Validity of a construction contract concluded by a contractor exceeding its qualification grade (or in the name of a grade below that required by the works): the exceeding-grade invalidity rule, the cure exception where the corresponding grade is obtained before completion, the consequences of reference-based compensation after invalidity, and the boundaries against qualification borrowing, contract transfer and unlawful subcontracting

A construction contract signed by a contractor that has not obtained a qualification or that exceeds its qualification grade is void under Article 153(1) of the Civil Code, Article 26 of the Construction Law and Article 1(1) of Fa Shi [2020] No. 25; but under Article 4 of that interpretation, where the contractor obtains the corresponding qualification grade before the completion of the works, the people's court will not support a party's request to handle the contract as void. Undertaking the works in the name of another's qualification (including a lower grade) is qualification borrowing, equally void (Article 3(1) of Fa Shi [2026] No. 12), and the before-completion cure does not apply to it. Where the contract is void but the works pass acceptance, compensation is made by reference to the contract (Article 793(1) of the Civil Code); 'by reference' covers the amount, the pricing method, the payment timing, the adjustment method and the settlement method (Article 11 of Fa Shi [2026] No. 12).

Applicable Codes

  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第一条、第四条、第七条、第二十四条、第四十三条
  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第三条、第四条、第六条、第七条、第十一条、第二十三条
  • 《中华人民共和国民法典》第一百五十三条、第七百九十一条、第七百九十三条
  • 《中华人民共和国建筑法》第二十六条
  • 《建设工程质量管理条例》(国务院令第714号,2019修订)第六十条
  • 建市规〔2019〕1号《建筑工程施工发包与承包违法行为认定查处管理办法》第七条至第十二条
  • https://www.court.gov.cn/fabu/xiangqing/504221.html

Scope and Positioning

This card answers the cluster of questions - where the contractor's qualification grade does not match the works (no qualification, exceeding its grade, or contracting in the name of a grade below the works' requirement or in another's name), is the construction contract valid, can the defect be cured, and how is it settled once void - and gives the demarcation against qualification borrowing, contract transfer and unlawful subcontracting.

Core Conclusions

1. Validity elements: void + cure exception

Normative chain of invalidity: Article 153(1) of the Civil Code ('A civil juristic act that violates a mandatory provision of a law or administrative regulation is void, unless that mandatory provision does not lead to the invalidity of the act.') -> Article 26 of the Construction Law ('A unit undertaking construction works shall hold a lawfully obtained qualification certificate and undertake works within the scope of business permitted by its qualification grade. Construction enterprises are prohibited from undertaking works beyond the scope of business permitted by their own qualification grade or from undertaking works in the name of any other construction enterprise in any form, and from allowing, in any form, any other unit or individual to use their qualification certificate or business licence to undertake works in their name.') -> Article 1 of Fa Shi [2020] No. 25:

A construction contract that has any of the following circumstances shall be held void under Article 153(1) of the Civil Code: (1) the contractor has not obtained a construction enterprise qualification or exceeds its qualification grade; (2) an actual builder without qualification contracts in the name of a qualified construction enterprise; (3) the construction works are subject to mandatory tendering but were not tendered, or the award is void. A construction contract signed by the contractor with another party as a result of transferring or unlawfully subcontracting the construction works shall be held void under Article 153(1) and Article 791(2) and (3) of the Civil Code.

Cure exception (the sole statutory exit): Article 4 of Fa Shi [2020] No. 25 -

Where a contractor signs a construction contract beyond the scope of business permitted by its qualification grade and obtains the corresponding qualification grade before the completion of the construction works, the people's court will not support a party's request to handle the contract as a void contract.

Elements table:

Scenario Validity Basis Key timing / condition
No construction enterprise qualification Void Article 1(1) of Fa Shi [2020] No. 25 Unqualified at signing and still so before completion
Exceeds qualification grade (own grade below the works' requirement) Void Same; Article 26(1) and (2) of the Construction Law Cure: where the corresponding grade is obtained before completion, the void-treatment request is not supported (Article 4)
Undertaking in another's name (low borrowing high, high borrowing low, or equal grades lending each other) Void (qualification borrowing) Article 1(2) of Fa Shi [2020] No. 25; Article 3(1) of Fa Shi [2026] No. 12; Article 10(2) of Jian Shi Gui [2019] No. 1 This is qualification lending, outside the cure of Article 4 (Article 4 targets only the exceeding-own-grade scenario itself)
Mandatory tendering skipped or void award Void Article 1(3) -
Contract transfer, unlawful subcontracting Void Article 1(2) + Article 791(2) and (3) of the Civil Code Occurs after contracting

Order of characterisation in practice: first fix the qualification class and grade the contractor actually held at signing and the qualification the works actually require, then look at the contracting party named in the contract / award documents - the characterisation must not rest solely on the qualification name appearing in the contract; on a mismatch (holding a high grade yet signing in the name of a low one, or borrowing another's low-grade name), apply the exceeding-grade rule or the qualification-borrowing rule according to the true qualification status and whose name was used.

2. Consequences of invalidity (reference-based compensation where quality passes)

  1. Article 793(1) of the Civil Code: 'Where a construction contract is void but the construction works have passed acceptance, the contractor may be compensated by reference to the agreed price provisions of the contract.'
  2. Paragraphs 2 and 3: where acceptance fails, and the works pass completion acceptance after rectification, the employer may claim the rectification costs from the contractor; where the works still fail after rectification, the contractor has no right to claim reference-based compensation; where the employer is at fault for the losses caused by the defects, it shall bear the corresponding liability.
  3. Scope of 'by reference' (Article 11 of Fa Shi [2026] No. 12): the phrase 'by reference to the agreed price provisions of the contract' in Article 793(1) of the Civil Code includes the agreed amount of the construction price, the pricing method, the payment timing, the adjustment method and the settlement method -> invalidity does not overturn the original pricing method, the discount rate or the payment milestones, nor does it trigger re-pricing under the quota norms.
  4. Several contracts, all void: refer to the one actually performed; where the actually performed contract is hard to identify, refer to the last one signed (Article 24 of Fa Shi [2020] No. 25).
  5. The payment relationship under qualification borrowing (Article 3 of Fa Shi [2026] No. 12): 'Where a construction enterprise lends its qualification or otherwise allows another to undertake works in its name, the people's court shall hold the contract lending the qualification or permitting the use of its name void. A claim by the construction enterprise for the agreed qualification lending fee or usage fee will not be supported.' 'Where the construction works are of acceptable quality, and the borrowing entity or individual claims payment of reference-based compensation from the construction enterprise by reference to its agreement with the construction enterprise on payment for the works, the people's court shall support the claim according to law.'
  6. The borrower claiming against the employer (Article 4 of Fa Shi [2026] No. 12): where the employer neither knew nor ought to have known of the qualification borrowing at contracting, and the borrower claims that the contract directly binds it and the employer for reference-based compensation, the claim is not supported; where the borrower proves that the employer knew or ought to have known at contracting, and claims reference-based compensation from the employer for the works it performed, the court shall notify the qualification-lending construction enterprise to participate as a third party, and shall, having regard to the employer's payment of the price and the borrower's performance, adjudge the employer to bear liability towards the borrower.
  7. A party accepting a transfer or unlawful subcontract has no direct claim against the employer (Article 6); the qualification borrower and the party accepting a transfer or unlawful subcontract may claim against the employer by subrogation under Article 535 of the Civil Code (Article 7).
  8. Joint compensation: Article 7 of Fa Shi [2020] No. 25 - where a unit or individual lacking qualification signs a contract in the name of a qualified construction enterprise, and the employer claims that the lender and the borrower bear joint compensation liability for losses from substandard quality of the works and other consequences of lending the qualification, the people's court shall support the claim.
  9. Administrative liability is not absorbed by civil invalidity: Article 60 of the Regulation on Quality Management of Construction Projects (State Council Order No. 714, 2019 revision) - a survey, design, construction or supervision unit undertaking works beyond its own qualification grade shall be ordered to stop the unlawful act ... the construction unit is fined 2% to 4% of the project contract price, may be ordered to suspend business for rectification or have its qualification grade lowered; in serious cases the qualification certificate is revoked; unlawful gains are confiscated; undertakings without a qualification certificate are outlawed and fined under the preceding paragraph. Obtaining the certificate by fraud and undertaking works with it leads to revocation of the certificate plus a fine.

3. Boundaries against qualification borrowing, contract transfer and unlawful subcontracting

Dimension Exceeding own grade Qualification borrowing (incl. high borrowing low) Contract transfer Unlawful subcontracting
Timing of the unlawful act At undertaking (bidding / contracting) Throughout the undertaking (joining the bid, signing the contract, handling construction formalities, performing) After contracting After contracting
In whose name contracted Own name The qualification-lending enterprise's name Own name (externally still the contractor) Own name
Who actually performs Itself (under-qualified) The borrower (unqualified or grade-mismatched) The transferee takes all the works, or all of it after piecing-out The subcontractor takes part of the works
Consideration pattern None (performs for itself, earns for itself) Qualification lending / usage fees, management fees Margin on management fees; payments passed through in full Subcontract price margin
Identification basis Article 1(1) of Fa Shi [2020] No. 25; Article 26 of the Construction Law Jian Shi Gui [2019] No. 1, Article 9 (definition of qualification borrowing) and Article 10 (list of scenarios, item (2) expressly covering a higher grade borrowing a lower one); Article 3 of Fa Shi [2026] No. 12 Jian Shi Gui [2019] No. 1, Article 7 (definition), Article 8 (nine scenarios, incl. no principal management personnel posted, principal materials procured by others, no payment flows between the contracting parties) Jian Shi Gui [2019] No. 1, Article 11 (definition), Article 12 (six scenarios, incl. subcontracting to individuals, to unqualified units, the general contractor subcontracting the main structure (steel structure excepted), re-subcontracting specialist works, re-subcontracting labour, specialist-work contractors charging for principal materials, large and medium plant and main consumables)

Key point: the divide between qualification borrowing and contract transfer lies in 'whose name + who was involved at the undertaking stage' - borrowing runs under another's name from bidding / contracting onwards; transfer means the contractor first obtains the works and only then hands it over wholesale (or pieced out). The transfer scenarios listed in Article 8 of Jian Shi Gui [2019] No. 1 carry a reverse exit: 'unless evidence proves qualification borrowing or another unlawful act' - facts formally fitting the transfer elements but proven to be borrowing are characterised as borrowing.

Scope Limits

  1. Reach of the cure exception: Article 4 of Fa Shi [2020] No. 25 covers only the scenario of a contractor signing beyond the scope permitted by its qualification grade, and is conditional on obtaining the corresponding grade before completion; lacking qualification, borrowing another's qualification, skipping mandatory tendering, transfer and unlawful subcontracting are all outside the cure. What is cured is the validity assessment, not the administrative handling of the violations already committed.
  2. The 'before completion' point: the grade must be obtained before the works are completed (pass acceptance); fix it by the qualification certificate issue time and the completion acceptance time. Obtaining it between signing and completion is still a cure; obtaining it after completion does not qualify.
  3. Versions and temporal boundary: Fa Shi [2020] No. 25 (Interpretation I) and Fa Shi [2026] No. 12 (Interpretation II, adopted at the 1969th meeting of the adjudication committee on 17 March 2026, published 29 June 2026, effective 30 June 2026) run in parallel; under its Article 23, first-instance construction contract dispute cases newly accepted after it takes effect apply this interpretation, and where earlier interpretations of the Supreme People's Court conflict with it after it takes effect, this interpretation prevails - old cases by the old rules, new cases by the new interpretation.
  4. Reference-based compensation presupposes acceptable quality of the works (or acceptable after rectification); works failing even after rectification bar the contractor's claim to reference-based compensation.
  5. Civil invalidity, administrative liability and joint compensation liability run in parallel; none is waived by the invalidity of the contract.

Further Reading

  • Validity: Article 1 and Article 4 of Fa Shi [2020] No. 25; Article 153 and Article 791 of the Civil Code; Article 26 of the Construction Law.
  • Consequences and settlement: Articles 7, 24 and 43 of Fa Shi [2020] No. 25; Article 793 of the Civil Code; Articles 3, 4, 6, 7, 11 and 23 of Fa Shi [2026] No. 12.
  • Identification of unlawful acts: Jian Shi Gui [2019] No. 1, Measures for the Identification and Investigation of Unlawful Conduct in the Award and Undertaking of Construction Works, Articles 7 to 12.
  • Administrative penalties: Regulation on Quality Management of Construction Projects (State Council Order No. 714, 2019 revision), Article 60.
  • Official text (release page of Fa Shi [2026] No. 12, Interpretation II): https://www.court.gov.cn/fabu/xiangqing/504221.html

Keywords

  • 超越资质等级
  • 借用资质
  • 挂靠
  • 合同无效
  • 竣工前取得资质
  • 折价补偿
  • 转包违法分包