Construction joint locations in concrete structures: recommended positions of horizontal/vertical construction joints in columns, walls, beams, slabs and stairs (GB 50666-2011 cl. 8.6.2, 8.6.3 + DB11/T 1832.3-2021 cl. 23.4.4)
Construction joints should be located where structural shear is small and construction is convenient. Horizontal joints (GB 50666-2011 cl. 8.6.2): columns and walls may be jointed at the top surface of foundations/floor structures (column: 0-100mm below... above the top surface 0-100mm; wall: 0-300mm) or at the bottom surface of floor structures (0-50mm from the bottom face; 0-20mm below the beam haunch where present). Vertical joints (cl. 8.6.3): one-way primary/secondary beam slabs within the middle 1/3 of the secondary beam span; one-way slabs anywhere parallel to the span direction; stair flights within the end 1/3 of the flight span; walls within the middle 1/3 of the door-lintel span or at wall intersections. Beijing DB11/T 1832.3-2021 cl. 23.4.4: column joints about 5mm above the soffit of the top slab; beam/slab joints within the middle 1/3 of the span; stairs without shear walls jointed in the 1/3 flight above the landing (3-4 steps); joints require removal of the weak layer/loose debris, washing and wetting, and for horizontal joints a same-composition cement-mortar regletering layer not thicker than 30mm. Joints at special locations or requiring rebar adjustment need designer confirmation.
Applicable Codes
- GB 50666-2011 混凝土结构工程施工规范 第8.6.2条、第8.6.3条
- DB11/T 1832.3-2021 建筑工程施工工艺规程 第3部分:混凝土结构工程 第23.4.4条
Topic Positioning
Code provisions on recommended locations of construction joints (horizontal, vertical, and post-cast strips) in cast-in-place concrete structural works, covering columns, walls, beams, slabs and stairs, per mandatory national standard GB 50666-2011 cl. 8.6.2 and 8.6.3, and Beijing local standard DB11/T 1832.3-2021 Construction Work Procedure Part 3: Concrete Structure Works, cl. 23.4.4. Usable for construction-scheme compilation, technical disclosure and site acceptance cross-checking.
Core Conclusions
Construction joints shall be located where structural shear is small and construction is convenient.
I. Horizontal construction joints (GB 50666-2011 cl. 8.6.2)
- Column and wall construction joints may be set at the top surface of foundations or floor structures: the distance from the column joint to the structural top surface should be 0-100mm; for walls 0-300mm;
- Column and wall joints may also be set at the bottom surface of floor structures, 0-50mm from the structural bottom face; where there is a beam haunch under the slab, the joint may be 0-20mm below the haunch;
- Tall columns, walls and beams, and thick foundations may have a horizontal joint at mid-height per construction needs; where the joint changes the stress state and rebar adjustment is needed, the designer shall confirm;
- Horizontal joints at special locations require designer confirmation. Commentary points: floor structure types include "beams with slab", "beams without slab" (joint at beam top) and "slab without beams" (joint at slab top); the floor structure bottom face means the bottom of beams, slabs and flat-slab column capitals — where bottom-bent anchorage bars make 0-50mm impractical, the joint is usually placed at the bottom of the bent bars, subject to cl. 8.6.2 item 4 (designer confirmation); tall columns, walls, beams and thick foundation slabs that are hard to cast at once may be jointed, with construction-load checks for staged pouring and designer confirmation for any rebar adjustment.
II. Vertical construction joints and post-cast strips (GB 50666-2011 cl. 8.6.3)
- Slabs with primary and secondary beams: joints within the middle 1/3 of the secondary beam span;
- One-way slabs: joints at any position parallel to the span direction;
- Stair flights: joints preferably within the end 1/3 of the flight span;
- Walls: joints preferably within the middle 1/3 of the door-opening lintel span, or at the intersections of longitudinal and transverse walls;
- Post-cast strip locations shall satisfy the design;
- Vertical joints at special locations require designer confirmation. Commentary points: large-area, large-volume members hard to cast at once may have vertical joints; joints at technically demanding locations — super-long structure segment joints, foundation slab zoning joints, between core walls and slabs, between mega-columns and slabs — all require designer confirmation.
III. Beijing local practice (DB11/T 1832.3-2021 cl. 23.4.4, for Beijing projects)
- Column horizontal joints about 5mm above the soffit of the top slab;
- Beam and slab joints within the middle 1/3 of the span;
- For stairs without shear walls on both sides of the frame, joints preferably in the middle 1/3 of the flight above the resting platform, 3-4 steps up;
- Joint treatment: horizontal joints — remove the weak layer to expose aggregate; vertical joints — remove loose stone and debris to expose dense concrete; joints shall be washed clean and wetted with water before concreting; horizontal joints shall receive a cement mortar of the same composition as the concrete slurry, with a regletering (grout bedding) layer not thicker than 30mm.
Applicable Boundaries
- Applies to cast-in-place concrete structural works (frame, shear wall and other general members); the horizontal provisions target columns, walls, beams and thick foundations, the vertical ones slabs, stairs, walls etc.
- GB 50666-2011 is a national standard; DB11/T 1832.3-2021 is a Beijing local standard directly applicable only to Beijing projects; elsewhere follow the national code and local standards.
- Joints at special locations, and rebar adjustments caused by jointing, require designer confirmation; post-cast strip positions follow the design. This card does not replace design documents; specific works follow the design-confirmed construction scheme.
- The Beijing practice "column joint about 5mm above the top-slab soffit" does not contradict the national "0-100mm": 5mm lies within the national range and is a more detailed practical value.
Further Reading
- GB 50666-2011 cl. 8.6.2 (horizontal joint locations) and cl. 8.6.3 (vertical joints and post-cast strips), in Chapter 8 "cast-in-place structural works", with commentary (definition of floor-structure bottom face, effect of bottom-bent anchorage bars, delineation of special locations).
- DB11/T 1832.3-2021 cl. 23.4.4 (concrete construction of frame structures — joint placement and treatment), directly citable for Beijing projects, including the <=30mm bedding layer practice.
- Extensions: other joint-related provisions of section 8.6 of the same code; post-cast strip concreting time and temperature requirements; comparable clauses of other provinces' work procedures may be cross-checked with the national code.