Joint and several liability of an EPC consortium (design firm + contractor) to the employer: constitutive requirements, internal division-of-work agreements unenforceable against the employer, and the distinction from subcontractor joint liability and from non-liability under parallel awarding
Where a design firm and a contractor form a consortium, tender, win and jointly sign the same EPC contract with the employer, they bear statutory joint and several liability to the employer for the whole EPC project, not limited by the internal division of work in the consortium agreement: under paragraph 3 of Article 31 of the Tendering and Bidding Law, 'where a consortium wins the tender, all consortium members shall jointly sign the contract with the tenderer and bear joint and several liability to the tenderer for the awarded project'; in the building and municipal sector, paragraph 2 of Article 10 of the Measures for the Administration of EPC of Building and Municipal Infrastructure Projects (Jian Shi Gui [2019] No. 12) directly provides that 'all consortium members shall jointly sign the EPC contract with the employer and bear joint and several liability for the EPC project'. The preconditions of joint liability are 'valid formation of the consortium + joint tendering and award + joint contracting'; separate contracts (parallel awarding) attract no joint liability, and where one party is the other's subcontractor, the subcontractor joint liability under paragraph 2 of Article 791 of the Civil Code applies (limited to the work results completed by the third party).
Applicable Codes
- 《中华人民共和国招标投标法》(主席令第86号,2017修正)第三十一条
- 《中华人民共和国招标投标法实施条例》(国务院令第709号,2019修订)第三十七条
- 《房屋建筑和市政基础设施项目工程总承包管理办法》(建市规〔2019〕12号)第六条至第十六条
- 《中华人民共和国民法典》第一百七十八条、第七百九十一条
- 《中华人民共和国建筑法》(2019修正)第二十七条、第五十五条
- 《建设工程质量管理条例》(国务院令第714号,2019修订)第二十七条
- 《房屋建筑和市政基础设施工程施工分包管理办法》(建设部令第124号)第十六条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第七条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第三条、第四条、第六条、第七条、第二十三条
Topic positioning
When an engineering procurement and construction (EPC) project is undertaken by a consortium of a design firm and a contractor, whether the two bear joint and several liability to the employer, how far that liability reaches, whether internal arrangements can be set up against the employer, and which scenarios fall outside consortium joint liability into subcontractor joint liability or into each party standing alone. For bid planning, EPC contract signing, defect recourse and the choice of parties in litigation.
Core conclusions
I. Affirmative scenario: statutory consortium joint liability, covering the whole awarded project. Article 31 of the Tendering and Bidding Law, text: 'Two or more legal persons or other organisations may form a consortium and tender jointly as one tenderer. Each member of the consortium must possess the corresponding capability to undertake the tendered project; where the relevant provisions of the State or the tender documents prescribe qualification requirements for tenderers, each member must possess the prescribed corresponding qualifications. A consortium composed of units of the same specialty is graded by the unit with the lower qualification grade. The members shall sign a joint tender agreement specifying the work and responsibilities each intends to undertake, and submit it together with the bid. Where a consortium wins the tender, all members shall jointly sign the contract with the tenderer and bear joint and several liability to the tenderer for the awarded project. The tenderer may not force tenderers to form a consortium to tender jointly, nor restrict competition among tenderers.'
Article 10 of the Measures for the Administration of EPC of Building and Municipal Infrastructure Projects (Jian Shi Gui [2019] No. 12): 'The EPC contractor shall hold both design and construction qualifications matching the scale of the project, or be a consortium formed by a design firm and a contractor each holding the corresponding qualifications. The EPC contractor shall have a corresponding project management system and project management capability, financial and risk-bearing capacity, and design, construction or EPC track records similar to the works being awarded. Where a design firm and a contractor form a consortium, the lead member shall be determined reasonably according to the characteristics and complexity of the project, and the consortium agreement shall specify the responsibilities and rights of the member units. All consortium members shall jointly sign the EPC contract with the employer and bear joint and several liability for the EPC project.'
Article 27 of the Construction Law (2019 revision): 'Large building projects or structurally complex building projects may be jointly contracted by two or more contractors. The parties to joint contracting bear joint and several liability for the performance of the contract. Where units of different qualification grades contract jointly, the works shall be undertaken within the business scope permitted to the unit with the lower qualification grade.'
II. Internal division-of-work agreements have no external effect. Article 178 of the Civil Code: 'Where two or more persons bear joint and several liability in accordance with law, the right holder may request one or all of the jointly liable persons to bear liability. The shares of the jointly liable persons are determined according to the extent of their respective responsibility; where the extent is difficult to determine, they bear the liability equally. A jointly liable person who has actually borne liability beyond its own share has the right to seek contribution from the other jointly liable persons. Joint and several liability arises from provisions of law or from agreement by the parties.' Accordingly, a consortium clause that 'the design side is responsible only for design, the construction side only for construction, with no joint liability between them' is valid only within the consortium; the employer may still claim full liability from any member, and a member that has performed beyond its share may seek contribution from the others (by extent of responsibility, or equally where indeterminable).
III. Stacked joint liability on the quality dimension. Article 55 of the Construction Law: 'Where a building project is under general contracting, the quality of the works is the responsibility of the general contractor; where the general contractor subcontracts the building project to other units, it shall bear joint and several liability with the subcontracting units for the quality of the subcontracted works. The subcontracting units shall accept the quality management of the general contractor.' Article 27 of the Regulation on Quality Management of Construction Projects: 'Where the general contractor subcontracts the construction project to other units in accordance with law, the subcontracting unit shall be responsible to the general contractor for the quality of its subcontracted works under the subcontract, and the general contractor and the subcontracting unit bear joint and several liability for the quality of the subcontracted works.'
IV. Negative scenarios and alternative routes.
- Where the design firm and the contractor separately sign a design contract and a construction contract with the employer (parallel awarding), with no consortium and no subcontract relationship: each is liable only under its own contract, with no joint liability - paragraph 3 of Article 178 of the Civil Code requires joint liability to arise 'from provisions of law or from agreement by the parties', and neither basis exists here. Paragraph 1 of Article 791 of the Civil Code additionally prohibits the employer from splitting works that should be completed by one contractor into parts awarded to several contractors.
- Where one party, after contracting, subcontracts part of the works to the other with the employer's consent: this is subcontractor joint liability, not consortium joint liability, and its scope is limited to the work results completed by the third party. Paragraph 2 of Article 791 of the Civil Code: 'The general contractor or the survey, design or construction contractor may, with the consent of the employer, entrust part of the work it has contracted to a third party for completion. The third party bears joint and several liability to the employer, with the general contractor or the survey, design or construction contractor, for the work results it completes.' With Article 16 of the Measures for the Administration of Construction Subcontracting of Building and Municipal Infrastructure Projects (Ministry of Construction Order No. 124): 'The subcontract-letting unit and the subcontract-taking unit bear joint and several liability to the employer for the subcontracted works.'
- Qualification borrowing (gui kao affiliation): Article 7 of Fa Shi [2020] No. 25: 'Where a unit or individual lacking qualification borrows the name of a qualified construction enterprise to sign a construction contract, and the employer requests the qualification-lending party and the borrowing party to bear joint and several compensation liability for losses caused by the lending of the qualification, such as substandard quality of the works, the people's court shall support the request.' This is joint and several compensation for lending qualifications, different from consortium joint liability both in basis and in scope.
- The consortium itself or the bid is void: the tenderer must state in the prequalification notice, the tender notice or the invitation to tender whether consortium tendering is accepted; adding, removing or changing members after prequalification invalidates the bid; and where members of a consortium tender separately in their own name or join other consortia in the same tender, the relevant bids are void (Article 37 of the Implementation Regulation of the Tendering and Bidding Law).
V. The boundary between the old and new judicial interpretations. Fa Shi [2026] No. 12 (Interpretation II), Article 23: 'This Interpretation takes effect on 30 June 2026. First-instance construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect shall apply this Interpretation. Where judicial interpretations previously issued by the Supreme People's Court are inconsistent with this Interpretation after it takes effect, this Interpretation prevails.' That is: first-instance cases newly accepted after 30 June 2026 apply the new interpretation; cases accepted earlier are not retrocovered.
Applicable boundaries
- Three preconditions must hold concurrently for consortium joint liability: the consortium is validly formed in accordance with law (joint tender agreement submitted), it tenders and wins in the consortium's name, and all members jointly sign the same EPC contract with the employer. Absent any one, the consortium joint liability rule does not apply.
- Article 10(2) of Jian Shi Gui [2019] No. 12 applies directly to building and municipal infrastructure projects; consortium joint liability for EPC in other sectors (highway, water conservancy, railway and the like) rests mainly on paragraph 3 of Article 31 of the Tendering and Bidding Law and on the rules of the competent sector authority, and clause numbers must not be transplanted.
- Consortium joint liability covers 'the awarded project as a whole', not apportioned by the members' division of work; subcontractor joint liability is limited to 'the work results completed by the third party'; the two must not be mixed.
- An agency-construction unit, a project management unit, a supervision unit, a cost consultancy or a tendering agency may not become the EPC contractor of the project; the units that compile, and the units that assess, the project proposal, feasibility study report and preliminary design documents of government-invested projects generally may not become the EPC contractor (Article 11 of Jian Shi Gui [2019] No. 12) - defects of entity eligibility raise separate contract validity issues, to be considered together with the liability finding.
- Interpretation II (Fa Shi [2026] No. 12) takes effect on 30 June 2026; first-instance cases accepted before that date are tried under the old rules; check the acceptance time before citing.
Further reading
- Consortium tendering rules: Article 31 of the Tendering and Bidding Law of the PRC; Article 37 of the Implementation Regulation (the tenderer must state whether consortium tendering is accepted; members may not be added, removed or changed after prequalification; double bidding is void).
- EPC awarding and implementation: Measures for the Administration of EPC of Building and Municipal Infrastructure Projects (Jian Shi Gui [2019] No. 12), Articles 6 to 16, most relevantly Article 6 (choice of implementation mode), Article 7 (approvals to be completed before award), Article 8 (tendering or direct award), Article 9 (content of tender documents), Article 10 (qualifications and consortium joint liability), Article 11 (exclusion for conflicts of interest), Article 15 (risk allocation), Article 16 (form of contract price).
- Contracting and subcontracting boundaries: Article 791 of the Civil Code; Articles 27 and 55 of the Construction Law (2019 revision); Article 27 of the Regulation on Quality Management of Construction Projects (State Council Decree No. 714, 2019 revision); Article 16 of the Measures for the Administration of Construction Subcontracting of Building and Municipal Infrastructure Projects (Ministry of Construction Order No. 124).
- General rules of joint liability and internal contribution: Article 178 of the Civil Code.
- Qualification-borrowing (gui kao) joint compensation and the old/new boundary: Article 7 of Fa Shi [2020] No. 25; Articles 3, 4, 6, 7 and 23 of Fa Shi [2026] No. 12 (Interpretation II).
Keywords
- EPC联合体
- 连带责任
- 招标投标法第三十一条
- 工程总承包管理办法第十条
- 设计单位与施工单位联合体
- 共同投标协议
- 分包连带责任
- 平行发包