified clause-by-clause; the negative conclusion rests on system analysis and public announcements - restated here as a boundary; verify with the PDF if available.
- The railway TZ 213-2005 clause number could not be located - flagged "to verify"; do not cite a hard number.
- JGJ 94-2008 6.5.3 concerns driven-tube "pipe withdrawal", mechanically different from bored-pile "casing extraction" - cite by process type.
Further Reading
- Verified originals: DBJ/T 36-055-2019 Clause 4.4.5; DBJ/T 15-236-2021 Clause 7.5.1; DB/T 29-75-2018 Clause 10.3.7; JGJ 94-2008 Clauses 6.5.3 and 6.3.30(4).
- Further channels: CJJ 2-2008 Clause 10.3.5(4) (full-casing underwater pours: casing bottom embedded >=1.5m in concrete, casing lifted as the tremie rises); GB 51004-2015 Clause 5.6.20(4) (continuous underwater pour within initial-set time); TZ 213-2005 concreting provisions (source number to verify).
- Adjacent cards: casing tolerances (railway TB 10752-2018 / highway JTG/T 3650-2020), casing installation values (GB 51004-2015/JGJ 94-2008/DB11/T 1832.1-2021), JTG/T 3650-2020 version history.
Keywords
- 护筒拔出时机
- 初凝前拔出
- JTG/T 3650-2020
- 公路桥涵施工技术规范
- 随灌随拔
- 钢护筒
- 旋挖成孔灌注桩
- 条文出处