Soil nail wall (composite soil nail wall): timing of lower-layer excavation after grouting the upper nails — the 48h fallback and 70% design strength control (GB 50739-2011 / GB 51004-2015 / DB11 489-2016 / JGJ 167-2009)
Two control calibers for excavating the next layer after grouting upper soil nails: national codes set "curing time or strength satisfying design" as the principle — where design is silent, cure at least 48h per GB 50739-2011 cl. 6.4.3 (time fallback); Beijing per DB11 489-2016 cl. 6.3.2 and collapsible-loess regions per JGJ 167-2009 cl. 6.4.2 require the grout and shotcrete face to reach 70% design strength before excavation (strength control). Prestressed anchors of composite soil nail walls require tensioning and lock-off (and grout at design strength) before excavating lower layers; GB 51004-2015 cl. 8.2.4 adds per-layer segment length preferably not over 30m.
Applicable Codes
- GB 50739-2011 复合土钉墙基坑支护技术规范 第6.4.3条
- DB11 489-2016 建筑基坑支护技术规程 第6.3.2条
- GB 51004-2015 建筑地基基础工程施工规范 第8.2.4条
- JGJ 167-2009 湿陷性黄土地区建筑基坑工程安全技术规程 第6.4.2条
Topic Positioning
Timing control for excavating the next soil layer after upper-nail grouting in soil nail wall (incl. composite walls and soil anchor support) excavations: the interplay of "time control (48h)" and "strength control (70% design strength)", plus the precondition of anchor tensioning and lock-off. For sequence control, safety disclosure and accident-liability determination.
Core Conclusions
Four code calibers govern the timing; excavating before strength is reached is a direct basis for collapse liability:
Time fallback (national) — GB 50739-2011 Technical Code for Composite Soil Nail Wall Retaining of Excavations, cl. 6.4.3: "The curing time after grouting an upper layer of nails shall satisfy the design; where the design specifies none, cure at least 48h before excavating the next layer. Prestressed anchors shall be tensioned and locked off before excavating the next layer."
Strength control (Beijing) — DB11 489-2016 Technical Specification for Retaining and Protection of Building Excavations, cl. 6.3.2: "Excavation and soil nail wall construction shall proceed top-down in stages and layers per design; the next soil layer may be excavated only after the upper nails' grout and the shotcrete face reach 70% of design strength." Beijing works must comply — merely waiting the time is insufficient; higher design requirements (e.g. 80%) prevail.
Strength control (collapsible loess) — JGJ 167-2009 cl. 6.4.2: "The next soil layer and nails may proceed only after the upper nails' grout and the shotcrete face reach 70% design strength. Excavation of the next layer is strictly forbidden from striking the upper soil nail structure."
Overall coordination (GB 51004-2015) — cl. 8.2.4 for soil nail and soil anchor excavations: (1) excavate only after cutoff walls or soldier-pile walls reach design strength and age; (2) coordinate excavation with support in cyclic operation; (3) excavate in layers and segments, segment length per layer preferably <=30m; (4) install nails/anchors promptly after each segment, shortening unsupported exposure; excavate the next layer only after the previous support's curing time or strength satisfies design. Commentary: generally at least 48h after nail grouting; anchors require tensioning, lock-off and grout at design strength before the next layer.
Synthesis: where design is silent, 48h is only the minimum time floor, not a sufficient condition; Beijing and loess-region works must control by "grout + shotcrete face at 70% design strength"; prestressed anchors in composite walls require tension-lock (and grout at strength) before downward excavation.
Applicable Boundaries
- Applies to the "excavate-support" cycle of soil nail walls, composite walls and soil-anchor excavations.
- Regional: Beijing executes DB11 489-2016's 70%; loess regions JGJ 167-2009's 70%; elsewhere GB 50739-2011's 48h fallback where design is silent; specific design requirements always prevail.
- Not applicable: ordinary sloped excavation and pile-anchor excavations without nails/anchors (those likewise need layering/segmenting and exposure control, but not this 48h/70% caliber); this card does not cover concrete member curing grades 7d/14d (GB 50666-2011 cl. 8.5.2 governs members, a different object from nail-grout curing).
- 48h is a floor, not a substitute for strength: judge primarily by strength, secondarily by time.
Further Reading
- GB 50739-2011 cl. 6.4.3 (curing time; anchor tension-lock).
- DB11 489-2016 cl. 6.3.2 (Beijing: grout and shotcrete face at 70% design strength).
- GB 51004-2015 cl. 8.2.4 and commentary (coordination, segment length <=30m, 48h, anchor tension-lock and grout strength).
- JGJ 167-2009 cl. 6.4.2 (70% strength; no striking the upper wall).
Keywords
- 土钉墙
- 复合土钉墙
- 注浆养护
- 48h
- 设计强度70%
- 下层土方开挖
- 预应力锚杆张拉锁定
- GB 50739-2011
- DB11 489-2016
- GB 51004-2015
- JGJ 167-2009
- 基坑分层分段开挖