Organization and preconditions of construction completion acceptance — Regulation on Quality Management of Construction Works art. 16 (organized by the construction/employer unit; five conditions; delivery only after passing)

Regulation on Quality Management of Construction Works (State Council Decree No. 714, 2019 revision) art. 16: completion acceptance is organized by the construction (employer) unit — upon receiving the completion report it organizes the design, construction and supervision units to conduct it — and requires five conditions: (1) all design and contractual contents completed; (2) complete technical archives and construction management records; (3) site entry test reports for main building materials, components and equipment; (4) quality-certifying documents signed separately by the survey, design, construction and supervision units; (5) a project warranty letter signed by the construction unit. Works may be delivered for use only after passing acceptance.

Applicable Codes

  • 《建设工程质量管理条例》(2019修订,国务院令第714号)第七条、第十条、第二十五条、第七十八条

Topic Positioning

The core rules of art. 16 of the Regulation on Quality Management of Construction Works (State Council Decree No. 714, 2019 revision): who organizes completion acceptance, what conditions passing requires, and the mandatory "delivery only after passing". For compliance judgment of completion acceptance across construction projects.

Core Conclusions

Art. 16, original: "Upon receiving the completion report of a construction project, the construction (employer) unit shall organize the design, construction, engineering supervision and other relevant units to conduct completion acceptance."

Completion acceptance shall possess the following conditions (five, original): (1) completion of all contents of the project design and the contract; (2) complete technical archives and construction management records; (3) site-entry test reports for the main building materials, components and equipment used in the project; (4) quality-certifying documents signed separately by the survey, design, construction and supervision units; (5) a project warranty letter signed by the construction unit.

"A construction project may be delivered for use only after passing acceptance."

Key points:

  • The organizer is the construction (employer) unit (not the contractor or supervisor); participants are the design, construction and supervision units; the supporting rule Measures for Completion Acceptance of Housing and Municipal Infrastructure Projects (Jian Zhi [2013] No. 171) art. 4 likewise states that acceptance is organized and implemented by the construction unit.
  • All five conditions are indispensable: item 2 is completeness of archives and management records; item 3 is the entry-test evidence for materials/components/equipment (missing records block acceptance level by level — see cited card); item 4 requires the four types of units to sign separately; item 5 requires the contractor's warranty letter.
  • "Delivery only after passing" is a mandatory precondition: no delivery without acceptance or with a failed acceptance; the consequences of the employer using un-accepted works (quality deemed accepted, transfer of liability etc.) are in the cited cards.
  • After passing, per art. 49, the construction unit shall, within 15 days of acceptance, file the acceptance report and the approvals or permits of planning, fire and environmental authorities with the construction administrative department.

Applicable Boundaries

  • Applies to completion-acceptance compliance of building and civil engineering projects (the Regulation covers civil works too).
  • Art. 16 governs organization and conditions (preconditions of the pass standard); specific procedures (pre-acceptance, special acceptances, panel composition, conclusions) follow Jian Zhi [2013] No. 171 and the GB 50300 acceptance series.
  • Warranty periods (art. 40) and final account pricing are not covered (see cited cards).
  • The 2019 revision keeps art. 16 identical to the 2017 revision.

Further Reading

  • Source: Regulation on Quality Management of Construction Works (Decree No. 714, 2019 revision), art. 16; extensions art. 49 (filing) and art. 40 (minimum warranty periods).
  • Procedure details: MOHURD Measures (Jian Zhi [2013] No. 171); work-section quality acceptance per GB 50300-2013 and GB 55032-2022.
  • Related cards: employer's use of un-accepted works (quality deemed accepted, completion date, warranty not exempted); failed acceptance effects on payment and settlement; material-record gaps blocking acceptance.