Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Preconditions for rebar mechanical splicing or welding and cutting splice test specimens from the completed works (GB 50666-2011 / GB 55008-2021 / GB 50204-2015)

Before rebar mechanical splicing/welding, entry conditions such as certified personnel and technique qualification tests must be met (GB 50666-2011 cl. 5.4.2, 5.4.3, 5.5.5); splice specimens shall be cut from the completed works — GB 55008-2021 cl. 5.3.1 (mandatory provision) requires they "be cut from the completed works", and the commentary of GB 50204-2015 cl. 5.4.2 specifies they shall be cut from the works after rebar installation and before concrete placement.

Applicable Codes

  • GB 55008-2021 混凝土结构通用规范
  • GB 50204-2015 混凝土结构工程施工质量验收规范
  • GB 50666-2011 混凝土结构工程施工规范
  • JGJ 107-2016 钢筋机械连接技术规程
  • JGJ 18 钢筋焊接及验收规程

Topic Positioning

This card answers, for concrete structural works, two questions about rebar mechanical splicing and welded splicing: "what conditions must exist before construction" and "where are splice specimens cut from", based on the original provisions of three standards: GB 50666-2011 Code for Construction of Concrete Structures, GB 55008-2021 General Code for Concrete Structures, and GB 50204-2015 Code for Quality Acceptance of Concrete Structure Construction.

Core Conclusions

I. Preconditions for mechanical splicing (GB 50666-2011 cl. 5.4.2):

  1. Operators fabricating rebar splices shall take up their posts after passing specialized training; rebar splice fabrication may proceed only after passing the technique qualification test.
  2. The concrete cover thickness of mechanical splices should comply with the minimum cover requirements for structural rebar in the current national standard GB 50010 Code for Design of Concrete Structures, and shall not be less than 15mm; the lateral clear spacing between splices should not be less than 25mm.
  3. After installing threaded coupler splices, the tightening torque shall be checked with a dedicated torque wrench; the fluctuation range of the indentation diameter of swaged splices shall be controlled within the allowable fluctuation range and checked with dedicated gauges. The torque wrench used for installation and that used for checking shall be used separately — their accuracy and calibration requirements differ.
  4. The application scope, technique requirements, coupler materials and quality requirements of mechanical splices shall comply with the current industry standard JGJ 107 Technical Specification for Mechanical Splicing of Steel Bars.

II. Preconditions for welding (GB 50666-2011 cl. 5.4.3):

  1. Welders engaged in rebar welding shall hold a rebar welder qualification certificate and work within the scope specified in the certificate.
  2. Before rebar welding on a project, the welders participating shall perform welding technique tests under site conditions and may weld only after passing; if the rebar grade or diameter changes during welding, the technique test shall be repeated. The materials, equipment, consumables and working conditions of the technique test shall all match actual construction.
  3. For fine-grain hot-rolled rebars and ordinary hot-rolled rebars over 28mm diameter, welding parameters shall be determined by test; head-heat-treated (quenched-and-tempered) rebars are unsuitable for welding.
  4. Electroslag pressure welding shall be used only for connecting vertical structural rebar in columns, walls and similar members.
  5. The application scope, technique requirements, selection of electrodes and fluxes, welding operations and quality requirements of welded splices shall comply with the current industry standard JGJ 18 Specification for Welding and Acceptance of Steel Bars.

III. Common quality-inspection requirements (GB 50666-2011 cl. 5.5.5): before rebar welding and mechanical splicing, technique qualification tests shall be performed; for mechanical splicing, valid type-test reports shall be checked; welded and mechanical splices shall be 100% inspected for appearance; lapped splices shall be sampled for lap length; threaded splices shall be sampled for tightening torque; welders shall self-inspect promptly and find and eliminate causes of weld defects and anomalies; splice percentages shall be checked during construction; splice specimens shall be taken for mechanical property tests per JGJ 107 and JGJ 18.

IV. Specimen cutting location (mandatory requirement):

  • GB 55008-2021 cl. 5.3.1 (mandatory provision): "Rebar mechanical splice or welded splice specimens shall be cut from the completed works and tested for performance as required." Rationale: specimens cut from the installed rebar works represent and reflect the connection quality more truly.
  • GB 50204-2015 cl. 5.4.2: where rebars are mechanically spliced or welded, the mechanical properties (and bending properties, for welding only) of splices shall comply with current national standards, and "splice specimens shall be cut from the works"; inspection quantities per JGJ 107 and JGJ 18; inspection method: checking quality certificates and sampling test reports; for mechanical splices the quality documents shall include a valid type-test report. The commentary states: to ensure specimens represent actual quality, splice specimens shall be cut from the works after rebar installation and before concrete placement.
  • Batch size for cutting per JGJ 107-2016 cl. 7.0.5: splices of the same bar manufacturer, strength grade, diameter, type and form shall be inspected and accepted in batches of 500; fewer than 500 also counts as one batch.

Applicable Boundaries

Applicable to preconditions checking and splice specimen acceptance for mechanical splices (threaded, swaged and other coupler connections) and welded splices (flash butt, arc, electroslag pressure welding etc.) in cast-in-place concrete rebar sub-works. Special restrictions: electroslag pressure welding only for vertical rebar of columns/walls; quenched-and-tempered rebars unsuitable for welding; welding parameters of fine-grain hot-rolled bars and ordinary hot-rolled bars over 28mm determined by test; changes of rebar grade or diameter require repeating the welding technique test. Cutting specimens from the works is a mandatory requirement of the all-mandatory GB 55008-2021 and shall not be replaced by submitted samples on site; for genuinely difficult cases such as precast structures, verify the applicable scope before applying local-code exceptions. For specific sampling quantities per batch and retest rules (including batch enlargement), see the JGJ 107 acceptance-batch card cited by this card.

Further Reading

  • GB 55008-2021 General Code for Concrete Structures, cl. 5.3.1 (mandatory provision, construction and acceptance chapter).
  • GB 50204-2015 Code for Quality Acceptance of Concrete Structure Construction, cl. 5.4.2 and commentary (Chapter 5 rebar sub-works).
  • GB 50666-2011 Code for Construction of Concrete Structures, cl. 5.4.2, 5.4.3, 5.5.5 (Chapter 5 rebar works).
  • JGJ 107-2016 Technical Specification for Mechanical Splicing of Steel Bars, Chapter 7 "site inspection and acceptance of splices", cl. 7.0.5 (batch division); JGJ 18 Specification for Welding and Acceptance of Steel Bars.
  • Sampling quantities and retest rules: see the built card "Rebar mechanical splice acceptance batch division and sampling rules (JGJ 107-2016 and railway TB 10424-2018)".

Keywords

  • 钢筋机械连接
  • 钢筋焊接
  • 接头试件截取
  • 工程实体
  • 工艺检验
  • 型式检验报告
  • 焊工考试合格证
  • GB 50666

Cited By