Casting and counting concrete test cubes: standard curing, same-condition curing, and impermeability specimens

Standard-cured cubes: sample ≥1 per 100 batches and not more than 100 m³; for continuous pours over 1000 m³, ≥1 per 200 m³; ≥1 per floor. Same-condition cured cubes of one strength grade: preferably not fewer than 10 sets and not less than 3 sets, ≥1 set per two consecutive floors. Impermeability specimens: one set (6 pieces) per 500 m³ continuous pour, and not fewer than 2 sets per project. Specimens are taken randomly at the casting point, 3 per set, under witnessed sampling.

Applicable Codes

  • GB/T 50107-2010 混凝土强度检验评定标准
  • GB 50204-2015 混凝土结构工程施工质量验收规范
  • DB22/T 5040-2020 建设工程见证取样检测标准
  • DB62/T 3023-2018 混凝土工程施工工艺规程

Topic Positioning

A consolidated summary of the core rules for casting and counting concrete test cubes (specimens): sampling frequency, set counts, and bottom-line requirements for standard-cured, same-condition-cured, and impermeability specimens — directly usable for preparing witnessed-sampling plans and construction schemes.

Core Conclusions

  1. Basic rules: specimens are taken randomly at the concrete casting point, 3 per set from the same batch or same truck of mix, under the witnessed sampling and testing system.
  2. Standard-cured specimens (for strength evaluation): for the same mix proportion, sample ≥1 per 100 batches mixed and not more than 100 m³; ≥1 per work shift when fewer than 100 batches; for continuous pours over 1000 m³, ≥1 per 200 m³; ≥1 per floor of buildings; at least one set per sampling. Specimens for evaluation must not be confused with same-condition specimens used during construction.
  3. Same-condition cured specimens (for in-situ structure verification): preferably not fewer than 10 sets and not less than 3 sets per strength grade (10 sets enable statistical evaluation; 3 sets is the minimum representativeness for non-statistical evaluation); ≥1 set per two consecutive floors and ≥1 set per 2000 m³; sampled under witness at the point of placement into forms and cured beside the structural member; in winter construction keep ≥2 additional sets; formwork-removal cubes at least one set per construction flow section.
  4. Impermeability specimens: one set per 500 m³ of continuous pour (6 per set), not fewer than 2 sets per project.
  5. Worked example: a single-floor continuous pour of 320 m³ — standard curing by the dual condition "100 batches and not more than 100 m³", whichever comes first, gives about 3 sets, also satisfying ≥1 per floor; same-condition sets placed at 1 per two consecutive floors, subject to the building-wide 10-set bottom line.

Applicable Boundaries

Applies to ordinary concrete structures of building and municipal works. Note that "100 batches and not more than 100 m³" is a dual condition, whichever is reached first; a "work shift" is 8 h; set counts for ready-mixed impermeability specimens depend on structural scale. Details such as strength conversion factors for non-standard specimen sizes and equivalent curing age (600 °C·d) conversion are not included here — consult the code text.

Further Reading

See GB/T 50107-2010, Standard for Evaluation of Concrete Compressive Strength, Clauses 4.1.3–4.1.4; GB 50204-2015, Code for Quality Acceptance of Concrete Structure Construction, Appendix C (incl. same-condition specimen strength testing and equivalent curing age conversion); DB22/T 5040-2020, Standard for Witnessed Sampling and Testing of Construction Works, Clause 8.1.2; DB62/T 3023-2018, Workmanship Specification for Concrete Works, Clause 5.3.5.