Static load test counts for foundation piles: design-basis test piles at least 3 per same condition; acceptance static load testing of working piles at least 1% of the pile sub-division's total under the same condition and never fewer than 3 - plus the 'same condition' definition and the high-strain alternative
Two classes of static load test counts: JGJ 106-2014 clause 3.3.1 - design-basis test piles, counts meeting the design and not fewer than 3 under the same condition, or not fewer than 2 where the expected total is under 50 piles; clause 3.3.4 - where any of six conditions holds (grade-A pile foundations, no pre-construction static test, changed process parameters or abnormal quality, complex ground with low reliability, new pile type or process locally, heaved or displaced piles in squeezed groups), single-pile vertical compressive static load testing carries the acceptance check, not fewer than 1% of the pile sub-division's total under the same condition and never fewer than 3 (2 where the total is under 50). GB 50202-2018 clause 5.1.6 to the same effect (grade A or complex ground: 1% and at least 3) and, in regions with experience and comparative data, allows grade-B / C foundations to use high-strain testing instead - not fewer than 5% of the total and 10 piles.
Applicable Codes
- JGJ 106-2014 · Technical Code for Testing of Building Foundation Piles 第3.3.1条、第3.3.4条、第3.3.6条、第3.3.7条
- GB 50202-2018 · Standard for Acceptance of Construction Quality of Building Foundation Works 第5.1.6条
- GB 50007《建筑地基基础设计规范》(设计等级划分)
- JGJ 94《建筑桩基技术规范》
Positioning
The count rules for single-pile vertical compressive static load tests of building foundation piles: the minimum counts, bases and the 'same condition' definition for the two classes - design-basis test piles and acceptance-basis working piles - for fixing test counts and thence test costs.
Core conclusions
1. Design-basis test piles (JGJ 106-2014 clause 3.3.1) Verbatim: 'Design-basis test pile testing shall follow the pile stress state fixed by the design and use the corresponding static load method to determine the ultimate bearing capacity; the count shall meet the design and, under the same condition, shall not be fewer than 3; where the expected total of working piles is under 50, not fewer than 2.' Commentary points:
- 'Stress state' means compression, uplift and lateral - choose the method accordingly.
- 'Same condition': similar ground and pile length, with the same bearing stratum, pile type, diameter and forming process; a large project's 'same condition' may span several pile sub-division (sub-sub-division) works; one sub-division may hold several 'same conditions' (400mm and 500mm pipe piles are treated apart).
- 'Three piles per same condition is the floor for a sound evaluation'; counts may rise where the basis is insufficient or the design asks; major changes of pile parameters or process call for re-testing.
- End-bearing large bored piles beyond equipment or site limits may use deep plate load tests or rock load tests per JGJ 94 / GB 50007, or static tests on smaller-diameter piles with strain instrumentation (allowing for size effect) - after technical appraisal by the responsible parties.
- Sites shall be representative with boreholes nearby; where shaft and end resistance tests are required, strain elements are installed during test-pile construction.
2. Acceptance testing of working piles (JGJ 106-2014 clause 3.3.4) Verbatim: 'Where any of the following holds, single-pile vertical compressive static load testing shall carry the acceptance check. The count shall not be fewer than 1% of the pile sub-division's total under the same condition, and not fewer than 3; where the total is under 50, not fewer than 2.' Six triggers: 1 grade-A design; 2 no single-pile static test before construction per 3.3.1; 3 a pre-construction test done but process parameters changed or quality anomalies appeared; 4 complex ground, low reliability of pile quality; 5 new pile type or process in the region; 6 heaved or displaced piles in squeezed groups. Commentary: pile foundations are sub-division works accepted as such, so acceptance counts are capped at the sub-division; squeezed driving can break, tear or heave piles (dense groups, poor order, fast rates) with the pre-tests too few to reveal the effect - post-construction capacity may diverge far from the tests; where a condition holds but count or method cannot follow this clause, clauses 3.3.6 / 3.3.7 provide the alternative methods.
3. The acceptance standard (GB 50202-2018 clause 5.1.6) Verbatim: 'For grade-A design or complex ground, static load testing shall check pile bearing capacity - not fewer than 1% of the total and 3 piles, or 2 where the total is under 50. In regions with experience and comparative data, grade-B and grade-C foundations may use the high-strain method for vertical compressive capacity - not fewer than 5% of the total and 10 piles.' Commentary: classification per GB 50007; where ground is simple and local experience ample, counts may be set by the design; pre-construction test piles not failed to failure and used in the works serve as acceptance evidence; non-static-test counts follow JGJ 106.
4. Cost meaning Static load tests price per pile tested (each including kentledge or anchors, mobilisation and labour), so the charging base = max(code floor (1% and >=3; >=2 under 50), design extras); 1% is a floor - stricter design, complex ground or stricter local rules raise counts and costs. Different 'same conditions' (diameter, type, process) each meet the floor separately.
Applicable boundaries
- For concrete bored and precast piles of building works; railway, highway and water works follow their own standards with possibly different counts.
- 1%, 3 and 2 are floors: counts satisfy the design and never fall below them.
- Bases differ: JGJ 106 clause 3.3.4 counts on the 'same-condition pile sub-division total' (sub-division accepted alone), GB 50202 clause 5.1.6 says 'total piles' - in practice accept by sub-division and group by same condition, never diluting or inflating by the whole unit works.
- The high-strain alternative (grade B / C with local experience and comparative data, 5% and 10 piles) never replaces static tests for grade A or complex ground; the six triggers call for static testing.
- Test piles (3) and acceptance tests (1% and 3) are two stages and two costs - never merged or double-charged.
Further reading
JGJ 106-2014 clauses 3.3.1 (with commentary), 3.3.4, 3.3.6-3.3.7; GB 50202-2018 clause 5.1.6 and commentary; GB 50007 (design grades); JGJ 94 (end-bearing large bored piles).