Attribution of site sampling inspection costs (including acceptance-lot sampling of rebar mechanical splice joints): the contractor's inspection and testing costs within overheads versus the quality testing costs listed separately by the employer, and the rule shifting the cost to the contractor when tests fail
Routine sampling and testing done under the construction quality acceptance standards (including the ultimate tensile strength test on 3 specimens sampled per 500-joint acceptance lot of rebar splices) falls under the contractor's inspection and testing costs within overheads - already included in the charge, not billed again. Testing commissioned by the employer from a testing agency is listed and paid separately by the employer under project costs other than the works (MOHURD Order No. 57, Article 17: 'when compiling project estimates and budgets the employer shall reasonably allow for construction quality testing costs, list them separately and pay them in time under the contract'); but where materials supplied by the contractor with certificates of conformity fail testing, that testing cost is paid by the contractor. Testing of new structures and new materials, destructive testing of members and other specially required testing, and testing required by the design beyond the acceptance standards are none of them the contractor's inspection and testing costs.
Applicable Codes
- 《建设工程质量检测管理办法》(住房和城乡建设部令第57号)第十七条
- JGJ 107-2016 · Technical Specification for Mechanical Connection of Steel Bars 第7.0.5、7.0.7条
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.9.2条(企业管理费—检验试验费)
- 湖北省建筑安装工程费用定额(2024)企业管理费—检验试验费
Scope and purpose
Determining who bears the inspection costs of site sampling during construction (e.g. the ultimate tensile strength test on rebar mechanical splice joints sampled by acceptance lot): which belong to the contractor's inspection and testing costs within overheads, which the employer should list under project costs other than the works, and how the cost shifts to the contractor when material tests fail.
Key conclusions
1. Scope of the contractor's 'inspection and testing costs' (within overheads, not billed separately) Clause 3.9.2 of the railway estimate and budget compilation rules defines inspection and testing costs: 'costs incurred by the construction enterprise in the general appraisal and inspection of the plant, materials, members and structures of the works as required by the codes and the construction quality acceptance standards, including the costs of materials and chemicals consumed in tests at its own laboratory and, as needed, the costs of testing commissioned by the contractor to outside bodies. Excluded: test costs for new structures and new materials chargeable to research and test funds and the three science and technology funds; the costs of testing materials with factory certificates required by the employer, destructive testing of members and other specially required testing; the costs of testing commissioned to outside bodies by the employer; and testing required by the design beyond the construction quality acceptance standards.' The buildings basis is aligned: inspection and testing costs 'mean the costs incurred by the construction enterprise in the general appraisal and inspection of the building and its materials, members and installed works under the relevant standards, including the costs of materials consumed in tests at its own laboratory. Excluded: test costs for new structures and new materials, the costs of destructive testing of members and other specially required testing, and the costs of testing entrusted by the employer to a testing agency; the costs of such testing are listed by the employer under project costs other than the works.' Hence: routine sampling and testing done under the construction quality acceptance standards and the codes (including the ultimate tensile strength test on 3 specimens per acceptance lot of joints) is the contractor's inspection and testing cost, already included in overheads, and may not be charged to the employer again.
2. Employer-commissioned testing is listed separately Article 17 of the Measures for the Administration of Construction Quality Testing (Ministry of Housing and Urban-Rural Development Order No. 57): 'The employer shall, when compiling project estimates and budgets, reasonably allow for construction quality testing costs, list them separately and pay them in time as agreed in the contract.' That is, testing carried out by an agency commissioned by the employer is listed separately under project costs other than the works (quality testing costs) and is not part of the contractor's inspection and testing costs within overheads.
3. On failed tests, the cost reverses to the contractor 'Where materials provided by the construction enterprise with certificates of conformity fail testing, that testing cost is paid by the construction enterprise.' - even employer-commissioned testing, once material with a conformity certificate fails, is paid for by the contractor.
4. Sampling scale drives testing cost, but not its attribution Joint sampling proceeds by acceptance lot: joints from the same bar producer, same strength grade, same size, same type and same form constitute one lot of 500, with fewer than 500 also forming one lot (JGJ 107-2016 Clause 7.0.5); from each lot 3 joint specimens are cut at random from the structure for the ultimate tensile strength test and rated per the joint class required by the design - all 3 passing rates the lot as passing; where only 1 fails, 6 more are taken for retesting, and a further failure rejects the lot (Clause 7.0.7). More acceptance lots and more sample groups raise the testing cost, but the cost remains within the contractor's inspection and testing costs.
Applicability boundaries
- The line between 'general appraisal and inspection' (the contractor's inspection and testing costs) and 'employer-commissioned testing' (listed separately by the employer) is drawn by who commissions the test and for what purpose, not by the test's name; the same test commissioned by the employer goes to project costs other than the works, while self-inspection by the contractor stays within overheads.
- Testing required by the design beyond the construction quality acceptance standards, test costs for new structures and new materials, and destructive testing of members are not borne by the contractor's inspection and testing costs.
- Cost item names and charging bases follow the pricing basis applicable to the project (building fee norms, railway estimate and budget compilation rules, highway cost-of-works composition, etc.) and are not interchangeable across sectors; in the railway basis, inspection and testing costs sit within overheads, and on-costs = (base-period labour cost + base-period plant and small tools cost) x the on-costs percentage rate (TB 10801-2024 Clause 3.9.3).
- Where the contract provides otherwise for inspection and testing costs (e.g. a category of testing agreed to be borne by the employer), the contract prevails, but the boundary 'employer-commissioned testing is not the contractor's inspection and testing cost' may not be crossed.
Further reading
- Measures for the Administration of Construction Quality Testing (MOHURD Order No. 57), Article 17 (the employer to allow for and list quality testing costs separately)
- TB 10801-2024, Compilation Rules for Design Estimates and Budgets of Railway Capital Construction Projects, Section 3.9 (on-costs - contents of overheads, including inspection and testing costs), Clause 3.9.3 (on-costs formula)
- Hubei Province building and installation works fee norms (2024), overheads composition item 8 'inspection and testing costs' (scope included and excluded, and who pays when material tests fail)
- JGJ 107-2016, Technical Specification for Mechanical Splicing of Steel Reinforcing Bars, Clause 7.0.5 (acceptance lots of 500), Clause 7.0.7 (3 specimens per lot, retest rules)
Keywords
- 检验试验费
- 质量检测费
- 建设单位委托检测
- project costs other than the works (land, consents, supervision, etc.)
- overheads (company and site)
- 接头抽检
- 验收批
- 费用归属