A three-tier progressive test for judging whether a planned duration is manifestly unreasonable: compression red lines, procedural requirements, and technical feasibility

Judge a planned duration with a three-tier progressive test: ① quantitative red line — compression ratio = (quota duration − planned duration) ÷ quota duration; tender compression ≤20% is ordinary acceleration (GB 50500-2013, Clause 9.11.1), above 20% the tender documents must state the acceleration cost; 20%–30% compression requires expert review (Beijing caps at 30%, Shandong requires technical review), and >30% is basically directly manifestly unreasonable; ② procedural requirements — the tenderer shall compute the duration rationally from the duration quota, bidders shall verify feasibility and raise written clarifications, and the schedule requires employer/supervisor approval with no arbitrary compression during construction; ③ technical feasibility — back-check with D=Q/(R×S) per process whether the resource input on the compressed critical path is realistically sustainable.

Applicable Codes

  • GB/T 50875-2013 工程造价术语标准
  • GB 50500-2013 建设工程工程量清单计价规范
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB 55032-2022 建筑与市政工程施工质量控制通用规范
  • DB11/T 382-2017 建设工程监理规程
  • DB37/T 5164-2020 建筑施工现场管理标准
  • DBJ/T 15-115-2016 广东省建设工程交易规范
  • JGJ/T 121-2015 工程网络计划技术规程
  • GB/T 51262-2017 建设工程造价鉴定规范
  • 建设工程质量管理条例(国务院令第279号)

Topic Positioning

A three-tier progressive framework for judging whether a tendered/contracted planned duration is "manifestly unreasonable": first compare compression against red lines, then check procedural requirements, finally verify technical feasibility. For tender-duration review, bid-duration feasibility checks, duration disputes, and cost expert determination.

Core Conclusions

The baseline is the duration quota (GB/T 50875-2013, Clause 2.3.13); the contract duration in principle follows the duration quota, and special works without quotas are negotiated by the parties (State Council document 〔1983〕122, Article 9). Compression ratio = (quota duration − planned duration) ÷ quota duration:

  • ≤20%: ordinary acceleration, with a matched acceleration-cost arrangement — still in the normal band;
  • 20%–30%: touches the red line — expert review + explicit acceleration measures/costs required. In tendering, exceeding 20% requires the tender documents to state the added acceleration cost (GB 50500-2013, Clause 9.11.1; Guangdong requires tender duration ≥80% of the standard duration); Beijing caps construction compression at 30% with expert review (DB11/T 382-2017, Clause 5.1.1); Shandong requires review by engineering experts (DB37/T 5164-2020, Clause 9.4.1); membrane structures and similar special works require review beyond 10% (T/CSCS 035-2023);
  • 30%: exceeds most regulatory caps and can basically be found directly manifestly unreasonable. Procedural requirements: the tenderer shall compute the duration rationally from the duration quota and set the maximum bid limit price accordingly (GB/T 50500-2024, Clause 5.2.2); bidders shall re-check feasibility of the planned duration, raise objections in writing for clarification, and the bid duration must not exceed the planned duration (Clause 6.1.4); schedules are executed after employer/supervisor approval, with no arbitrary compression during construction (GB 55032-2022, Clause 2.0.6, mandatory). Technical feasibility: back-check resources per process with D = Q/(R×S) (JGJ/T 121-2015, Clause 3.2.13) and test whether the resource input on the compressed critical path is realistic.

Applicable Boundaries

Applies to works covered by duration quotas; special works without quotas follow the contract (GB/T 51262-2017, Clause 5.7.2 duration-dispute determination: agreed terms govern; absent agreement, department rules or the duration quota). The 20%/30%/10% figures are local or industry thresholds — apply the current rules of the project location first; within the red line but procedurally deficient, or technically infeasible, the duration is still unreasonable. Acceleration-cost calculation and resource back-calculation are on companion cards and not repeated here.

Further Reading

GB/T 50875-2013, Clause 2.3.13 (duration quota); GB 50500-2013, Clause 9.11.1 (20% tender compression red line); GB/T 50500-2024, Clauses 5.2.2, 6.1.4, 8.11.17; GB 55032-2022, Clause 2.0.6; DB11/T 382-2017, Clause 5.1.1; DB37/T 5164-2020, Clause 9.4.1; DBJ/T 15-115-2016, Clause 4.1.3; T/CSCS 035-2023, Appendix A.8.4; Regulations on Quality Management of Construction Works, Article 10; JGJ/T 121-2015, Clauses 3.2.13 and 6.3.2; GB/T 51262-2017, Clause 5.7.2.

Keywords

  • 计划工期
  • 定额工期
  • 压缩工期
  • 合理工期
  • 工期不合理
  • 赶工费
  • expert panel review
  • 工期红线