Statutory minimum warranty periods for building works: durations per part, commencement, and agreement rules (Regulations Article 40; Ministry of Construction Order No. 80)
Nationwide statutory minimum warranty periods: foundations and the main structure — the reasonable service life specified in the design documents; roof waterproofing and seepage prevention for bathrooms, rooms, and exterior walls with waterproof requirements — 5 years; heating and cooling systems — 2 heating/2 cooling seasons; electrical wiring, water supply/drainage pipes, equipment installation, and decoration — 2 years; other items by agreement of the parties. Warranty periods run from passing completion acceptance; Beijing housing runs from first delivery. Contractual periods may not fall below the statutory minima; repaired portions restart their warranty period.
Applicable Codes
- 《建设工程质量管理条例》第四十条(国务院令第714号,2019年修订)
- 《房屋建筑工程质量保修办法》第七、八条(建设部令第80号)
- DB11/T 641-2018 · Specification for Quality Warranty of Housing Works (Beijing) 第5.0.14条
- 《北京市建设工程质量条例》第54条
Topic Positioning
This card gives the statutory minimum warranty periods per building part (including infrastructure works), the commencement rules, and the agreement rules, per Article 40 of the "Quality Management Regulations for Construction Projects" (State Council Decree No. 714, 2019 revision), Ministry of Construction Order No. 80 "Measures for Quality Warranty of Housing Construction Projects", Articles 7-8, and the Beijing housing special rule (DB11/T 641-2018, Clause 5.0.14).
Core Conclusions
Under normal use, minimum warranty periods (statutory floors — contractual periods may not fall below): (1) Infrastructure works and the foundation and main structure of buildings — the reasonable service life of the project specified in the design documents (not a fixed number; per design — housing typically designed for 50 years); (2) Roof waterproofing works and seepage prevention for bathrooms, rooms, and exterior walls with waterproof requirements — 5 years — the statutory floor for roofs being 5 years; (3) Heating and cooling systems — 2 heating periods and 2 cooling periods — counted by "seasons", not calendar years: heating covered for 2 full heating seasons, cooling for 2 full cooling seasons; (4) Electrical wiring, water supply and drainage pipes, equipment installation, and decoration works — 2 years. Other items' periods are agreed by the letting and contracting parties. Order No. 80, Article 7 lists "equipment installation" and "decoration works" separately (electrical wiring, water pipes, equipment installation — 2 years; decoration — 2 years), matching the Regulations. Commencement:
- National rule: warranty periods run from the date of passing completion acceptance (Regulations Article 40(2); Order No. 80, Article 8, same intent).
- Beijing housing special rule: quality warranty periods run from the owner's first delivery of the housing; for common parts, from delivery of the first dwelling of that unit works (DB11/T 641-2018, Clause 5.0.14, with Beijing Quality Regulations Article 54: the owner's warranty period to titleholders runs from delivery) — for purchasers, the actual delivery date, not the acceptance date.
- Within the warranty period, repaired portions restart their period from acceptance by the titleholder and relevant units (DB11/T 641-2018, Clause 5.0.14). Practice: the Regulations set only floors — warranty letters (issued by the contractor at completion) and contract clauses below the statutory floors are executed at the statutory minima; the "reasonable service life" of foundations and the main structure must be checked in the design documents.
Applicable Boundaries
- A nationwide statutory floor for housing construction; Regulations Article 40 covers more (including infrastructure works).
- Warranty period and defect liability period (commonly agreed at 1 year from passing completion acceptance, running parallel to the warranty period) are distinct concepts; defect liability rules are outside this card.
- Beijing's "from first delivery" is a local special rule limited to Beijing housing; elsewhere, from passing completion acceptance absent special rules.
- Warranty obligations are independent of "the owner's unauthorized use of unaccepted works": unauthorized use does not exempt warranty (see cited card 222220c2).
Further Reading
- "Quality Management Regulations for Construction Projects", Article 40: State Council Decree No. 714 (2019 revision, in force); identical text in the 2000 Decree No. 279 and 2017 revision (Decree No. 687).
- Ministry of Construction Order No. 80 "Measures for Quality Warranty of Housing Construction Projects", Articles 7 and 8.
- DB11/T 641-2018 "Specification for quality warranty of housing projects", Clause 5.0.14 (Beijing local standard); "Beijing Regulations on Construction Project Quality", Article 54.
- Extension: GB 55032-2022 "General code for construction quality control of buildings and municipal works", Chapter 5 "quality warranty and maintenance" — fully mandatory; current standards inconsistent with it yield to it.
Keywords
- 最低保修期
- 保修期限
- 房屋建筑工程质量保修办法
- 建设工程质量管理条例第四十条
- 屋面防水保修5年
- 供热供冷系统保修
- 保修期起算
- 首次交付