Administrative penalties and civil consequences of contract transfer (re-letting of the whole works) and unlawful subcontracting: fine bases and ranges (works contractors 0.5%~1% of the works contract price; survey and design 25%~50% of the survey and design fees; supervision fees 25%~50%), confiscation of illegal gains, business suspension, qualification downgrade or revocation, joint and several liability for quality losses, and the layering of contract invalidity with compensation by reference to the contract price
Administrative penalty rules for contract transfer and unlawful subcontracting: Construction Law Article 67 orders rectification, confiscation of illegal gains and a fine, and may order business suspension or a lower qualification grade, with revocation of the qualification certificate in serious cases, and imposes joint and several liability with the unit that accepted the transfer or subcontract for losses caused by the transferred or unlawfully subcontracted works failing to meet the prescribed quality standards; the fine ranges follow Article 62 of the Regulations on Quality Management of Construction Projects: a survey or design unit is fined not less than 25% and not more than 50% of the survey or design fees agreed in the contract; a works contractor is fined not less than 0.5% and not more than 1% of the works contract price; a supervision unit transferring its supervision business is fined not less than 25% and not more than 50% of the agreed supervision fee. Administrative penalties do not displace the civil consequences of contract invalidity (Fa Shi [2020] No. 25 Article 1(2)) and compensation by reference to the contract price (Civil Code Article 793).
Applicable Codes
- 《中华人民共和国建筑法》(2019修正)第二十八条、第二十九条、第六十七条
- 《建设工程质量管理条例》(国务院令第714号,2019修订)第七十八条、第六十二条
- 《中华人民共和国民法典》第八百零六条
- 《中华人民共和国民法典》第七百九十三条
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第一条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第六条、第二十三条
Scope
After a contractor transfers the contract or unlawfully subcontracts the works, what administrative penalties follow: what types of penalty, on what base the fine is calculated, and in what range; and how civil joint and several liability for quality losses and the consequences for contract validity layer on top.
Key conclusions
1. Penalty rule in the superior law (Construction Law Article 67, full text). 'Where a contractor transfers the works it contracted, or subcontracts in violation of this Law, it shall be ordered to rectify, its illegal gains shall be confiscated and it shall be fined; it may be ordered to suspend business or to have its qualification grade lowered; where the circumstances are serious, its qualification certificate shall be revoked. Where a contractor commits an act in the preceding paragraph, it shall bear joint and several liability with the unit that accepted the transfer or the subcontract for losses caused by the transferred works or the unlawfully subcontracted works failing to meet the prescribed quality standards.'
2. Fine base and range (Regulations on Quality Management of Construction Projects, Article 62, full text). 'Where a contractor, in violation of these Regulations, transfers the works it contracted or subcontracts unlawfully, it shall be ordered to rectify, its illegal gains shall be confiscated; a survey or design unit shall be fined not less than 25% and not more than 50% of the survey or design fees agreed in the contract; a works contractor shall be fined not less than 0.5% and not more than 1% of the works contract price; it may be ordered to suspend business or to have its qualification grade lowered; where the circumstances are serious, the qualification certificate shall be revoked. Where a supervision unit transfers its supervision business, it shall be ordered to rectify, its illegal gains shall be confiscated, and it shall be fined not less than 25% and not more than 50% of the supervision fee agreed in the contract; it may be ordered to suspend business or to have its qualification grade lowered; where the circumstances are serious, the qualification certificate shall be revoked.'
That is: the works contractor basis is 0.5%~1% of the works contract price; the survey and design basis is 25%~50% of the agreed survey and design fees; the supervision transfer basis is 25%~50% of the agreed supervision fee; all three are combined with confiscation of illegal gains, and may be accompanied by ordered business suspension or a lower qualification grade, with revocation of the qualification certificate in serious cases.
3. The conduct boundaries of the penalised parties (basis of determination). Article 78 of the Regulations: contract transfer means 'the act of a contractor which, after contracting a construction project, fails to perform its contractual responsibilities and obligations and transfers the whole of the construction project it contracted to another party, or divides the whole of the construction project it contracted into parts and transfers them to other units in the name of subcontracting'; the four situations of unlawful subcontracting are: the main contractor subcontracts to a unit without the corresponding qualifications; it awards part of the works to another unit without agreement in the main contract and without recognition by the employer; the works main contractor subcontracts the construction of the main structure to another unit; a subcontractor further subcontracts the works it contracted. Construction Law Articles 28 and 29 impose parallel prohibitions: transfer of the whole works and disguised transfer in the name of subcontracting are prohibited; subcontracting must go to units with corresponding qualifications and, apart from agreement in the main contract, requires recognition by the employer; the main structure must be completed by the contractor itself; further subcontracting is prohibited; the main contractor and the subcontractor bear joint and several liability to the employer for the subcontracted works.
4. Administrative and civil liability run in parallel. Administrative penalties do not displace civil consequences: (1) contract validity: construction contracts signed by a contractor with others for transferred or unlawfully subcontracted works are invalid under Fa Shi [2020] No. 25 Article 1(2), applying Civil Code Article 153(1) and Articles 791(2) and 791(3); (2) price settlement: where the works pass acceptance, the contractor may be compensated by reference to the agreed works price (Civil Code Article 793(1)); (3) claim paths: where the unit or individual that accepted the transfer or the unlawful subcontract claims from the contractor compensation by reference to the transfer or subcontract, the people's court supports the claim according to law, but a claim against the employer, with whom it has no contractual relationship, for compensation by reference to the contract price or for damages is not supported (Fa Shi [2026] No. 12 Article 6); (4) quality liability: the joint and several liability under Construction Law Article 67(2) covers only 'losses caused by the transferred works or the unlawfully subcontracted works failing to meet the prescribed quality standards', borne jointly with the unit that accepted the transfer or the subcontract.
Application boundaries
- The fine calculation base must be distinguished by party: works contractors calculate on the works contract price; survey and design units on the agreed survey and design fees; supervision units on the supervision fee; the bases may not be mixed.
- Article 62 of the Regulations targets contractors (survey, design, works) and supervision units transferring supervision business; fragmentation of the award by the employer falls under other provisions and cannot be handled under this article.
- The fine ranges are ranges fixed by administrative regulation; the specific amount is at the enforcement authority's discretion within the range and cannot be agreed by the contract parties themselves.
- Administrative penalties, contract invalidity, compensation by reference to the contract price and joint and several liability rest on different bases of claim; they can arise together and do not substitute for one another.
- Application point of Fa Shi [2026] No. 12: it takes effect on 30 June 2026 and applies to first-instance construction contract dispute cases newly accepted by the people's courts after that date (Article 23).
Further reading
Construction Law (2019 revision) Articles 28, 29, 67; Regulations on Quality Management of Construction Projects (2019 revision, State Council Order No. 714) Articles 78, 62; Civil Code Articles 806, 793; Fa Shi [2020] No. 25 Article 1; Fa Shi [2026] No. 12 Articles 6, 23.