Daily / per-shift pre-weld test for stud (shear-connector) welding in steel structures: trial-welded studs + 30-degree bend check (GB 50755-2012 / DB11/T 1832.5-2023 / T/CSCS 016-2021)
Before formal stud welding each day (shift), a pre-weld test is mandatory: GB 50755-2012 Clause 6.4.14 requires trial-welding at least 3 studs before each shift's welding, checked (complete fusion, full perimeter weld, no cracks in the heat-affected zone after a 30-degree bend) before formal welding; DB11/T 1832.5-2023 Clause 8.4.3 requires trial-welding 2 specimens before each day's formal welding, passing the 30-degree bend check; T/CSCS 016-2021 Clause 8.7.12 refines this: trial-weld 3 studs on specimens of the same base-metal category and similar thickness, re-weld on failure, and re-qualify the welding procedure if 2 attempts still fail.
Applicable Codes
- GB 50755-2012 钢结构工程施工规范 第6.4.14条
- DB11/T 1832.5-2023 建筑工程施工工艺规程 第5部分:钢结构工程 第8.4.3条
- T/CSCS 016-2021 钢结构制造技术标准 第8.7.12条
- GB 50205-2020 钢结构工程施工质量验收标准 第4.6.4条
- GB/T 10433 电弧螺柱焊用圆柱头焊钉
Topic Positioning
This card covers the "pre-weld test" (trial welding) required before formal daily or per-shift stud welding (welded studs / shear connector welding) in steel structures: number of trial-welded studs, check methods, and pass criteria, across three calibers - national standard, Beijing local standard, and association standard.
Core Conclusions
A pre-weld test (trial welding) is mandatory before formal welding each day / shift, and formal welding may start only after it passes. The three standards: 1. GB 50755-2012 "Code for construction of steel structures" Clause 6.4.14 (nationwide)
Before each shift's welding, at least 3 studs shall be trial-welded and checked as acceptable before formal welding. The trial welds serve to adjust welding parameters, so the checks are strict: complete fusion, full weld around the perimeter, and no cracks in the heat-affected zone on a 30-degree bend of the stud.
2. DB11/T 1832.5-2023 "Construction work procedure specifications for building works, Part 5: steel structure works" Clause 8.4.3 (for construction in Beijing)
A pre-weld test shall be carried out before formal welding each day: trial-weld 2 specimens and pass the 30-degree bend check before formal welding.
3. T/CSCS 016-2021 "Technical standard for steel structure fabrication" Clause 8.7.12 (association standard, further detail)
Before each shift's welding, 3 studs shall be trial-welded per the WPS parameters on specimens of the same base-metal category and similar thickness, and checked for weld appearance and by bending. On failure, re-do the trial welding as above; if 2 attempts still fail, find the cause and re-qualify the welding procedure. Surfaces of members receiving welded studs should not be coated; after welding, all ceramic ferrules and slag shall be removed. With drawn-arc stud welding, trial welding on a test plate approximating production conditions mainly verifies the parameter settings.
Field execution points: timing = before each day's / shift's formal welding; quantity = at least 3 studs (national), 2 specimens (Beijing local), 3 studs (association); condition = specimens of the same base-metal category and similar thickness; checks = weld appearance + complete fusion, full perimeter weld, no visible cracks in weld or HAZ after a 30-degree bend; purpose = adjust and confirm welding parameters.
Applicable Boundaries
- This covers the daily / per-shift routine trial weld (30-degree bend check) to confirm the day's parameters; it does not replace the welding procedure qualification required before first-time welding (which includes static tension, repeated bending, 90-degree bending and stricter tests; first use of new materials, new processes, or through-welding requires qualification first - see DB11/T 1832.5-2023 Clause 8.3.3 and the re-qualification conditions of GB 50661-2011 Section 6.3).
- Distinct from incoming material retest: GB 50205-2020 Clause 4.6.4 requires incoming retest of stud mechanical and welding properties per GB/T 10433 (one set per lot: >= 5 tension + 5 bend tests) - an entry inspection that accompanies, but never substitutes for, the daily trial weld.
- With three coexisting standards: nationwide projects follow GB 50755-2012; Beijing construction additionally follows DB11/T 1832.5-2023; where T/CSCS 016-2021 is adopted, follow its detail. Where trial counts differ (3 vs 2), apply the stricter per the project's governing standard.
Further Reading
- GB 50755-2012 "Code for construction of steel structures" Clause 6.4.14 (stud-welding pre-weld test).
- DB11/T 1832.5-2023 "Construction work procedure specifications for building works, Part 5: steel structure works" Clause 8.4.3 (pre-weld test), Clause 8.3.3 (first-time procedure qualification).
- T/CSCS 016-2021 "Technical standard for steel structure fabrication" Clause 8.7.12 (stud trial welding, coating restriction, ferrule and slag removal).
- Companions: GB 50661-2011 "Code for welding of steel structures" Section 6.3 (re-qualification conditions for stud welding among the seven processes); GB 50205-2020 Clause 4.6.4 with GB/T 10433 (incoming stud retest).
Keywords
- 栓钉焊接
- 焊前试验
- 试焊
- 弯曲30°
- GB 50755
- DB11 T 1832.5
- T CSCS 016
- 焊钉