Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Tensioning and locking of anti-floating (prestressed) anchors: pre-tensioning, over-tensioning, locking load, and acceptance testing (DB11/T 1832.1-2021 / GB 51004-2015 / GB 50086-2015 / JGJ 476-2019)

Four codes govern anchor tensioning-locking: Beijing DB11/T 1832.1-2021 Clause 23.4.6; GB 51004-2015 Clause 6.10.6; GB 50086-2015 Clauses 4.7.12-4.7.14 (applied to prestressed anti-floating anchors per 11.3.3) and 11.2.5; JGJ 476-2019 Clauses 8.5.6 and 9.4.5. Common points: calibrate tensioning equipment beforehand; bearing surfaces flat and perpendicular to the anchor axis; pre-tension once or twice at 0.1-0.2 x design load (JGJ 476: 10%-15%) before formal tensioning; loading rate 50-100 kN/min; GB 51004-2015 requires tensioning to 1.05Nt-1.10Nt holding 10min in rock/sand or 15min in cohesive soil, then unloading to the locking value; post-locking prestress change generally not over 10% of design; anti-floating anchor locking load preferably 0.8-1.0 x design; randomly sample >=10% of tensioned anchors for over-tensioning checks at not less than 1.2 x design.

Applicable Codes

  • DB11/T 1832.1-2021 · Specification for Construction Technology of Building Works (Part 1: Foundation Works) (Beijing) 第23.4.6条
  • GB 51004-2015 · Code for Construction of Building Foundation 第6.10.6条
  • GB 50086-2015 · Technical Code for Engineering of Ground Anchor and Shotcrete Support 第4.7.12~4.7.14条、第11.2.5条、第11.3.3条
  • JGJ 476-2019 · Technical Standard for Anti-Floating of Building Engineering 第8.5.6条、第9.4.5条及App. H

Topic Positioning

Operational rules and acceptance testing for the tensioning and locking of anti-floating anchors (prestressed anchors), compiling the four codes: Beijing DB11/T 1832.1-2021, and the national/industry standards GB 51004-2015, GB 50086-2015, JGJ 476-2019 - for tensioning plans, site disclosure, and acceptance testing.

Core Conclusions

1. Beijing DB11/T 1832.1-2021 Clause 23.4.6 (anti-floating anchor tensioning and locking):

  • Anchor rest period and grout/structure strength shall meet design before tensioning;
  • Tensioning equipment and gauges shall be calibrated beforehand;
  • The structure's bearing surface shall be flat and perpendicular to the anchor axis;
  • Tensioning shall proceed in an order avoiding interaction between neighboring anchors;
  • Pre-tension once or twice at 0.1-0.2 x the expected maximum test load to straighten the tendon and seat all parts;
  • Loading/unloading rate for load tests and tension-locking preferably 50-100 kN/min;
  • Over-tensioning is preferred, the over-tension load being the design locking load plus expected losses;
  • Load-dispersive anchors should use parallel jack groups for synchronized load-controlled tensioning of each unit; other methods allowed after comparative tests establish and compensate stress losses;
  • Cut the free (tensioning) length and cap the anchor only after acceptance;
  • At lock time the grout of the bonded length and the bearing-base concrete shall meet Table 23.4.6 (tiered by soil/rock anchor and tension/compression/compression-dispersive type - values per the code table); keep the force on the anchor axis without bending the prestressing tendon, using angle and bearing plates on the structure or ground surface where needed.

2. GB 51004-2015 Clause 6.10.6:

  • The bearing surface of the anchor head base shall be flat and perpendicular to the axis; calibrate equipment before tensioning;
  • Before formal tensioning, pre-tension once or twice at 0.1-0.2 x the design axial tension Nt to straighten the tendon and seat all parts;
  • Tension to 1.05Nt-1.10Nt, hold 10min in rock and sand strata and 15min in cohesive strata, then unload to the design locking value. Commentary: tensioning and locking is the last and most direct performance check of anchor construction; pre-tensioning reduces strand force imbalance and prestress loss; over-tensioning compensates losses from wedge pull-in at lock.

3. GB 50086-2015 "Code for engineering of ground anchors and shotcrete support":

  • 11.3.3: prestressed anti-floating anchors shall follow Clauses 4.7.12-4.7.14;
  • 4.7.12: grout and base concrete strengths not below Table 4.7.12; bearing surface flat and perpendicular; orderly tensioning avoiding neighbor interaction; calibrated equipment; pre-tension 0.1-0.2 x design once or twice; record load and deformation;
  • 4.7.13: after passing multi/single-cycle acceptance tests, load to the locking value at 50-100 kN/min and lock; account for losses from tendon draw-in and free-length friction; post-locking prestress change generally not over 10% of design - beyond that, compensating (secondary) tensioning is required; permanent anchors needing adjustment shall have re-tensionable heads, not sealed in concrete;
  • 11.2.5 (initial prestress of anti-floating anchors): locking load preferably 0.8-1.0 x the design anchor tension; for long-term stable buoyancy or strict deformation control, take the design value; for compression-dispersive anti-floating anchors, take the design value.

4. JGJ 476-2019 "Standard for anti-floating design and construction of building engineering":

  • 8.5.6: calibrate equipment; bearing surface flat; grout/base strengths per Table 8.5.6; pre-tension once or twice at 10%-15% of design; for load-dispersive anchors with locking load equal to design pullout, use parallel jacks synchronously, otherwise tension each unit from bottom to top with equal force; tension evenly and orderly, avoid concentrated tensioning affecting neighbors, do not disturb tendons/jacks/wedges during tensioning; fully record load and deformation; cap anchor heads promptly after tensioning;
  • 9.4.5: randomly sample >=10% of tensioned anchors for over-tensioning checks at not less than 1.2 x design; locking-value checks per Appendix H.

Applicable Boundaries

  • Tensioning-locking applies only to prestressed anchors (incl. prestressed anti-floating and load-dispersive/compression-dispersive anchors); non-prestressed anchors involve no locking.
  • Regions: Beijing projects follow DB11/T 1832.1-2021 first; elsewhere GB 51004-2015 and GB 50086-2015; anti-floating projects combine JGJ 476-2019. Explicit design requirements always prevail.
  • Pre-tension wording differs: GB 51004-2015/GB 50086-2015 use 0.1-0.2 x design tension; JGJ 476-2019 uses 10%-15% (narrower); DB11/T 1832.1-2021 uses 0.1-0.2 x expected maximum test load - on site the design document governs.
  • Grout/base strength values in Tables 23.4.6, 4.7.12, 8.5.6 are per the original code tables and are not expanded here.
  • Not applicable: staged loading of basic and multi/single-cycle acceptance tests (a separate process - GB 50086-2015 Section 12.1 IV).

Further Reading

  • DB11/T 1832.1-2021 Clause 23.4.6 and Table 23.4.6.
  • GB 51004-2015 Clause 6.10.6 and commentary (1.05Nt-1.10Nt hold 10/15min then unload to lock; over-tension compensating wedge pull-in).
  • GB 50086-2015 Clauses 4.7.12-4.7.14, 11.2.5, 11.3.3; Section 12.1 IV (acceptance tests).
  • JGJ 476-2019 Clauses 8.5.6, 9.4.5 and Appendix H (locking-value verification).

Keywords

  • 抗浮锚杆
  • 张拉锁定
  • 预应力锚杆
  • 预张拉
  • 超张拉
  • 锁定荷载
  • 锚杆张拉
  • 锁定值检验