Concrete curing time brackets: GB 50666-2011 cl. 8.5.2 (7d/14d brackets and conditions) + 28d for post-cast strips and linkage with mineral-admixture concrete curing
Curing time per GB 50666-2011 cl. 8.5.2 falls into 6 brackets: concrete made with Portland/ordinary Portland/slag Portland cement not less than 7d; other cements per cement properties; concrete with retarding admixtures or high-volume mineral admixtures, impermeable concrete, C60 and above, and post-cast strip concrete all not less than 14d; basement lowest-level and first-storey walls/columns appropriately extended; mass concrete per the construction scheme. Post-cast strips in waterproofed underground works must be cured not less than 28d per GB 50108-2008 cl. 5.2.13 (stricter rule applies).
Applicable Codes
- GB 50666-2011 混凝土结构工程施工规范 第8.5.2条
- GB 50108-2008 地下工程防水技术规范 第5.2.13条
- GB/T 51003-2014 矿物掺合料应用技术规范 第6.3.3条
- DB11/T 1832.3-2021 建筑工程施工工艺规程 第3部分:混凝土结构工程 第24.4.5条
Topic Positioning
The code basis of curing-time brackets in concrete structural construction: centered on GB 50666-2011 cl. 8.5.2, bracketed by cement type, admixture type, strength grade and member location; linked with the 28d for post-cast strips in waterproofed underground works (GB 50108-2008), 7d/14d for mineral-admixture concrete (GB/T 51003-2014), and the Beijing execution caliber (DB11/T 1832.3-2021).
Core Conclusions
I. GB 50666-2011 cl. 8.5.2 (cast-in-place works) — six curing-time brackets:
- Concrete made with Portland cement, ordinary Portland cement or slag Portland cement: not less than 7d; with other cement types, curing time is determined by cement properties (no fixed value);
- Concrete made with retarding admixtures or high-volume mineral admixtures: not less than 14d;
- Impermeable concrete and concrete of strength grade C60 and above: not less than 14d;
- Post-cast strip concrete: not less than 14d;
- Basement lowest-level walls/columns and first-storey walls/columns of the superstructure: curing time appropriately extended;
- Mass concrete: curing time per the construction scheme.
II. Key quantitative definitions and notes (cl. 8.5.2 commentary):
- Quantitative definition of "high-volume mineral admixture": concrete where fly ash or slag powder alone is not less than 30% of total binder, or their sum not less than 40%, counts as high-volume and follows 14d;
- Curing time includes formwork-on curing before decamping and curing after decamping — it shall not be restarted at decamping;
- Mass concrete curing time is controlled by temperature differences at the relevant points; curing may end only after the differences comply with cl. 8.7.3;
- Basement foundation slabs / transitions from underground to first-storey walls and columns involve long intervals, completed shrinkage and high restraint prone to vertical cracks; extend curing per actual conditions.
III. Stricter rule for post-cast strips in waterproofed locations (GB 50108-2008 cl. 5.2.13): Post-cast strip concrete shall be placed in one lift without construction joints; after placing it shall be cured promptly for not less than 28d. The commentary requires the strip concrete to be cured thoroughly wet for 6 weeks. I.e., GB 50666's 14d is the general structural floor; waterproofed underground locations follow the stricter 28d.
IV. Mineral-admixture concrete (GB/T 51003-2014 cl. 6.3.3): Moist curing not less than 7d; concrete with shrinkage-compensating, impermeability or retarding requirements not less than 14d; extend curing in cold or dry environments. Concrete with w/b below 0.40 has high autogenous shrinkage — cover and cure immediately when placed in dry or windy conditions; when water-curing, water temperature shall suit the concrete surface temperature.
V. Beijing execution caliber (DB11/T 1832.3-2021 cl. 24.4.5, consistent with the national code plus supplements):
- Horizontal members: cover with plastic film and water-spray curing; vertical walls: spray curing; condensate shall remain under the film; no spray curing when the day's minimum temperature is below 5 degrees C; apply curing agent where spraying is impractical;
- Cover and moist-cure within 12h after placing;
- Formwork-on curing of basement lowest-level and first-storey walls not less than 3d; concrete with Portland/ordinary Portland/slag Portland cements not less than 7d; impermeable, post-cast strip and C60+ concrete not less than 14d; mass concrete and winter concreting per the construction scheme.
Applicable Boundaries
- GB 50666-2011 applies to cast-in-place concrete structural works as the general floor; where brackets overlap (e.g. impermeable + high-volume admixture), execute the longer curing time.
- Post-cast strips in underground (waterproofed) works must follow GB 50108-2008's 28d, not 14d; superstructure strips follow GB 50666's 14d.
- The 14d bracket for "high-volume mineral admixture" applies only at the commentary thresholds (>=30% or >=40%); below them, ordinary-admixture concrete follows GB/T 51003-2014 moist curing preferably not less than 7d.
- Mass concrete has no fixed curing time — per the construction scheme, with the cl. 8.7.3 temperature-difference control as the end condition.
- DB11/T 1832.3-2021 is a Beijing local procedure; other regions follow their current local procedures; no spray curing below 5 degrees C daily minimum.
- Curing time includes formwork-on and post-decamping curing, counted from completion of placing; watering frequency keeps the surface moist.
Further Reading
- GB 50666-2011 cl. 8.5.2 and commentary (quantitative definition of high-volume admixtures; curing includes formwork-on time), cl. 8.5.1 (cover and moist-cure within 12h), cl. 8.7.3 (mass concrete temperature-difference control);
- GB 50108-2008 Technical Code for Waterproofing of Underground Works, cl. 5.2.13 and commentary (one-lift placing, 28d curing, thoroughly wet 6 weeks);
- GB/T 51003-2014 Technical Specification for Application of Mineral Admixtures, cl. 6.3.3 and commentary (7d/14d moist curing; covering measures);
- DB11/T 1832.3-2021 cl. 24.4.5 (Beijing caliber: 3d formwork-on curing, 5-degree spray restriction, 12h covering). These four are the direct evidence sources; consult the current effective versions for full texts.