Four temperature-control indicators for mass concrete construction: placing temperature, temperature rise, interior-surface difference and cooling-rate limits (GB 50496-2018 cl. 3.0.4, 5.1.7 + GB 50666-2011 cl. 8.7.3)
Four mass concrete temperature-control indicators: placing temperature preferably 5-30 degrees C (GB 50496-2018 cl. 5.1.7; GB 50666-2011: preferably not above 30); temperature rise above the placing temperature preferably not over 50 degrees C (GB 50496-2018 cl. 3.0.4, mandatory); interior-surface difference preferably not over 25 degrees C, and the surface-to-air difference when removing insulation not over 20 degrees C (GB 50496-2018 cl. 3.0.4); GB 50666-2011 cl. 8.7.3: the difference between 40-100mm below the surface and the surface not over 25 degrees C, that between this point and the ambient after decamping not over 25 degrees C, and between adjacent internal points not over 25 degrees C; cooling rate preferably not over 2.0 degrees C/d (both codes; GB 50666-2011 allows relaxation with reliable experience). Both codes must be satisfied simultaneously.
Applicable Codes
- GB 50496-2018 · Standard for Mass Concrete Construction 第3.0.4条、第5.1.7条
- GB 50666-2011 · Code for Construction of Concrete Structures 第8.7.3条
Topic Positioning
This card consolidates the current national limits of the four core temperature-control indicators of mass concrete construction — placing temperature, temperature rise, interior-surface difference and cooling rate — covering GB 50496-2018 Standard for Construction of Mass Concrete (the dedicated standard; cl. 3.0.4 is mandatory) and GB 50666-2011 cl. 8.7.3 (workmanship provisions), for compiling temperature-control schemes, judging site readings and compliance checking.
Core Conclusions
GB 50496-2018 cl. 3.0.4 (mandatory provision): temperature-control indicators of mass concrete construction shall comply with: 1 The temperature rise of the concrete pour above the placing temperature should not exceed 50 degrees C; 2 The interior-surface temperature difference of the pour (excluding the shrinkage-equivalent temperature) should not exceed 25 degrees C; 3 The cooling rate of the pour should not exceed 2.0 degrees C/d; 4 When removing insulation covers, the surface-to-atmosphere difference of the pour shall not exceed 20 degrees C. Cl. 5.1.7: the placing temperature should be controlled at 5-30 degrees C (the 5-degree floor is for winter anti-freeze).
GB 50666-2011 cl. 8.7.3: 1 The placing temperature should not exceed 30 degrees C; the maximum temperature rise of the pour should not exceed 50 degrees C. 2 During covered or formwork-on curing, the difference between the temperature 40-100mm below the surface of the pour and the surface temperature shall not exceed 25 degrees C; after ending covered curing or decamping, the difference between the temperature at that position and the ambient shall not exceed 25 degrees C. 3 The difference between adjacent internal measuring points shall not exceed 25 degrees C. 4 The cooling rate should not exceed 2.0 degrees C/d; with reliable experience, this may be relaxed.
Key interpretations:
- Taking 5-30 degrees C for placing temperature covers both codes (GB 50496-2018 sets the floor, GB 50666-2011 the ceiling).
- Temperature-difference control has two stages: during curing, compare "40-100mm-below-surface vs surface", both <=25 degrees C; after ending covered curing or decamping, compare "that position vs ambient", <=25 degrees C; GB 50496-2018 additionally limits the surface-to-air difference when removing insulation to 20 degrees C, stricter than 25.
- Surface temperature means that measured between the insulation cover or formwork and the concrete; after decamping it cannot be measured, so the 40-100mm-below-surface point substitutes. When a difference trends above 25 degrees C, add insulation cover (or hang insulation outside the formwork); after decamping, re-cover or add external insulation.
- Controlling the maximum temperature rise is the key to controlling differences, mainly via the mix proportion; before placing, compute the adiabatic temperature rise per GB 50496 — the computed adiabatic rise plus the estimated placing temperature gives the estimated internal maximum temperature.
Applicable Boundaries
Applies to compiling mass concrete temperature-control schemes, judging readings and compliance checking. GB 50666-2011 cl. 8.7.3 applies to mass concrete (foundations, columns, walls, beams etc.) in concrete structural works; foundation mass concrete may end covered curing when the 40-100mm-below-surface vs ambient difference is below 25 degrees C (cl. 8.5.6); columns, walls and beams may reference this for decamping time. The two national standards have different positioning (workmanship code vs dedicated standard); schemes must satisfy both; the indicators are minimum compliance and actual schemes may be stricter. Measuring-point layout per GB 50666-2011 cl. 8.7.4, 8.7.5.
Further Reading
- GB 50496-2018 cl. 3.0.4 (mandatory) and cl. 5.1.7 (placing temperature 5-30 degrees C); adiabatic rise computation methods in that standard (for estimating the maximum rise).
- GB 50666-2011 cl. 8.7.3 (commentary details the two-stage difference control and surface-temperature definition), cl. 8.5.6 (end of covered curing), cl. 8.7.4 and 8.7.5 (measuring-point layout).
- GB/T 51028-2015 Code for Temperature Measurement and Control of Mass Concrete — refined site measurement frequency and alarm thresholds, usable as site control reference (e.g. cooling-rate alarm thresholds stricter than 2.0 degrees C/d).
- Other mass/cast-in-place control points such as construction joints are in the related cards cited by this card.