- 01
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completio…
GB/T 50500-2024《建设工程工程量清单计价标准》第2.0.21条、第3.3.5条、第8.7.1~8.7.4条、第10.2.3条、第10.2.7条、第10.3.2条、附录A.2.1~A.2.4、附录G.2T/ZBD 100.5-2023《建设工程结算审核作业指引》第3.1.7条2026-09-12 - 02
Rules for determining the construction-period price (measurement-period market price Ci) in material adjustment (GB/T 50500-2024 appendix A.2)
The construction-period price is the measurement-period market price Ci…
GB/T 50500-2024 附录A.2.1~A.2.5GB/T 50500-2024 第8.7.2/8.7.4条GB/T 50500-2024 附录A.1.52026-08-11