joint sign-off (countersignature)
- 01
Determining validity when a site instruction / variation record conflicts with meeting minutes: the three-tier cascade of certification and sign-off validity -> formation time -> actual completion
When a site instruction / variation record conflicts with meeting minute…
GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.9节、第5.9.1条T/GAEC 201-2018 · Guideline for Compilation and Management of Supervision Documents of Construction Projects 第5.1.4条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第12.2.1条2026-09-25 - 02
Evidentiary weight of meeting minutes in settlement and contract disputes: a tiered analysis based on countersigned consensus
The evidentiary weight of meeting minutes is tiered by "whether mutual c…
GB/T 50500-2024 建设工程工程量清单计价标准 第12.2.1条T GAEC 201-2018 建设工程监理文件资料编制与管理指南 第5.1.4条建筑安装工程承包合同条例 第三条2026-09-25 - 03
A site instruction / variation record signed only by the employer: determination of validity and remedying defects (signing with approval vs merely acknowledging receipt)
A site instruction / variation record signed only by the employer is a p…
GB/T 51262-2017 建设工程造价鉴定规范 5.9DB37/T 5130-2018 建设工程造价咨询服务规范 9.3.7/9.3.8GB/T 50875-2013 工程造价术语标准 3.4.82026-09-25