Acceptance lotting and sampling rules for rebar mechanical splice joints (JGJ 107-2016 and railway TB 10424-2018)
Joints of the same rebar manufacturer, strength grade, size, type, and form constitute one acceptance lot per 500 joints (fewer than 500 also counts as one lot); per lot randomly cut 3 specimens for ultimate tensile strength testing (2 for lots under 200), thread/swaged joints inspected 10% at installation; with only 1 failed specimen, retest 6 (4 for small lots); 2 or more failures fail the lot outright; after 10 consecutive lots at 100% first-pass, or with product certification, lots may enlarge to 1000–1500. Railway per TB 10424-2018: mechanical-property testing per 500 joints per lot, the contractor tests once per lot, the supervisor witnesses 20% but at least once; tightening-torque check 10% per lot and ≥20 joints, supervisor witness ≥4.
Applicable Codes
- JGJ 107-2016 · Technical Specification for Mechanical Connection of Steel Bars
- TB 10424-2018 · Standard for Construction Quality Acceptance of Railway Concrete Works
Topic Positioning
Lot division, sampling counts, and pass/fail rules for site inspection and acceptance of rebar mechanical splice joints (parallel-thread, swaged, etc.) under JGJ 107-2016, Technical Specification for Mechanical Splicing of Steel Bars, Chapter 7; railway works additionally follow TB 10424-2018, Standard for Constructional Quality Acceptance of Railway Concrete Works, Section 5.4.
Core Conclusions
- Lot division (7.0.5): joints of the same rebar manufacturer, strength grade, size, type, and form — one acceptance lot per 500 joints; fewer than 500 also counts as one lot and must not be merged with other lots.
- Technique (process) inspection (7.0.2): performed before construction on rebars delivered from each mill, covering every joint type and form, items being monotonic-loading ultimate tensile strength and residual deformation; ≥3 specimens per size; supplementary inspection is required when the rebar manufacturer or the splice technology provider changes; a failed technique inspection allows adjustment of process parameters and re-inspection, without invoking the retest rules.
- Site sampling (7.0.6, 7.0.7): per acceptance lot, randomly cut 3 joint specimens from the structure for ultimate tensile strength; after installation, thread joints have tightening torque checked on 10% of the lot — where failures exceed 5% of the checked joints, re-tighten all joints until passing; swaged sleeve joints: check 10% per lot for crimp diameter or post-swaging sleeve length (meeting Clause 6.3.3 item 3) and rebar insertion depth.
- Judgment and retest (7.0.7): if all 3 specimens meet the grade requirements of Table 3.0.5 the lot passes; with exactly 1 failure, take 6 more for retest — any further failure fails the lot; with 2 or 3 failures the lot fails outright with no retest allowed.
- Swaged joint sampling (7.0.5 item 2 of 7.0.6): where appearance/dimension failures exceed 10%, 3 specimens may be cut from the failed-appearance joints of the lot for ultimate tensile testing and evaluated per 7.0.7.
- Witnessed sampling (7.0.8): where random cutting from the structure is impractical, witnessed sampling is allowed — with supervisor and QC personnel present throughout, cut rebar specimens at random from inspected and passed threaded bar ends and assemble joint specimens with randomly drawn connectors.
- Small lots and enlargement (7.0.9, 7.0.10): lots under 200 joints sample 2 specimens — both passing passes the lot, 1 failure leads to 4 more for retest and any further failure fails the lot; with 10 consecutive lots at 100% first-pass tensile results, lots may enlarge to 1000; certified joint products may enlarge to 1000; both conditions together allow 1500. Any failed evaluation after enlargement reverts subsequent lots to 500 permanently.
- Railway works (TB 10424-2018, 5.4.1–5.4.2): mechanical-property lots are 500 joints per batch of same-condition, same-material, same-grade, same-size, same-form joints (fewer than 500 also one lot); the contractor tests once per lot, the supervisor witnesses 20% of the contractor's tests but at least once; upset/rolled-thread torque checks: 500 joints per lot, contractor checks 10% and ≥20 joints per lot, supervisor witnesses 20% and ≥4 joints.
Applicable Boundaries
Applies to site inspection and acceptance of rebar mechanical splices in building and general municipal works; railway works follow TB 10424-2018 (mechanical-property lots are likewise 500, but the contractor tests once per lot and the supervisor witnesses 20% at least once — different from JGJ 107's rule of randomly cutting 3 specimens per lot). Lot enlargement applies only after 10 consecutive 100% first-pass lots or with valid product certification; any failure after enlargement reverts to 500 permanently. Technique inspections are performed per rebar manufacturer; changing the manufacturer or technology provider requires supplementary inspection.
Further Reading
See JGJ 107-2016, Chapter 7, Clauses 7.0.2, 7.0.5–7.0.10; joint strength-grade requirements in Table 3.0.5, residual deformation in Table 3.0.7, monotonic-loading regime in Appendix A Table A.1.3, swaged-joint crimp requirements in Clause 6.3.3 item 3. Railway: TB 10424-2018, Clauses 5.4.1–5.4.3; 5.4.3 additionally governs joint position and connection zones (splice percentages ≤50% in tension zones of flexural members and ≤25% in axially tensioned members; connection-zone length 35d and not less than 500 mm).